Random freezes, missing sound and display glitches usually trace back to one bad driver. Find and replace yours safely.Free scan · under a minutePlanning permission and building control approval are separate processes. A delay in one does not satisfy the other, and neither deadline means you can safely start work without the required approval. This guide explains the England process, the checks to make immediately, and the formal escalation routes when a decision is late.
First confirm which approval is delayed, when a valid application was received, whether the authority has requested information or agreed an extension in writing, and what decision date it now expects. Keep a dated record of every submission, call, email and agreement. The rules below are for England; building-regulation procedures differ in Scotland and Northern Ireland, and equivalent Welsh rules are not covered here.
As an Amazon Associate I earn from qualifying purchases.
Planning permission and building control: two different approvals
Planning permission deals with whether a proposed development is acceptable in its location: for example, its use, scale, appearance, access and effect on neighbours. The decision-maker is normally your local planning authority (LPA).
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Building control approval deals with whether the design and construction comply with Building Regulations, including structural safety, fire safety, energy performance, drainage and access. For ordinary, non-higher-risk work in England, the route may be through your local council or a registered building control approver. Higher-risk building work generally follows the Building Safety Regulator (BSR) route.
#1 Best Overall
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
You may need both approvals. A planning delay does not extend a building-control deadline, and a building-control approval does not grant planning permission. Keep separate files, reference numbers and contacts for each application.
What to do in the first 24 hours
- Identify the decision-maker. Contact the LPA for planning. Contact the council building control service or registered building control approver for ordinary building work. Check whether the project is higher-risk and therefore within the BSR framework.
- Confirm validity and receipt. Ask when the authority accepted a complete, valid application. An early draft, an incomplete form or an unpaid fee may not start the statutory clock.
- Check the application type. Planning periods depend on whether the case is non-major, major or subject to environmental impact assessment (EIA). Building control periods depend on the route, such as full plans.
- Read every message. Look for requests for drawings, reports, fees, ownership certificates, consultation information or clarifications. Check for a written extension agreement and its end date.
- Request a written status update. Ask what remains outstanding, whether consultations are complete and the date the authority currently expects to decide.
- Protect the programme. Do not mobilise contractors or start work solely because a deadline has passed. Re-sequence work that does not depend on the delayed approval and notify affected suppliers in writing.
Use a simple log with the date, person contacted, reference number, information supplied, promised action and next follow-up date. It provides an accurate chronology if you later need an appeal or formal complaint.
How long should an England planning application take?
The ordinary statutory periods described in the government’s planning guidance are measured from a valid application, unless a different period was agreed in writing. The applicable period depends on the classification of the application.
| Planning application | Usual period | Qualification |
|---|---|---|
| Non-major | 8 weeks | Period described in the cited planning appeals guidance; check the case classification and any written extension. GOV.UK appeals guidance |
| Major | 13 weeks | Ordinary period in the same guidance, subject to a written extension. GOV.UK appeals guidance |
| Application subject to environmental impact assessment | 16 weeks | Period stated in the guidance, unless another period was agreed in writing. GOV.UK appeals guidance |
These are procedural deadlines, not statistics about actual waiting times. A valid extension changes the date on which the application is technically overdue, so obtain the agreement and revised date in writing.
Rank #2
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Both tools are designed to fit into difficult to reach spaces
- Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
- Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
If your planning application is overdue
Ask the LPA for a firm decision date
Before escalating, ask the case officer or planning department to confirm the application’s validity, outstanding information, consultation position and expected committee or delegated decision date. Ask whether the authority considers an extension to be in force and request a copy or written confirmation. A realistic date may let you avoid the cost and uncertainty of an appeal.
Consider an appeal against non-determination
If the statutory or agreed period has expired without a decision, a qualifying applicant may appeal to the Planning Inspectorate on the ground of non-determination. This is a procedural route, not an automatic grant of permission. The inspector considers the planning merits and the evidence; an appeal can still be dismissed.
Check the application date before using the online guidance. The Planning Inspectorate has a separate procedural guide for applications dated on or after 1 April 2026: 2026 planning appeals guide. Applications dated on or before 31 March 2026 follow the earlier guide: Procedural Guide: Planning appeals – England.
Appeal time limits vary by application type and circumstances. Confirm the limit on the official page before filing: How long you have to appeal. Householder cases and other categories can have different periods, and enforcement action can shorten the available time. The Planning Inspectorate’s overview explains the process and submission requirements: Appeal against a planning decision: Overview.
Rank #3
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
Balance an appeal against waiting
- Proceeding to appeal: creates a formal timetable and avoids an indefinite wait, but requires a complete statement of case and may involve fees or professional costs. Permission is not guaranteed.
- Allowing a short further period: may produce a quicker local decision if the officer has identified a near-term committee date, but obtain that commitment in writing and set a review date.
- Withdrawing and resubmitting: can be appropriate only after professional advice. It may lose the original submission date, require new fees and restart consultations.
Do not assume that missing the deadline means the proposal is approved. The guidance describes a right to appeal and, in specified circumstances, a fee refund under the planning guarantee policy, not automatic permission.
What the planning guarantee does—and does not—do
The planning guarantee is government policy rather than a replacement for statutory deadlines. The cited guidance describes a guarantee of no more than one year to a decision, including decision-making stages such as an appeal. It identifies 26 weeks for major applications and 16 weeks for non-major applications where no extended period has been agreed. These figures are policy benchmarks, not an entitlement to permission or a promise that every application will be decided within that time.
The policy also describes circumstances in which a fee may be refunded after the relevant guarantee period if no appeal was made. Check the current wording and your application’s classification in Determining a planning application before relying on a refund.
Quick wins for a faster PC:
Clear out junk files and repair common Windows errorsFree Scan →Scan for outdated or missing drivers - takes under a minuteDriver Scan →Building control delays in England
Full-plans applications: the five-week period
For a full-plans building control application, the decision period is five weeks unless you agree a longer period in writing. GOV.UK summarises the expectation as a decision within five weeks, or two months with your consent, for the full-plans route: Building regulations approval: How to apply. The Building Regulations 2010, as amended, provide the legal framework; see the England provisions retrieved on 1 July 2026 at Part 3 and the current body at the legislation page.
Rank #4
- Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
- Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
- Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
- Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
- Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed
Silence is not deemed approval or rejection. When the five weeks expires, contact the building control body and ask it to confirm the date received, whether the application is complete, whether plans or calculations are outstanding, whether an extension was agreed, and the date it will issue its decision.
Do not confuse a delay with a refusal
A delayed application and a formal rejection have different remedies. If the local authority rejects certain full-plans applications, the Regulations provide a 21-relevant-day appeal period in specified circumstances. The precise trigger and route depend on the decision, so check the legislation and obtain confirmation before relying on that limit. The Building Safety Regulator’s guidance lists appeal routes for certain building-regulation decisions: Building regulations approval: Appeals.
Higher-risk building work
Higher-risk building applications use a separate BSR process rather than the ordinary local-authority route. For prescribed higher-risk applications, a missed statutory decision period may allow a non-determination application to the Secretary of State if the required conditions are met. The procedure and eligibility are set out in Non-determination applications for higher-risk buildings procedures: applying to the Secretary of State.
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Check that the application type is covered, that the statutory period has actually expired and that no written extension was agreed. Once the Secretary of State referral process has been initiated, it cannot be paused simply to return the case to the regulator for an agreed extension. Because the consequences are significant, obtain specialist building-regulations advice before filing.
Best Value
- Milwaukee Ink all Fine Point Marker, Black, 4 Per Pack
- 4 per pack Features Clog Resistant Marker Tip Writes through Dusty, Wet and Oily Surfaces Durable Marker Tip for Writing on Concrete, OSB and Rough Surfaces
- Clog resistant tip writes on dusty, wet and oily surfaces and is optimized for rough surfaces such as OSB, cinderblock and concrete
- Hard hat clip- attaches for easy access
- Quick dry time with reduced smearing and marking
Choosing the next action
| Your situation | Immediate route | What to verify |
|---|---|---|
| Planning application still within its statutory or agreed period | Ask the LPA for status and a decision date | Validity, classification, consultation responses, outstanding information and written extension. |
| Planning application past its deadline | Assess a non-determination appeal | Application date, appeal time limit, procedure, planning merits, cost and whether a short local delay is acceptable. |
| Ordinary, non-higher-risk building work | Contact the council or registered building control approver | Application route, date received, completeness, written extension, inspection scope and decision date. The available sources do not establish that either route is always faster. |
| Higher-risk building work | Use the BSR process and check the prescribed non-determination route | Whether the application is covered, the statutory deadline, any extension and the Secretary of State procedure. |
Keep the construction programme moving safely
Separate activities that require approval from preparatory work that does not create an unlawful commitment. You can review procurement, update a risk register, refine sequencing and prepare information for the authority, but do not begin regulated construction on the assumption that approval will arrive later. Ask your designer, contractor and insurer how a change in sequence affects warranties, preliminaries, temporary works and payment milestones.
Update the programme with three dates: the statutory or agreed decision date, the authority’s latest forecast and the date by which the project must decide whether to escalate. Record the cost of each week of delay separately from the cause you currently suspect; correspondence should establish facts rather than accuse the authority of a particular failure without evidence.
When professional help is worthwhile
A planning consultant or architect can help check validity, respond to technical requests, assess planning merits and prepare a non-determination appeal. A registered building control approver or building-regulations professional can clarify the correct application route, resolve plan queries and explain inspection requirements. These are optional professional services: no service provider can guarantee that an authority will decide faster, and the available guidance does not establish any standard fee or guaranteed acceleration.
Seek specialist advice promptly where the project is commercially time-critical, the application involves an EIA, the appeal deadline is close, the work may be higher-risk, or a refusal has been issued rather than a decision simply being late.
Common mistakes that make delays worse
- Counting from the date an incomplete draft was uploaded instead of the date a valid application was received.
- Assuming a case is non-major, full plans or non-higher-risk without confirming its classification.
- Relying on a telephone promise instead of obtaining an extension or decision date in writing.
- Treating planning and building control correspondence as one approval file.
- Starting work because the authority has not responded. Missed deadlines do not create automatic planning permission or building-control approval.
- Filing an appeal without checking the application-date guide and the category-specific time limit.
- Assuming a private approver or council route is invariably quicker; the published material does not support that blanket claim.
Bottom line
Confirm the valid receipt date, application category and any written extension; ask the correct authority for a documented status and decision date; then escalate only through the route that matches the approval. In England, an overdue planning application may support a non-determination appeal, while a full-plans building-control application is not approved by silence. Higher-risk building work follows a separate BSR procedure, so verify the route before taking action.