Nepal has approved a temporary special price-adjustment process for public construction contracts facing abnormal cost increases linked to international conflict and resulting supply-chain disruption, according to reports published by OnlineKhabar on October 13, 2026, and Ratopati on October 12, 2026. The mechanism is conditional: contractors must apply to the relevant public entity, document actual costs and quantities, and show that existing contract-adjustment provisions do not adequately protect project continuity.
The reports describe a price-increase trigger above 10 percent, a reported ceiling of 25 percent of the original contract amount, and a 45-day examination period for the public entity. Because the government procedure and annex were not independently available for review, these details should be treated as reported provisions until the official text is checked.
As an Amazon Associate I earn from qualifying purchases.
What the new mechanism does
The reported Special Price Adjustment Procedure—called the “Special Price Adjustment Procedure 2026” in OnlineKhabar’s English report and “Special Price Adjustment Procedure, 2083” by Ratopati—targets contracts whose ordinary price-adjustment clauses do not adequately reflect exceptional increases in construction inputs. Covered cost categories are reported to include materials, labour, fuel, equipment and transportation.
Relief is not automatic. A contractor must submit a supported application, and the public entity must verify the circumstances, quantities and prices before deciding whether a special adjustment is necessary to keep the project moving in the public interest.
#1 Best Overall
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
Ratopati reports that the Council of Ministers approved the procedure under Section 74 “A” of Nepal’s Public Procurement Act, 2063. That legal basis and the procedure’s exact wording should be confirmed against the government instrument before being relied on in a dispute or claim.
Who may qualify
OnlineKhabar reports that the process is aimed at contracts meeting all of the following reported conditions:
Rank #2
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Compact and Lightweight: Both tools are designed to fit into difficult to reach spaces. The 1/4" impact driver has a length of 5.55 in. and weighs just 2.8 lbs, while the 1/2" drill/driver measures only 7.5 in. and weighs 3.6 lbs
- Both the DEWALT impact driver and electric drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
- Power drill cordless with 1/2" single sleeve ratcheting chuck provides tight bit gripping strength, making bit changes faster and more secure
- The tender was invited before the disruption caused by international conflict began.
- The contract was signed and work had started before that disruption.
- The contract period or defect-liability period continued beyond the disruption’s start.
- The exceptional circumstances have been verified.
- The existing price-adjustment arrangement is absent or inadequate, and a special adjustment is necessary for project continuation and public interest.
These conditions do not establish eligibility for any particular contract. The relevant disruption date, the contract’s clauses and the official procedure must be checked together.
Do these 3 things before closing this tab:
1Repair Windows errors before they cause bigger problems2Scan for outdated or missing drivers - takes under a minute3Clear out junk files and repair common Windows errorsReported threshold, deductions and cap
| Element | Reported rule | Important qualification |
|---|---|---|
| Price trigger | Increase greater than 10 percent from the price at the start of the disruption | Reported by OnlineKhabar and Ratopati in 2026; this is a procedural threshold, not an independent economic statistic. |
| Initial deduction | The first 10 percent of the increase is excluded from the special calculation | The official calculation method should be checked. |
| Overall ceiling | Special adjustment may not exceed 25 percent of the original contract amount | Reported cap; it is not a guarantee that a contractor will receive that amount. |
| Existing adjustment | Amounts payable under an existing legal or contractual adjustment provision are deducted | Only a remaining eligible amount may be paid as a special adjustment. |
| Application deadline | One month from publication of the relevant ministry’s price-adjustment notice | Reported by OnlineKhabar; the notice and its publication date determine the actual deadline. |
Ratopati describes a calculation based on the difference between the base rate at the start of the war and the prevailing rate 30 days before application, multiplied by the actual quantity consumed. That formula is a news-report description, not a substitute for the procedure’s annex; contractors should not use it for a claim until the official text confirms the reference dates, inputs and rounding rules.
Rank #3
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
What contractors must submit
The reports indicate that an application should explain why the contract’s existing adjustment mechanism cannot absorb the abnormal increase and should include evidence that ties the claimed cost to work actually performed.
- Prices for the construction materials or other inputs claimed.
- Actual quantities consumed on the project.
- Purchase invoices and, where available, delivery records, supply agreements or comparable procurement evidence.
- A project-progress statement showing the position as of the application date.
- The contract and relevant price-adjustment provisions, so the agency can calculate any amount already payable under them.
Organising records by input, supplier, date, quantity and project activity can make verification easier. Record-keeping software may be used as an optional administrative aid, but no particular product is required or endorsed by the government.
Rank #4
- Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
- Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
- Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
- Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
- Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed
How the public entity is expected to decide
- Receive the application. The contractor files it with the public entity responsible for the contract, within the reported one-month window after the ministry notice.
- Check the contractual position. The entity determines whether an existing adjustment or compensation clause already covers the increase.
- Verify prices and quantities. Agencies may compare submitted prices with procurement evidence, approved norms and standards, and the actual quantities used.
- Inspect the project if necessary. The reports say site inspections and price checks may be carried out.
- Determine the claim. OnlineKhabar and Ratopati report a 45-day period for examination and determination.
- Record and report the result. Higher-level authorities are to be notified and consolidated records maintained, with safeguards against duplicate benefits and payment of unverified adjustments.
Contracts and payments reportedly excluded
OnlineKhabar says a contract is excluded if compensation has already been imposed. It also reports exclusion where a separate exceptional-cost provision applies and the contractor has received, or is entitled to receive, compensation under that provision. The same cost increase should not produce duplicate payment through overlapping mechanisms.
How long the procedure lasts
Ratopati describes the process as temporary. It reports that the infrastructure ministry will stop adjustment work under it one month after publishing an official notice that the international-war and supply-disruption situation has ended. The notice, the end date and the precise transition rules were not established in the published reports, so contractors should monitor the responsible ministry rather than assume the mechanism remains open indefinitely.
Best Value
- Milwaukee Ink all Fine Point Marker, Black, 4 Per Pack
- 4 per pack Features Clog Resistant Marker Tip Writes through Dusty, Wet and Oily Surfaces Durable Marker Tip for Writing on Concrete, OSB and Rough Surfaces
- Clog resistant tip writes on dusty, wet and oily surfaces and is optimized for rough surfaces such as OSB, cinderblock and concrete
- Hard hat clip- attaches for easy access
- Quick dry time with reduced smearing and marking
Practical checks before filing
- Confirm when the tender was invited, when the contract was signed, when work began and when the contract or defect-liability period ends.
- Identify the disruption date used by the official procedure, rather than selecting a convenient market-price date.
- Separate costs already recoverable under the contract from the exceptional amount being requested.
- Reconcile invoices and delivery records with site quantities and approved work norms.
- Calculate the filing deadline from the ministry’s actual notice publication date.
- Keep copies of the complete submission and evidence of delivery to the public entity.
What remains to be confirmed
The government’s official procedure and annex are needed to confirm the formal title, commencement and disruption dates, the precise threshold and cap mathematics, the calculation formula, exclusions, application window and termination-notice mechanism. Until those documents are available, the provisions above should be described as reported by OnlineKhabar and Ratopati, not as a definitive legal interpretation.