October DealsAmazon USOctober deal check: compare before you payAmazon US: current deals, useful picks and tech finds.Check DealsClean PCRecommendedOne scan can reveal what keeps slowing WindowsLook for cleanup and repair opportunities.Run ScanOctober DealsAmazon USDeal season is back - check today's better picksAmazon US: current deals, useful picks and tech finds.See Picks×
Skip to content
Bettesworth Construction
building safety

Essendi v London Property Co: Why Contractors Should Take Notice

The Essendi cladding ruling allocated remediation duties under a particular commercial lease, not contractor liability in general. Its practical lesson is to document façade design, materials, warnings and contractual responsibilities.

By Bettesworth Construction Team 4 min read

What’s actually slowing this PC down?

Pick the symptom - the matching free tool is one click away.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

In Essendi UK Hotels 2 Ltd v London Property Company Ltd [2026] EWHC 1354 (TCC), the court held the landlord responsible under the current commercial lease for removing and replacing dangerous ACM cladding at an Ibis hotel. The decision is relevant to contractors because it shows how safety-critical design and installation decisions can surface years later in a dispute. It is not a ruling that the contractors involved, or contractors generally, were liable.

What did the court decide?

On 5 June 2026, HHJ Stephen Davies, sitting as a High Court Judge in the Technology and Construction Court, found the landlord in breach of the current lease’s covenants concerning the building’s condition and compliance with legal obligations. The reported outcome required removal and replacement of the Category 3 aluminium composite material (ACM) cladding.

The judge described the principal issue as “who, if anyone, is responsible for undertaking major building safety works to remove external cladding” from the hotel. In the evidence recorded in the judgment, fire-safety experts for both parties agreed that the panels presented an “intolerable risk” of fire and needed to be removed. That is the experts’ characterization as reported by the judge, not a general finding about every ACM façade.

The decision allocated responsibility between landlord and tenant under this lease, on the wording and evidence before the court. It did not establish that historic contractors were liable for the cladding or that a landlord must always bear remediation costs.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What was the cladding risk at the Wembley hotel?

The dispute concerned the purpose-built Ibis London Wembley hotel, a 16-storey building standing 42.5 metres high, with 210 bedrooms. Those are case facts stated in the judgment, not industry-wide statistics. The external façade included ACM panels with a highly combustible polyethylene core. Post-Grenfell testing had placed the material in Category 3, which the judgment describes as highly combustible.

The parties’ case history records a series of investigations after Essendi raised concerns:

  • An invasive survey and architectural report identified ACM panels and found no evidence of cavity barriers in three of the four surveyed locations.
  • A fire specialist reported that the cladding core had no flame-retardant properties.
  • A detailed fire-engineering assessment classified the material as Category 3 and advised removal and replacement.

These were steps taken in this dispute, not a universal inspection protocol. A visual check alone cannot be treated as resolving a technical fire-safety question.

Why did the lease history matter?

The court’s answer turned on the relevant covenants in the current lease and the circumstances of this building. The indexed judgment text also records arguments about the tenant’s role in commissioning replacement cladding in 2005 and bespoke remedial and indemnity provisions in an earlier lease. The court considered whether the later-identified, latent fire-safety risk fell within those earlier provisions.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Rank #3

That history matters because an earlier project, an old indemnity, or a party’s involvement in selecting or replacing façade materials does not by itself answer who must undertake later remediation. The actual contract wording, when the risk became known, the parties’ responsibilities, and the evidence all matter. The reported result should therefore not be reduced to a general rule about cladding products or responsibility for façade defects.

What should contractors take from the decision?

For contractors, the practical lesson is to preserve an accurate record of decisions and responsibilities on safety-critical façade work. Cladding can remain in place long after the original design and installation team has moved on; records may become important if a hazard is discovered later and parties dispute who controlled a decision or accepted an obligation.

Keep the technical and project record

  • Retain product specifications, fire-performance documentation, submittals, approved substitutions, design approvals and installation records.
  • Keep inspection reports, handover documents, notices, warnings and records of assumptions or limitations communicated during the work.
  • Record who selected materials, who held design responsibility, who reviewed or accepted the design, and what remedial obligations—if any—survive handover.

Make responsibility explicit in the contract

Check the scope of work, design responsibility, warranties, notice requirements, inspection duties, remedial provisions and insurance arrangements. Distinguish the respective roles of the landlord, tenant, building owner, designer, main contractor, specialist subcontractor and fire-risk assessor. A lease allocates duties between its parties; it does not, without more, establish a contractor’s obligations under a separate works contract or warranty.

Escalate a potential safety issue appropriately

If a façade concern is raised, document the investigation, the information available and the decision trail, and obtain advice from appropriately qualified professionals. Do not assume that a generic visual inspection, a proposed mitigation measure or the presence of a particular product label settles whether the building is safe or whether legal obligations have been met. The Wembley dispute involved expert assessments and a finding that the cladding needed removal and replacement.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

When reviewing a project or a later dispute, focus on the actual wording of the relevant lease or works contract, who controlled design and material selection, the timing and knowledge relevant to any latent defect, the duties to inspect or notify, and the evidence supporting the risk assessment. Take legal, technical and insurance advice appropriate to the project rather than treating this lease decision as a substitute for it.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

What changed in the October 2026 procedural ruling?

In a separate ruling handed down on 2 October 2026, Essendi UK Hotels 2 Ltd v London Property Company Ltd [2026] EWHC 2501 (TCC), HHJ Davies considered whether the trial judge could be told the date of the defendant’s earliest Part 36 offer after the claimant had substantially succeeded at the preliminary-issues trial. He concluded that the date could be disclosed under CPR 36.16.

This was a procedural decision about disclosure of the offer date. It did not determine the amount or allocation of costs, and it did not change the substantive cladding decision.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

More from the Site Office

Recommended PC Tool
Recommended PC Tool
Outdated Drivers Are Slowing You DownFree scan - exact matches
Windows Errors? Fix Them Before They SpreadFree repair scan

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.