In England, you generally need Building Safety Regulator (BSR) Gateway 2 approval before starting work to construct a higher-risk building (HRB), change an existing building so that it becomes or ceases to be an HRB, or carry out building work on an existing HRB. The first step is to check whether the building meets the HRB test; the second is to check whether the particular work is covered by an exception. A pending or validated application is not approval, and work requiring approval must not start while the application is being assessed.
First check whether the building is higher-risk
For the building-control Gateway 2 process in England, a building is an HRB if it meets the height or storey threshold and the relevant use test:
As an Amazon Associate I earn from qualifying purchases.
- It is at least 18 metres high or has at least 7 storeys; and
- It contains at least 2 residential units, or it is a hospital or care home.
The height/storey condition and the use condition work together. A building does not qualify just because it is at least 18 metres high or has 7 storeys; its use must also meet the second part of the test. Conversely, a residential building with 2 or more units does not meet this HRB test for Gateway 2 unless it also reaches the height or storey threshold.
Quick wins for a faster PC:
Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →The test is specific to England’s higher-risk building control regime. If the building does not meet it, do not assume that Gateway 2 is the right route: non-HRB building control is handled separately, through the local authority or a registered building control approver as applicable.
#1 Best Overall
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
Residential HRBs with at least 2 units must also be registered with the BSR before occupation. Registration is a separate requirement from obtaining Gateway 2 approval for building work.
Which projects need Gateway 2 approval?
The BSR is the building control authority for higher-risk building work in England. Its review considers whether the proposed work complies with building regulations, whether the client will manage the project properly, and whether the people appointed to carry out relevant work are competent.
Subject to the specific exceptions below, the approval requirement covers these three situations:
1. Constructing a new higher-risk building
A project to build a new HRB needs approval before construction starts. This includes a new building that meets the height or storey and use tests, and can include a conversion that results in a new HRB.
2. Work that changes a building’s HRB status
Approval is required before work to an existing building that will make it an HRB, or before work that will stop an existing building being an HRB. The trigger is the effect of the work on the building’s status, not simply whether the project is described as a new build or a refurbishment.
Rank #2
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Compact and Lightweight: Both tools are designed to fit into difficult to reach spaces. The 1/4" impact driver has a length of 5.55 in. and weighs just 2.8 lbs, while the 1/2" drill/driver measures only 7.5 in. and weighs 3.6 lbs
- Both the DEWALT impact driver and electric drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
- Power drill cordless with 1/2" single sleeve ratcheting chuck provides tight bit gripping strength, making bit changes faster and more secure
3. Building work to an existing HRB
Building work to an existing HRB generally needs approval before it begins, unless the work falls within a specified exception. That can include work on a registered high-rise residential building or work involving connected HRBs. Where the scope is complicated, such as work spanning connected buildings or several work types, professional help may be useful in deciding how to apply.
A project can involve both higher-risk and non-higher-risk buildings. Normally, the BSR controls the HRB work while the local authority or a registered building control approver controls the other buildings. The BSR may agree to control both in limited circumstances, but applicants should not assume this will happen automatically.
Crashes, No Sound, or Screen Glitches?
Random freezes, missing sound and display glitches usually trace back to one bad driver. Find and replace yours safely.Free scan · under a minutePC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11What work may be exempt?
Exceptions are limited to specified work and circumstances. Do not treat an entire refurbishment as exempt just because it includes repairs or maintenance: an exception may cover only a particular component, while the wider project still needs an application.
Specified exempt work
The official list includes most repairs, replacements and maintenance, but it has exceptions. Examples included in the guidance are:
- Some electrical work.
- Replacement baths, toilets, basins and sinks.
- Insulation in roof spaces or under timber floors.
- Certain hot water systems under 15 litres.
- Gutters and downpipes.
- External doors with less than 50% of their surface glazed.
The guidance identifies heating systems, oil tanks, fuse boxes and glazing units among the exceptions to the broad category of most repairs, replacements and maintenance. Check the detailed official list against the exact work and item involved; a general description such as “repair” or “like-for-like replacement” is not enough to establish an exemption.
Rank #3
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
Competent-person-scheme work
Work carried out under a competent person scheme does not need its own Gateway 2 approval. Ask the scheme provider whether its scheme covers the specific work being done in an HRB. If exempt or scheme work is part of a wider building project that needs an application, include that work in the project application rather than treating the whole project as exempt.
Qualifying fibre-optic cabling
Qualifying fibre-optic cabling work in an existing HRB is an exception to the usual application requirement. It has a separate notification requirement after completion, so exemption from an application does not mean there is no process to follow. The BSR guidance records a change concerning this work on 22 September 2026; check the current requirements for the particular cabling work.
Emergency repairs
Emergency repair is another specified exception. It should not be stretched to cover routine, planned work simply because delaying it would be inconvenient. If the situation is not clearly an emergency, check the applicable guidance before proceeding.
How to decide whether your project needs approval
Use the sequence below before appointing the application route or setting a start date. It helps separate the building test, the work trigger, and any possible exception.
- Confirm the building’s location and use. This Gateway 2 test applies in England. Establish whether the building contains at least 2 residential units or is a hospital or care home.
- Check height and storeys. Establish whether it is at least 18 metres high or has at least 7 storeys. The use and height/storey parts of the test must both be met.
- Describe what the work will do. Identify whether it constructs a new HRB, changes an existing building so that it becomes or stops being an HRB, or is building work to an existing HRB.
- Check each claimed exception against the exact work. Confirm whether a listed exemption, competent-person scheme, qualifying fibre-optic cabling rule, or emergency-repair exception applies. Do not assume that an exception for one component covers the rest of the project.
- Check transitional arrangements if work began before BSR became the building control authority. Separate guidance covers new HRBs and work on existing HRBs. The applicable route depends on the individual case.
- Identify the correct building-control authority for each building. For a mixed project, the HRB and non-HRB portions may have different control routes. Do not submit an ordinary non-HRB project through Gateway 2 solely because it is part of a wider development.
- Do not set work in motion before the required approval. If an application is staged, each stage needs approval before work on that stage begins.
If a resident or client is uncertain about a complex existing-building project—for example, work in a registered high-rise residential building, work spanning connected HRBs, or a package combining different work types—the BSR guidance advises considering professional help. For existing HRBs, first check whether an application is needed and whether the work falls into Category A or Category B. Selecting the wrong category can result in rejection.
Rank #4
- Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
- Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
- Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
- Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
- Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed
Who must apply, and can applications be staged?
The client is responsible for ensuring that required approval is obtained before work starts and that the application information is correct. The client may authorize another person to submit and manage the application, but delegating the task does not transfer the client’s legal responsibility.
For a new building, an application may cover one tower or multiple connected towers that share a podium or common part. A staged application may also be possible. The BSR considers staged applications case by case, and applicants are advised to contact the BSR before submitting a staged application for a multiple-tower project.
Staging does not allow work to start ahead of a decision: the application for each stage must be approved before that stage begins. Similarly, a validated application is not an approved application. Validation confirms a process step, not permission to start building work.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.How long does Gateway 2 approval take?
The official guidance gives assessment periods of up to 12 weeks for new HRBs and up to 8 weeks for existing HRBs, unless an extension is agreed. These are stated assessment periods, not guaranteed individual decision dates. The BSR says timing depends on the quality and complexity of the application.
Actual operational times reported by the BSR for July to September 2026 were longer than those stated assessment periods:
Best Value
- Milwaukee Ink all Fine Point Marker, Black, 4 Per Pack
- 4 per pack Features Clog Resistant Marker Tip Writes through Dusty, Wet and Oily Surfaces Durable Marker Tip for Writing on Concrete, OSB and Rough Surfaces
- Clog resistant tip writes on dusty, wet and oily surfaces and is optimized for rough surfaces such as OSB, cinderblock and concrete
- Hard hat clip- attaches for easy access
- Quick dry time with reduced smearing and marking
| Application type | BSR median approval time, July–September 2026 | BSR approval rate, July–September 2026 |
|---|---|---|
| New higher-risk buildings and conversions | 23 weeks | 97% |
| External remediation | 32 weeks | 87% |
The BSR stated that the underlying data were correct on 5 October 2026. These are period-specific figures: they are not statutory deadlines, forecasts for an individual application, or a promise that a project will be approved. The same dataset noted a significant rise in applications ahead of the building safety levy taking effect on 1 October 2026, so the figures should not be assumed to describe a stable future trend.
For a project plan, distinguish the stated assessment period from the reported median and allow for the possibility of extensions and application-specific complexity. Neither figure changes the rule that approval must be in place before the relevant work starts.
What happens if you start without approval?
The BSR guidance states: “Carrying out building work without the required building control approval is a criminal offence.” The practical consequence is that a project should not treat an application in progress, validation, or an anticipated decision date as permission to begin work.
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →The client is responsible for ensuring the approval is obtained. This remains true even when another person is authorized to prepare or submit the application. For a staged project, approval must be secured before work on each stage begins; for a project with an exception, confirm that the exception actually covers the work being undertaken.
What if the approved design changes?
Once an application is approved, the documents submitted become the agreed documents for the project. Subsequent changes are controlled and fall into three categories: recordable, notifiable, or major. The category determines what must happen before or during the changed work.
- Recordable change: log the change in the project records.
- Notifiable change: submit it to the BSR before starting the related work.
- Major change: obtain BSR approval before proceeding with the affected work. That work must stop until approval is given.
Potential major changes include changes to a building’s height or width, number of storeys, escape routes, external walls, fire-safety measures, common-part layout, residential or commercial unit count, or structural design. These examples show why a seemingly narrow design amendment can affect the approved safety case or building-control documents.
Product substitutions also need screening through change control rather than an assumption that “same purpose” means “same specification.” A replacement product may be recordable if it is of the same or higher specification. A different reaction-to-fire specification may be notifiable even if it is higher, while a lower reaction-to-fire specification may be a major change. The classification depends on the change and the applicable rules.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Does a consultation change the current rules?
As of 13 October 2026, the core BSR guidance for this process was last updated on 1 October 2026. The Ministry of Housing, Communities and Local Government’s 2026 consultation concerns proposals about proportionality in the Gateway 2 regime, including work categorization and the role of competent-person schemes. It applies to England. Consultation proposals are not themselves a change to the current approval requirements; follow the rules in force unless and until a change takes effect.
Quick Recap