Maryland unveiled a preliminary design for the Francis Scott Key Bridge replacement on February 4, 2025. The planned crossing is more than two miles long, with a 1,665-foot cable-stayed main span and at least 230 feet of clearance above the federal navigation channel. It is still under construction: the state’s October 1, 2026 progress snapshot reported permanent supports 55% complete at the south tower and 26% at the north.
What Maryland unveiled—and what the design describes
The February 4, 2025 announcement presented a preliminary design concept for the replacement of the Francis Scott Key Bridge, which collapsed in March 2024. It was a design milestone, not a completed bridge or a final construction status report. Maryland said final design work and regulatory approvals would follow before construction. Maryland Governor’s Office, February 4, 2025
Subsequent procurement documents provide more specific dimensions than the initial unveiling. The Maryland Transportation Authority’s July 21, 2026 request for qualifications (RFQ) describes a cable-stayed main bridge and sets dimensions for the main span and marine approaches contract. The state’s broader description of the finished crossing is more than two miles long. Those figures refer to different scopes: the total crossing is not the same measurement as the contract’s main-span length.
| Measurement | What it describes | Specified value |
|---|---|---|
| Total crossing | Maryland’s description of the finished bridge in its October 2026 update | More than 2 miles |
| Main span | Cable-stayed span specified in the July 2026 RFQ | 1,665 feet |
| Main span and marine approaches contract | Total contract length specified in the July 2026 RFQ | 3,365 feet |
| Pylons | Elevation specified in the July 2026 RFQ | 602 feet |
| Navigation clearance | Minimum vertical clearance above the federal navigation channel in the July 2026 RFQ | 230 feet |
The RFQ also calls for about 660 feet of south approach over water and about 1,560 feet of north approach over water. These approach lengths are part of the main-span and marine-approaches contract. The contract includes a vessel collision protection system at the main pylon piers. Maryland Transportation Authority, July 21, 2026
The Tool Desk
Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →#1 Best Overall
- BUILD A REAL DA VINCI INSPIRED BRIDGE Construct a working model based on Leonardo da Vinci’s famous self-supporting bridge design. This hands-on wooden STEM kit demonstrates real engineering principles through an engaging and rewarding building experience.
- EDUCATIONAL STEM LEARNING EXPERIENCE Explore concepts in engineering, architecture, physics, and history while building. Great for students, hobbyists, makers, homeschool projects, classroom activities, and anyone interested in mechanical design.
- APPROXIMATELY 1 HOUR BUILD TIME Designed to provide an immersive yet manageable project experience. The completed bridge makes an impressive display piece and conversation starter once assembled.
- HIGH-QUALITY WOODEN MODEL KIT – AGE 14+
- Made from durable precision-cut wood components with detailed illustrated instructions. A thoughtful gift idea for teens, adults, engineers, history enthusiasts, and STEM lovers.
What “designed for a 100-year lifespan” means
A February 6, 2025 Maryland Department of Transportation blog search result described the bridge’s “expected life span” as 100 years. The page itself was not retrievable, and the current official project sources cited here do not independently restate the figure. It is therefore best understood as an agency-reported design expectation, not a guarantee that the bridge will last exactly a century or a published result of a durability test.
Construction progress as of October 2026
Maryland’s latest sourced progress snapshot in the state’s October 1, 2026 dashboard announcement, updated October 2, reports the following figures as of October 1:
Rank #2
- HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up
- NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs
- BROOKLYN BRIDGE – 2 Sheet Model with a moderate difficulty level. Once assembled, dimensions are 5.39"L x 0.91"W x 1.97"H (13.7 x 2.3 x 5 cm)
- FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions
- HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all
- Permanent supports: 55% complete at the south tower and 26% at the north tower.
- Temporary work platforms on both sides: 99% complete.
These are point-in-time construction progress measures; they do not establish a completion date. Maryland describes the dashboard as a monthly source for measurable construction progress, completed work, design and procurement milestones, and stakeholder outreach. Maryland Governor’s Office, October 1, 2026; updated October 2, 2026
Why the procurement plan changed
The original plan used a progressive design-build agreement. In August 2024, the Maryland Transportation Authority awarded Kiewit a Phase 1 contract, with exclusive rights to negotiate Phase 2 if the parties agreed on a guaranteed maximum price. The announcement anticipated the replacement opening in fall 2028 under that earlier plan. Maryland Department of Transportation, August 29, 2024
Recommended Free Tools
Rank #3
- HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up.
- NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs.
- PREMIUM SERIES BROOKLYN BRIDGE - 3 Sheet Model with a challenging difficulty level. Once assembled, dimensions are 10.40" L x 2.20 W x 2.20 H inches. 1:6861 Scale.
- FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions
- HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all.
That arrangement changed. On April 28, 2026, MDTA said Kiewit’s Phase 2 proposal exceeded the state’s independent cost estimates and that the authority would seek other contractors. Kiewit’s Phase 1 work, including foundation piles and a temporary trestle, continued. Maryland Transportation Authority, April 28, 2026
In July 2026, MDTA released an RFQ for a competitive, sealed, two-step process to select a design-build team for the main span and marine approaches—the largest of the project’s four contracts. This later procurement specification is the source for the dimensions listed above; it does not itself supply a current opening date or total project cost.
Rank #4
- This is a model of the arch bridge designed by Leonardo da Vinci
- The design uses a self-supporting arch concept to distribute weight through the full curve of the arch
- The kit is a replica of the oldest known arch bridge design
- Snap together assembly of textured parts
- No batteries, paint, or glue required
When will the replacement bridge open?
The fall 2028 date was an expectation announced in August 2024 under the earlier contracting plan. The official sources cited here do not establish a replacement opening date after the Phase 2 procurement changed. For dated construction and procurement updates, consult Maryland’s Key Bridge rebuild dashboard announcement.
Quick Recap
Best Value
- WHAT IS IT ? The Strauss Bascule Bridge is a multifaceted diy wooden bridge building model kit for kids. First, construct a working replica 3D puzzle bridge. Once assembled, children can enjoy hours of imaginative play with the wooden bridge toy. It's compatible with toy cars, toy trains, and figurines, adding endless creative play possibilities. Educational toys for kids 7+. An excellent way to introduce children to the principles of engineering and mechanics.
- HOW LONG DOES IT TAKE? The working wooden model building blocks set takes around 30-45 mins to assemble depending on the young builders model kit building experience. Hands on learning kids toy that makes science fun! A great stem project for kids 6-10
- WHO IS IT IDEAL FOR? Ideal gift for kids. 7+. Younger kids can also enjoy the toy but may need assistance building the bridge. Gift for kids ages 6 8 a rainy day activity for kids 7 years old a stem activity to do alone or as a family. A 3 d puzzle for kids model building kit. Makes a unique gift for a kid 6 7 8 . A great birthday present for girls age 6 8 8 10. Gift for boys 6 8. Science fair project idea or desk toy.
- WHAT DO I LEARN? Learn about levers, pullies, and the mechanical engineering behind the construction of bridges. This Stem kit includes great educational information and links to learn more about levers and bridges. Inspire your child's interest in science, technology, engineering, and mathematics with this exciting construction toy.
- Interactive Learning: The functional lift bridge is not only a fun project but also a practical demonstration of real-world engineering
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.