The James River Crossing earned ENR MidAtlantic’s 2026 Project of the Year by solving a difficult construction tradeoff: install a 5,700-foot section of 42-inch high-density polyethylene (HDPE) wastewater force main beneath an active shipping channel, while avoiding an additional marine work platform. The extended horizontal directional drilling (HDD) route reduced in-water work and reported project costs, but pushed the pipe pullback well beyond the length previously reported for pipe of this size and wall thickness.
What the James River Crossing does
The James River Crossing (JRX) is a subaqueous section of Hampton Roads Sanitation District’s wastewater transmission system in Newport News, Virginia. The wider system connects the Boat Harbor Pump Station to the Nansemond treatment facilities and the Sustainable Water Initiative for Tomorrow (SWIFT), the district’s water-replenishment program. The pipeline is designed to convey more than 45 million gallons of wastewater per day, according to the Design-Build Institute of America; that is reported capacity, not a measured daily flow. DBIA’s project award page describes the project’s capacity and purpose.
ENR named JRX its 2026 MidAtlantic Project of the Year and Best Project in the Water/Environment category. Brierley Associates also lists a 2025 No-Dig Show paper award from the North American Society for Trenchless Technology and a 2024 honorable mention from Trenchless Technology. ENR’s 2026 feature covers the project award; Brierley’s project page lists the additional recognition.
The delivery team included Garney as general contractor, Dewberry as lead designer, Brierley Associates for geotechnical and bore-path development, Huxted Trenchless for HDD work, and Seaward Marine for marine support. Garney’s project page and Brierley’s project page identify the project and its participants.
Quick wins for a faster PC:
Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →#1 Best Overall
- Build 20 different models that each teach about force, load, compression, tension and more
- Over 285 interchangeable building pieces
- Includes 36-page, illustrated experiment manual and Assembly guide
- Skill level: Intermediate
Why the HDD pullback was exceptional
The team installed 5,700 feet of 42-inch DR-11 HDPE beneath the Newport News Shipping Channel using HDD. Garney says the route reached more than 100 feet below the riverbed and describes the operation as the world’s longest-known pullback of 42-inch HDPE pipe. Brierley calls it a world record and the longest of its type in the United States. Those are source-attributed record claims, not an independently audited universal ranking. Garney’s project account and Brierley’s project page give their respective descriptions.
The reported pullback duration differs across coverage: ENR’s 2026 feature says 22 hours, while Garney reports 24 hours and ENR’s earlier milestone report says more than 24 hours. The installation therefore took about a day, but the sources do not give one consistent duration. ENR’s 2026 account, Garney’s project page, and ENR’s earlier milestone report use those different figures.
Rank #2
- BUILD A REAL DA VINCI INSPIRED BRIDGE Construct a working model based on Leonardo da Vinci’s famous self-supporting bridge design. This hands-on wooden STEM kit demonstrates real engineering principles through an engaging and rewarding building experience.
- EDUCATIONAL STEM LEARNING EXPERIENCE Explore concepts in engineering, architecture, physics, and history while building. Great for students, hobbyists, makers, homeschool projects, classroom activities, and anyone interested in mechanical design.
- APPROXIMATELY 1 HOUR BUILD TIME Designed to provide an immersive yet manageable project experience. The completed bridge makes an impressive display piece and conversation starter once assembled.
- HIGH-QUALITY WOODEN MODEL KIT – AGE 14+
- Made from durable precision-cut wood components with detailed illustrated instructions. A thoughtful gift idea for teens, adults, engineers, history enthusiasts, and STEM lovers.
Why the team chose a longer crossing
The initial concept used a shorter crossing and two marine platforms. One proposed platform location risked congestion near an oil depot and naval vessels. Extending the HDD alignment to shore removed the need for a second platform, reduced in-water work, and avoided interference with shipping and nearby operations.
That choice exchanged marine access demands for a longer and more demanding pullback. ENR reports the extension saved more than $10 million; Garney also reports savings exceeding $10 million and says the extension added 2,300 feet. ENR states that the previous known installation length for 42-inch HDPE at the specified wall thickness was roughly 4,000 feet, making JRX’s 5,700-foot run a substantial increase. These savings and record comparisons are reported project figures and claims, not independently audited industry benchmarks. ENR’s feature and Garney’s project page describe the alignment decision.
The Tool Desk
Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Rank #3
- 【DIY London Tower Bridge Model Kit】This 3D London Tower Bridge wooden puzzle with LED light is one of the iconic buildings in Britain, ancient and elegant. Assemble Size: 14.1x2.9x4.6in.
- 【Unique Gifts】This Tower Bridge construction model kit is the best gift for teens, friends, family members, architectural enthusiasts around the world or those who love handmade crafts on birthday, Christmas, or another occasion.
- 【English Instruction】This DIY model Tower Bridge Kit cut with exquisite laser technology and accompany english instruction, the matierial is environmentally friendly, non-toxic, 113 pcs easy to assemble, recommended for over 14 years old. Kids can also assemble with the help of adults.
- 【Fun Project】This 3D puzzles can greatly stimulate the spatial imagination of players, improve the graphics recognition ability, enhance the player's observation and hand-eye coordination ability, Three-dimensional Puzzles is also a very interactive activity for both children & adults
- 【Perfect Decoration】Our Big Ben model kit is good for Home decoration. It looks great to show on your table, bookshelf, add it in your collections or hang on the window, wherever you put, it makes your home more exquisite and vintage.
| Approach | Project-specific benefit | Tradeoff or constraint |
|---|---|---|
| Shorter crossing with two marine platforms | Less HDD length and a shorter pipe pullback. | Required a second platform in a constrained area near an oil depot and naval vessels, with added marine work and potential interference. |
| Extended HDD to shore | Eliminated the second platform, reduced in-water work, and avoided interference with shipping and nearby operations; ENR reports savings of more than $10 million. | Required a 5,700-foot pullback of 42-inch HDPE, increasing installation demands and the need to verify subsurface conditions, bore alignment, and pipe loading. |
These are the tradeoffs documented for JRX, not proof that HDD is the right answer for every water crossing. An HDD route depends on suitable ground, a workable bore path, access and staging at both ends, and the ability to manage pulling loads. A marine or open-cut approach presents different impacts and constraints; the project accounts establish the advantages of JRX’s chosen alignment, not a universal ranking of methods.
How the team managed the longer pullback
The design-build brief left the route and construction solution to the team. Garney vice president Jeff Seal described it this way: “Basically, they gave us a flow rate and they said that that it needed to be trenchless with an HDD,” says Jeff Seal, vice president at Garney. “They gave us two connecting points—one on either side—and for the rest of it, they said, ‘Figure it out.’” The team’s response combined investigation, equipment, pipe controls, and continuous coordination.
Rank #4
- HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up.
- NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs.
- PREMIUM SERIES GOLDEN GATE BRIDGE - 2.5 Sheet Model with a moderate difficulty level. Once assembled, dimensions are 14.45 L x 0.94 W x 2.95 H inches. 1:7535 Scale.
- FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions
- HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all.
- Checked the ground and alignment: The team performed supplemental geotechnical borings and a pilot drill to examine subsurface conditions and validate the alignment before committing to the pullback.
- Used a pipe pusher to reduce pulling demand: A custom pusher mounted on the marine work platform could apply up to 750,000 pounds of force, helping reduce net tensile stress on the HDPE during installation.
- Tightened the pipe ovality tolerance: ENR reports that the allowable ovality was reduced from 5% to 3%. ENR says the tighter tolerance improved installation performance and long-term integrity.
- Selected corrosion-resistant material: The under-channel section used 42-inch DR-11 HDPE, stepping up to 48-inch and 54-inch pipe elsewhere. ENR reports the larger diameters reduce pumping head and energy use. Dewberry’s Paul Longo explained the material choice: “They wanted to never have to go back in [to fix] it and the risk of a coating system failing is higher than the fact that HDPE is a full wall of corrosion resistant thermoplastics.”
- Designed for the bore conditions: Trenchless Technology describes soft soils, 66-inch conductor casings driven to approximately 100 feet, and a bottom drill elevation near 165 feet below the stated reference elevation. It reports that the bore geometry was designed to reduce inadvertent returns and loading on the HDPE. Trenchless Technology’s project report provides these technical details.
- Coordinated work crews continuously: Drilling, marine support, and pipe-handling crews had to work in sequence during the pullback, leaving little room for a handoff or timing breakdown.
ENR’s 2026 project feature describes the pusher, ovality tolerance, pipe sizes, and team decisions. Read ENR’s account for those reported details.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.What the project figures say about delivery
ENR reports a final construction cost of $139 million, $14 million below the original proposal price. It also reports approximately $2 million saved by avoiding privately leased oyster beds and approximately $1.8 million saved by revising shallow-water construction methods and avoiding articulated concrete mats. These are ENR-reported project figures, not independently audited totals. ENR’s 2026 feature gives the cost and savings figures.
Do these 3 things before closing this tab:
1Clear out junk files and repair common Windows errors2Scan for outdated or missing drivers - takes under a minute3Repair Windows errors before they cause bigger problemsBest Value
- The London Tower Bridge wood model kit consists of 113 wooden pieces and it takes 1.5-2 hours to put it together. It will be easy to build even if you are 3D puzzle beginner. If you have not experienced wooden 3D assembly products and have a little hesitate, you can use this product to practice and experience the fun of mortise and tenon craft.
- All you need comes in the package: 5 precious laser-cut plywood sheets, illustrated English instructions, and screwriver. This is an unfinished product, need to assemble yourself.
- With adorable design, this DIY model is a perfect desk display for you to build. A home decor for your home&office.
- It is also a cool gift for your family or friends on Christmas/Birthday/Valentine's Day.
- The 3D puzzle is a nice stress reliever and after finishing,you will have a true sense of accomplishment.
Together, the figures show that the long HDD was one part of a broader delivery strategy. The design team also changed shallow-water methods and avoided a potential oyster-bed lease, while the extended route reduced the need for marine infrastructure. The project’s recognition reflects both the scale of the crossing and the way the team balanced constructability, marine constraints, and reported cost.