Black Friday PreviewAmazon USBlack Friday preview: compare before the rush hitsAmazon US: current deals, useful picks and tech finds.Check DealsWindows FixRecommendedWindows errors stealing your time? Find the fix fastScan stability, cleanup and performance issues.Fix NowBlack Friday PreviewAmazon USThe best pick may show up before FridayAmazon US: current deals, useful picks and tech finds.See Picks×
BETTESWORTHConstruction
affordable housing

Samaritan House gives tour of reduced-cost apartments under construction in Kalispell

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Some links on this page are affiliate links: if you buy through them we may earn a commission, at no extra cost to you.

Samaritan House is building an 18-unit apartment complex in Kalispell, Montana, for families and low-income earners. The two- and three-bedroom homes are projected to open in late summer 2027, with reduced-cost eligibility set at 30% to 50% of Flathead County’s area median income (AMI). A tour on October 20, reported by the Daily Inter Lake on October 27, 2026, showed a project designed around family visibility, sound control, trauma-informed circulation and lower-energy operation.

What is Samaritan House building?

The Building Stability project is an 18-unit complex just off Second Street West and east of South Meridian Road in Kalispell. It will contain two- and three-bedroom apartments intended for households of roughly three to five people. Households with or without children may apply for the reduced-cost homes, and a couple of apartments are planned at market rates.

As an Amazon Associate I earn from qualifying purchases.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Rural Community Assistance Corporation is the developer, with Swank Enterprises responsible for construction. Shopworks Architecture and LSW Architects shaped the design after interviewing Samaritan House guests, residents and staff in 2022.

When are the apartments expected to open?

Samaritan House expects the apartments to be ready in late summer 2027. That is a projection rather than a guaranteed leasing date; the organization has not announced when applications will open, how units will be screened or who will handle leasing.

The project site is part of a broader campus expansion that is expected to nearly double Samaritan House’s capacity. Construction schedules, inspections, utility work and final occupancy approvals could affect the projected opening.

Who qualifies, and how much income is allowed?

Reduced-cost applicants must fall between 30% and 50% of area median income. Samaritan House and Flathead County gave an example of $33,000 for a family of four at the 30% AMI level. The organization said people it served in 2026 earned about $28,000 on average.

What’s actually slowing this PC down?

Pick the symptom - the matching free tool is one click away.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The available data does not state the exact 50% AMI dollar limit, proposed rents, utility allowances or screening criteria. Income limits can vary by household size, so prospective applicants should wait for Samaritan House’s formal eligibility guidance rather than apply the $33,000 example to every household.

What features were shown on the construction tour?

The interior plan emphasizes supervision, privacy and comfort for families who may have experienced trauma or housing instability.

Also popular on Amazon

Sound control between floors

Gypcrete flooring between levels is intended to reduce the transmission of noise. Samaritan House executive director Cassidy Kipp said visitors should note the soundproofing because “there’s gonna be a lot of children here.” Gypcrete is a concrete-like underlayment commonly used to add mass between floors; the project has not published an independent acoustic measurement.

Open sightlines with private bedrooms

Open living areas are arranged so parents can keep children in view while bedrooms remain separate. Kipp described it as “a very open floor plan” in which “the bedrooms are private, but still, parents can always have the kids in their sightlines.”

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Fall-risk and trauma-informed details

Window limiters are intended to reduce fall risk. Wide entryways and hallways are designed to feel less restrictive and more comfortable for residents who have experienced trauma. Each apartment is planned to include its own washer and dryer, eliminating the need for a shared laundry room.

How will the building handle energy and materials?

The complex is all-electric. Rock wool insulation will line the exposed exterior, and the roof is being designed so solar panels can be added later if funding becomes available.

Flathead Electric Cooperative and Bonneville Power Administration agreed to provide $200,000 in rebates and energy incentives in 2026. Project officials say some materials cost more at the start but should lower energy costs over time; that expectation is not an independently measured savings result.

During the tour, Kipp described the rock wool as porous but heavy, fire-resistant and unable to support mold growth. Those are characteristics of the specified insulation material; long-term performance will depend on installation, moisture control and building operation.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

How is the $11.4 million effort being funded?

HUD recently awarded Samaritan House $2.6 million. About $1.9 million is designated for construction, while $700,000 supports two years of rental assistance for nine households and resident services.

Funding element Amount Purpose
HUD award $2.6 million Combined construction, rental assistance and services
Construction share About $1.9 million Building work
Rental assistance and services $700,000 Two years for nine households plus resident services
Utility rebates and incentives $200,000 Flathead Electric Cooperative and Bonneville Power Administration, 2026

Samaritan House said it was one of 13 agencies nationwide to receive the HUD funding. The award moved its $11.4 million capital campaign from 83% funded to 94% funded.

Why is the Samaritan House shelter closed?

The emergency shelter has been closed for renovations since July 2026 while the campus work continues. Kipp said reopening before Thanksgiving was a hope, not a firm date, because crews still had to complete construction cleanup, reinstall furnishings and finish staffing. She said operations were on hold while flooring was being installed.

The apartment building and shelter renovation are related parts of the campus expansion, but an apartment opening should not be treated as a reopening date for emergency shelter services.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What should prospective applicants watch for?

  • A formal application announcement and leasing contact.
  • Published rents, utility policies and the exact AMI limits by household size.
  • Any preference or documentation rules for households receiving rental assistance.
  • Updated construction and occupancy timing as late summer 2027 approaches.

Until those details are released, the confirmed information is the planned unit count, bedroom mix, income band, design approach and funding structure—not a guaranteed move-in date or a complete application procedure.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Frequently Asked Questions

Have Samaritan House apartment rents been announced?

No. The project information available from the tour does not include a rent schedule, utility allowance or security-deposit amount. Those figures should be issued with the leasing and application notice.

Can a household without children apply for a reduced-cost unit?

Yes. Samaritan House says households with or without children may apply, subject to the project’s income limits and whatever screening rules are ultimately published.

Is there a confirmed application opening date?

No application date or leasing contact has been confirmed. People interested in the homes should monitor Samaritan House’s public announcements for the formal process rather than rely on the projected construction completion.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Will all 18 apartments receive rental assistance?

No. HUD’s $700,000 service component is designated for rental assistance for nine households over two years, so the award does not indicate that every apartment will have a subsidy.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply. Prices as of November 18, 2026 9:40 am GMT+0000.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Recommended PC Tool
Recommended PC Tool
Windows Errors? Fix Them Before They SpreadFree repair scan
Crashes, No Sound, or Screen Glitches?Free driver scan

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.