Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Some links on this page are affiliate links: if you buy through them we may earn a commission, at no extra cost to you.
Public and private construction contracts differ mainly in who controls procurement, which funding and labor rules attach, and how strictly changes, records, and claims must be documented. Public work can bring formal solicitations, mandatory clauses, bonds, prevailing-wage duties, audits, and administrative claim procedures; private work is shaped more by the signed agreement, the owner’s requirements, and state law. Neither label answers every question. A federally funded local project may carry federal labor rules, while a private lender may demand controls that resemble a government contract. Before pricing either job, obtain the complete solicitation or agreement, every amendment and incorporated document, and the law governing the project.
At a glance
| Name | Best for | Key spec | Checked |
|---|---|---|---|
| Public construction contract | Contractors prepared for formal procurement and compliance administration | Solicitation and funding can trigger bid procedures, responsibility reviews, bonds, prevailing-wage clauses, payroll reporting, procurement records, audits, written change authority, and administrative claims | November 2026 |
| Private construction contract | Contractors negotiating directly with an owner, developer, lender, or construction manager | Terms are driven by the agreement and state or local law; owners and lenders may still require bonds, insurance, reporting, retainage, schedules, and strict change-order procedures | November 2026 |
What is the legal difference between a public and a private construction contract?
A public contract is awarded by a government entity or through a publicly funded program, so procurement rules and funding conditions can become part of the deal. A private contract is between nongovernmental parties, but it remains subject to applicable state and local statutes, licensing rules, lien law, building regulations, and the negotiated contract.
As an Amazon Associate I earn from qualifying purchases.
“Public” is not one uniform category. A federal agency procurement, a city project paid partly with a federal grant, a state highway job, a school-district contract, and a public-private arrangement may use different statutes, forms, wage rules, bond requirements, and dispute forums. “Private” is equally broad: a small renovation, a lender-controlled development, and a large design-build project can impose very different obligations.
The practical distinction is therefore not simply government versus business. It is the combination of owner, funding source, procurement method, incorporated clauses, and governing law. Read those items before assuming a requirement is present or absent.
Popular on Amazon
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Both tools are designed to fit into difficult to reach spaces
- Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
- Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
Why does funding matter more than the project label?
Funding can extend federal requirements into a contract that is not signed directly with the federal government. The U.S. Department of Labor explains that Davis-Bacon coverage may apply to federally funded or federally assisted construction agreements outside the Federal Acquisition Regulation procurement system when the statutory coverage conditions are met. A local project can therefore require federal wage clauses even though the contracting agency is a city or nonprofit.
Start by identifying every funding stream: federal appropriations, a grant or loan, state money, municipal revenue, private equity, and lender financing. Then identify the grantor or pass-through entity and read the funding agreement. The solicitation should identify incorporated statutes, regulations, agency supplements, wage determinations, disadvantaged-business requirements, domestic-preference rules, reporting forms, and flow-down clauses. If the documents conflict, ask the contracting officer or owner for a written interpretation before bidding.
For covered non-Federal prime construction contracts, a 2026 federal regulation excerpt states that when program legislation requires Davis-Bacon compliance, contracts in excess of $2,000 must include the applicable clause. That is a coverage-specific federal-assistance rule, not a universal threshold for every public project, state contract, or private job. Confirm the statute funding your project and the clause actually included in the bid package.
How does public procurement change the way a contractor bids?
Public owners generally must follow a documented procurement method, such as sealed bidding, competitive proposals, a qualifications-based process, or a permitted cooperative purchase. The solicitation may prescribe the bid form, alternates, unit prices, bonds, licenses, prequalification, subcontractor disclosures, non-collusion certifications, and how mistakes are handled. A bid that is commercially attractive can still be rejected as nonresponsive if a required form, signature, acknowledgment, or bid security is missing.
Federal construction procurements are governed by the solicitation and the applicable Federal Acquisition Regulation provisions, including FAR Subpart 36.2. State and local procurements may use different statutes and protest deadlines. Build a compliance calendar that includes the question deadline, site visit, bid opening, validity period, notice of intent, protest window, bonds, insurance certificates, and contract execution.
Public agencies commonly evaluate both responsiveness and responsibility. Responsiveness asks whether the bid complies with the submission instructions. Responsibility examines whether the apparent low bidder has the financial capacity, experience, licenses, equipment, safety record, and integrity to perform. A public owner may also check debarment status, tax compliance, past performance, and proposed subcontractors.
PC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchPrivate owners usually have more discretion to negotiate scope, schedule, contingencies, and qualifications. They may solicit several proposals, negotiate with one contractor, or select on value rather than low price. That flexibility does not eliminate risk: the owner can make its own representations about budget, financing, site access, or design completeness, and the contract should state what happens if those assumptions fail.
Also popular on Amazon
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
Do public construction jobs require performance and payment bonds?
Often, but not identically. Federal construction rules address performance and payment bonds, and many state and local statutes impose their own bond requirements. The solicitation should state whether a bid bond, performance bond, payment bond, or all three are required; the penal amount; the approved surety standard; the form; and when the bonds are due.
Check whether the bond amount is based on the original contract price, an adjusted price, or a statutory schedule. Confirm that your surety is eligible for the particular public owner and that the bond form matches the agency’s form. Ask how options, change orders, and extensions affect the bond. A failure to furnish an acceptable bond on time can result in award to another bidder or a default finding.
Private owners and lenders can require the same package, even when no statute compels it. They may also ask for subcontractor bonds, subcontractor default insurance, payment guarantees, parent-company guarantees, or letters of credit. Price the premium, collateral, indemnity, and underwriting time into the bid. A private contract may permit a substitute security or a negotiated waiver; a public solicitation often will not.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Are prevailing wages and payroll reporting required?
They are required when the applicable federal, state, local, or contract-specific labor regime says so. On covered federal or federally assisted work, the contract normally identifies a classification-by-classification wage determination and labor clauses. The Department of Labor’s wage-determination guidance explains that the agency is responsible for including the appropriate current determination and that revisions may be incorporated up to the applicable lock-in point.
Do not rely on an old wage sheet or a general estimate. Compare the determination’s county, construction type, classifications, basic hourly rate, fringe benefit obligation, and effective date with your staffing plan. Track amendments to the solicitation. A wage revision before award can change labor cost, fringe payments, certified payroll, and subcontract prices. Ask the agency which date locks the determination for your contract and what happens if award is delayed.
Covered work can require weekly certified payroll, employee and classification records, fringe-benefit documentation, posting of notices, interviews, restitution procedures, and flow-down clauses in every covered subcontract. Assign one person to collect payroll data and verify classifications before the first pay application. Keep evidence that fringe benefits were paid or credited correctly; a payroll spreadsheet alone may not prove compliance.
Private projects generally do not receive federal prevailing-wage clauses merely because they are large. However, a state or local prevailing-wage statute, an incentive program, a development agreement, a union requirement, or the private owner’s contract can impose wage floors and reporting. Treat any wage clause as a pricing term and identify who bears increases, misclassification exposure, and audit costs.
Also popular on Amazon
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
How do payment terms and security differ?
Public contracts commonly prescribe the pay application form, supporting schedules, invoice routing, approval chain, retainage, withholding rights, and prompt-payment or subcontractor-payment rules. Payment can depend on a designated public official’s certification, an appropriations process, or receipt of grant funds. Verify whether the agency may withhold for defective work, wage violations, missing reports, disputed quantities, or subcontractor claims.
Private contracts are more negotiable but can be equally restrictive. A lender may require monthly draws, sworn statements, lien waivers, inspections, title updates, and evidence that subcontractors were paid. The owner may condition payment on architect certification, completion of punch-list work, or receipt of a lender advance. Read the pay-when-paid or pay-if-paid language carefully and check whether state law limits its effect.
Security remedies also vary. A public project may prohibit mechanic’s liens against government property while providing a payment-bond claim route. A private project may permit a mechanic’s lien, a payment bond claim, or both, depending on the jurisdiction and the project documents. Construction-law guidance for the United States emphasizes that lien, bond, notice, and limitation periods differ by state. Calendar preliminary-notice, invoice, retainage, claim, and suit deadlines when the contract is signed.
Who can authorize a change order on public and private work?
The contract controls. On public work, identify the contracting officer or other expressly authorized representative. A field inspector, resident engineer, architect, or project manager may administer the work without having authority to increase the contract price or extend time. Follow the written change directive, notice, pricing, and documentation procedure even when the physical change appears urgent.
Federal Transit Administration contract-administration guidance discusses cost analysis for modifications and change orders and directs parties to process disputes under the contract’s disputes clause. Use the same discipline on other public projects: record the instruction, affected drawings and quantities, labor and equipment, subcontractor quotations, schedule effect, mitigation, and reservation of rights. Submit a notice within the stated number of days and separate undisputed work from disputed entitlement where the contract permits.
Private contracts can allow architect’s instructions, construction-manager directives, or owner emails, but informal authority is dangerous. Require a written change order that states scope, price or pricing method, schedule adjustment, allowance treatment, and effect on retainage and bonds. If emergency work is necessary, send a confirming notice immediately and document the basis for proceeding.
What records and audits should a contractor expect?
Public owners and grant recipients must be able to show how the procurement was conducted and how the price was determined. Federal grant procurement standards require a record of procurement history, including the method, contract type, contractor selection, and price basis, and assign recipients responsibility for disputes and claims arising from their procurement transactions. The rule appears in 2 CFR Part 200; related guidance is available in the OMB procurement standards.
Also popular on Amazon
- Toolwiz 17-inch magnetic sweeper maintaining a load capacity of up to 8.8 pounds provides a perfect solution to the problem of clearing small ferrous metal objects, such as nails, tacks, bolts, and metal shavings from workshops or garage floors.
- Convenient and portable:17” is good for home, small workshop, or small yard as it is space-saving and more reachable for narrow areas. Perfect for collecting nails or small parts in the car, under the table, and in other nooks or crannies.
- Upgraded Handle Design: The handle features a sturdy, non-telescopic design to completely prevent slipping during use. By simply adding or removing the extension poles, the height can be adjusted to 3 different lengths: 18.9" (48 cm), 32.5" (82.5 cm), and 42.5" (108 cm) from ground to top. This customizable height helps prevent back bending and muscle strain, making your cleaning tasks effortless
- Flexible wheels: Upgrade wheel screws to avoid being too tight to spin or too loose. More comfortable 3-inch rubber wheels roll smoothly on carpet, grass, concrete, and hardwood floors. Just push and pull this rolling magnet-sweeper to pick up metal nails easily.
- Lightweight materials: The magnetic nail sweeper's compact and lightweight design makes the sweeping can be done anywhere you want, Push or pull it under the furniture, passing through the workshop floor, driveway, mud, grass, and gravel.
Your contract may require retention of bids, estimates, payroll, certified payroll, time sheets, delivery tickets, subcontracts, invoices, change-order calculations, disadvantaged-business reports, safety records, and correspondence. It may grant access to agency, grantor, inspector-general, or auditor reviews years after final payment. Ask for the retention period, electronic format, confidentiality limits, and subcontractor flow-down language.
Quick wins for a faster PC:
Scan for outdated or missing drivers - takes under a minuteDriver Scan →Repair Windows errors before they cause bigger problemsFix Now →Private owners and lenders can demand detailed cost reports, open-book accounting, schedule updates, lien waivers, insurance renewals, quality records, and audit rights. The difference is usually who can inspect and under what clause, not whether records matter. Preserve the contemporaneous record that supports entitlement: a later reconstruction is harder to defend in any forum.
How do disputes, suspension, and termination differ?
Public contracts often require an administrative claim, a contracting-officer decision, a designated appeal board, or a specified court before litigation. Deadlines can be short and may run from notice of the event, a written denial, or final payment. The contract may also allow suspension for funding, convenience termination, default termination, cure notices, and setoff against other amounts owed.
Read the disputes clause before signing and map every step: notice, supporting statement, certification, decision, appeal, mediation, arbitration, litigation forum, and deadline. Determine whether continuing performance is mandatory during a dispute and whether the owner can direct segregation of disputed work. A contractor that misses a contractual notice can lose time or cost recovery even if the underlying change was real.
Private contracts may provide negotiation, mediation, arbitration, or court litigation, with different attorney-fee and lien-waiver consequences. They can also contain broad termination-for-convenience rights, termination fees, consequential-damage waivers, or personal-guarantee provisions. Compare the remedy language with the payment schedule and your exposure for committed labor, materials, and subcontract cancellation costs.
Recommended Free Tools
What should I review before bidding or signing?
Use this sequence for either contract type, adding the public-procurement steps when applicable:
- Identify the parties and authority. Confirm the legal owner, contracting entity, funding recipient, authorized signatory, project address, and notice addresses. For a public job, verify the agency and grant or pass-through relationship.
- Collect the complete document set. Obtain the solicitation or request for proposals, agreement, general and supplementary conditions, drawings, specifications, addenda, wage determination, bond forms, insurance requirements, schedules, and every incorporated clause. Do not price from an excerpt.
- Build a compliance matrix. List each required form, certification, license, prequalification, subcontractor disclosure, domestic-preference rule, labor clause, reporting duty, and due date. Assign an owner and evidence for each item.
- Confirm scope and risk allocation. Mark exclusions, owner-furnished items, site conditions, design responsibility, testing, permits, temporary facilities, utility relocation, hazardous materials, and commissioning. Identify which assumptions are stated facts and which are your contingencies.
- Price labor and wage exposure. Check classifications, fringe obligations, payroll systems, overtime rules, union terms, travel, escalation, and flow-down requirements. On covered public work, verify the wage determination and its lock-in rule.
- Validate bonds and insurance. Obtain surety capacity before bid submission. Check bond forms, penal amounts, aggregate limits, additional-insured wording, completed-operations coverage, professional liability, builders risk, workers’ compensation, and cyber or pollution requirements if specified.
- Model payment timing. Calculate mobilization cash needs, retainage, approval lag, stored-material rules, lender draws, withholding rights, and subcontractor payment deadlines. Identify preliminary-notice, invoice, and payment-bond claim deadlines in the project jurisdiction.
- Map change authority. Name who can direct a change, the notice period, required pricing backup, markup caps, time-extension procedure, force-account rules, and treatment of owner-caused delay. Require written confirmation before performing extra work whenever possible.
- Plan records and flow-downs. Set up payroll, certified-payroll, cost-code, schedule, daily-report, submittal, safety, and change-order files. Put matching labor, audit, insurance, indemnity, and payment obligations into subcontracts.
- Review default and exit rights. Note cure periods, suspension, termination for convenience, termination for default, step-in rights, damages caps, release language, dispute forum, and survival clauses. Have counsel confirm that statutory remedies are not waived inadvertently.
- Submit clarifying questions in the permitted channel. Public solicitations usually bind bidders to a formal question process and may publish answers to every bidder. For private work, issue a written clarification or contract exhibit rather than relying on a meeting statement.
- Obtain a project-specific legal or procurement review. State and local rules control many deadlines and remedies. A lawyer or procurement professional familiar with the project jurisdiction can verify coverage that a generic template cannot.
What common mistakes cause avoidable losses?
- Assuming every public job has the same rules. Fix: identify the agency, funding statute, grant terms, and incorporated clauses; do not copy a prior project’s compliance checklist.
- Using the wrong wage determination. Fix: download the determination named in the current solicitation, review every addendum, and obtain written confirmation of the applicable lock-in date.
- Starting extra work on a verbal instruction. Fix: send a notice describing the direction, scope, cost, and schedule impact, then obtain a signed directive or reserve rights under the contract.
- Submitting a complete invoice without required evidence. Fix: mirror the pay-application checklist, including certified payroll, lien or bond information, insurance, schedules, and subcontractor payment certifications.
- Leaving compliance obligations out of subcontracts. Fix: attach the required clauses and forms, explain reporting deadlines, and review lower-tier flow-downs before mobilization.
- Missing notice or claim deadlines. Fix: calendar each event-based and payment-based deadline and send protective notices while entitlement is investigated.
- Ignoring owner credit and funding controls. Fix: evaluate appropriations, grant reimbursement, lender draw conditions, and the owner’s ability to pay progress and closeout amounts.
- Relying on a generic contract template. Fix: reconcile the template with the solicitation, local law, bond forms, insurance endorsements, and dispute forum before execution.
How should a contractor compare a public opportunity with a private one?
Compare the full risk-adjusted return, not the headline contract value. A public bid may offer a clearly defined scope and payment bond but require expensive compliance staff, certified payroll, bonding capacity, strict notice, and limited negotiation. A private job may allow better commercial terms but expose you to owner-credit risk, lender controls, incomplete design, negotiated indemnities, or lien and payment disputes.
Also popular on Amazon
- APPLY TO MOST DRILLS : 6 pieces screw extractors work with any drill and all the screw size or bolt (3-12mm), These extractor tools are used to reverse the damaged screw counterclockwise until it is released
- The DIY Tools for Men-Men won't know they need screw extractor set until they have one! This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and Unique tool gifts for men women. The must have stocking stuffers for men, gifts for dad, husband, father, him, guy teens, adult, Boyfriend, son on Birthdays, Christmas, Fathers Day or anniversary. Perfect Holiday Gifts Guide
- HIGH QUALITY - This damaged screw remover tool kit is made from High-Speed Steel H.S.S 4341# , which have high hardness of 63hrc, it's durable and easily to remove any damaged screws.
- EASY TO USE: Just two simple steps to get the job done - drill a hole with a cutting size using the right size screw extractor and easily remove the screw or bolt using the removal tool Hardness 63-65HRC: Titanium hardened steel material, more durable than most screw extractors on the market, better hardness and durability than others, buy with confidence and complete peace of mind
- Cool Gadgets for Men Dad Christmas Birthday Gifts for Men and Women - Men won't know they need screw extractor sets until they have one! Every screw has the potential to rust and break, which can create a situation where it cannot be removed. Owning it, there will be no anxiety about rusty screws. This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and unique tool gifts for men women. A must have stocking stuffer for men on birthdays, Christmas, Father's Day or anniversaries, a gifts for dads, husbands, fathers, him, adults, boyfriends, sons. The best and most practical and surprising Christmas gifts
Prepare a side-by-side worksheet with these fields:
| Decision point | Public project questions | Private project questions |
|---|---|---|
| Access and award | What procurement method, bid security, responsibility test, protest period, and authorization apply? | Who selects the contractor, what can be negotiated, and is financing or board approval still pending? |
| Funding and clauses | Which federal, state, local, grant, and agency clauses flow down? | Which lender, development-agreement, incentive, or owner policies are incorporated? |
| Labor | Is Davis-Bacon or another prevailing-wage regime covered, and what payroll evidence is required? | Do state law, a union agreement, an incentive, or the owner’s contract impose wage or reporting duties? |
| Security | Which bid, performance, and payment bonds and approved surety forms are mandatory? | Are bonds, guarantees, letters of credit, or subcontractor security required by the owner or lender? |
| Payment | What approvals, retainage, prompt-payment rules, appropriations, and bond-claim notices apply? | What draw, certification, lien-waiver, retainage, and owner-credit conditions control payment? |
| Changes and claims | Who has authority, what notice and pricing rules apply, and what administrative forum decides disputes? | Who can direct changes, how are delays valued, and are mediation, arbitration, or court remedies available? |
| Records | What payroll, procurement, audit, retention, and grantor-access duties survive closeout? | What owner, lender, accounting, quality, and closeout records are required? |
How this comparison is organized
The comparison uses the criteria that most affect a contractor’s price, cash flow, administrative workload, and ability to recover costs: procurement access, funding and incorporated clauses, bonds and insurance, labor and payroll, payment security, change authority, records and audits, dispute and termination rights, and owner-credit risk. These are document-driven questions, not assumptions about every project labeled public or private.
Free tools Windows power users keep installed
One-click scans. No signup required.
Bottom line: which contract type is better for a contractor?
Neither is automatically better. Public work can provide a structured award process and statutory payment protections, but it may demand bonding capacity, prevailing-wage administration, extensive records, and strict claim procedures. Private work can offer negotiation flexibility, yet the contractor may face concentrated owner or lender risk and fewer standardized protections.
The safer decision is the one you can price and administer. Obtain the complete documents, identify the funding and legal coverage, verify wage and bond requirements, model payment timing, confirm written change authority, calendar every notice deadline, and obtain project-specific advice on state and local law before submitting a bid or signing.
Frequently Asked Questions
Can a private construction contract require prevailing wages?
Yes. A state or local statute, development agreement, public incentive, union arrangement, or negotiated owner clause can impose wage floors and payroll reporting on a private project. The contract should identify classifications, fringe obligations, records, audit rights, and responsibility for wage increases or misclassification claims.
Are public construction contracts always safer because they have government owners?
No. A public owner may have formal payment and dispute procedures, but appropriations, grant reimbursement, retainage, audits, and strict notice rules can delay recovery. Evaluate the actual funding, payment clause, bond remedy, and claim forum rather than relying on the owner’s public status.
What happens if the wage determination changes after I submit a bid?
The applicable solicitation and agency rules determine whether a revision is incorporated and which date locks the determination. Review every amendment and ask the agency in writing how a delayed award or revised determination affects your price before accepting the contract.
Can I rely on an architect’s or inspector’s oral change instruction?
Only if the contract gives that person authority and the required notice procedure is satisfied; many contracts do not. Send a prompt written confirmation stating the instruction, scope, estimated cost, and schedule effect, and preserve your rights if a formal directive is not issued.