The House of Commons Public Accounts Committee (PAC) says Sizewell C’s financing leaves UK taxpayers and electricity consumers carrying unusually large construction and operating risks, while private investors face comparatively small additional losses if costs rise. The committee’s warning, published on 28 October 2026, covers an expected project cost of £40.5bn to £47.7bn and completion between 2039 and 2043. The Guardian summarised the criticism as a “terrible deal”; that phrase is not the formal title of the PAC report.
The dispute is not over whether nuclear power can provide reliable electricity. It is over whether the regulated-asset-base (RAB) model gives consumers enough protection for the risk they are being asked to fund.
As an Amazon Associate I earn from qualifying purchases.
Do these 3 things before closing this tab:
1Clear out junk files and repair common Windows errors2Fix the driver behind crashes, sound loss and screen glitches3Repair Windows errors before they cause bigger problemsWhy are MPs calling Sizewell C financing a “terrible deal”?
The PAC’s core objection is the allocation of risk. Its figures indicate that consumers could provide an additional £9.8bn during construction if costs exceed forecasts and as much as £12bn through the 60-year operating contract. In the committee’s comparison, private investors would provide only an additional £30m for those overruns.
PAC chair Sir Geoffrey Clifton-Brown said: “The high level of risk borne by taxpayers and consumers for the construction of Sizewell C is extraordinary. Private investors look set for significant returns on their investments, while customers are likely to be saddled with higher energy bills.”
Popular on Amazon
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Both tools are designed to fit into difficult to reach spaces
- Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
- Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
The committee is also concerned that government is providing most of the finance but has relinquished majority control of the delivery body, which is primarily owned by private investors. It says that combination could leave weak incentives to contain cost and schedule overruns.
What is Sizewell C and when is it due to be finished?
Sizewell C is a planned 3.2GW nuclear power station on the Suffolk coast. UK Parliament says that capacity would represent about 7% of current UK electricity demand. The design is an EPR used in France, Finland and China and being built at Hinkley Point C in Britain.
PC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchThe latest PAC notice gives a construction-completion window of 2039 to 2043. Earlier oral evidence in June referred to a £38.2bn estimate and electricity for about six million homes from 2038. Those are earlier, different estimates and should not be treated as interchangeable with the PAC’s later range.
The project’s Final Investment Decision was recorded on 22 July 2025, and contracts were finalised on 4 November 2025. The PAC says no comparable nuclear station anywhere in the world has yet been completed both on time and on budget, making the delivery timetable a central part of its concern.
Also popular on Amazon
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
How does the Sizewell C RAB model work?
A regulated-asset-base model allows public finance and regulated consumer charges to support a project during construction as well as operation. Private investors hold equity, while the regulated income is intended to reduce financing costs and encourage construction of infrastructure that may take decades to repay.
Submitted evidence records the following ownership split:
Free tools Windows power users keep installed
One-click scans. No signup required.
| Investor | Recorded share |
|---|---|
| UK government | 44.9% |
| La Caisse | 20% |
| Centrica | 15% |
| EDF | 12.5% |
| Amber Infrastructure | 7.6% |
Because charges can support the asset before it generates electricity, consumers can be exposed while construction is still incomplete. The PAC argues that the public therefore supplies most of the downside protection, while equity investors retain the prospect of substantial returns.
How much could taxpayers and consumers pay if the project overruns?
The PAC’s quantified figures describe possible additional exposure, not a bill that has already been charged. They are scenario amounts cited by the committee in its warning.
Also popular on Amazon
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
| Figure | What it represents | Source and qualification |
|---|---|---|
| £40.5bn–£47.7bn | Expected total project cost | PAC, 2026 estimate |
| 2039–2043 | Expected construction-completion window | PAC, 2026 forecast |
| £9.8bn | Additional consumer contribution cited for construction overruns | PAC comparison of potential exposure |
| £12bn | Additional consumer exposure through the 60-year operating contract | PAC comparison of potential exposure |
| £30m | Additional private-investor contribution in the same overrun comparison | PAC figure |
The available data does not establish a current average household charge or a settled lifetime electricity price. A precise monthly bill figure would therefore be misleading.
What benefits do the government and nuclear industry claim?
Supporters argue that the RAB structure is justified by the value of firm generation: electricity available regardless of whether wind or solar output is high at a particular moment. A UK government spokesperson said Sizewell C could save £2bn a year across the energy system once operational and said more than 2,000 workers were already on site.
Recommended Free Tools
The PAC also cites a possible £26.6bn addition to the UK economy during construction and a government objective for 70% of construction spending to be in the UK. The Nuclear Industry Association argues that nuclear can reduce balancing and network costs. Its chief executive, Tom Greatrex, said £2.8bn had been spent so far that year managing a dysfunctional grid, including payments to curtail wind and to run gas-fired backup.
These are claimed system-wide benefits, not a guarantee that every household will see a particular reduction. Their value depends on Sizewell C being completed, operating reliably and displacing enough balancing, network or fuel costs to offset its financing and operating commitments.
Also popular on Amazon
- Toolwiz 17-inch magnetic sweeper maintaining a load capacity of up to 8.8 pounds provides a perfect solution to the problem of clearing small ferrous metal objects, such as nails, tacks, bolts, and metal shavings from workshops or garage floors.
- Convenient and portable:17” is good for home, small workshop, or small yard as it is space-saving and more reachable for narrow areas. Perfect for collecting nails or small parts in the car, under the table, and in other nooks or crannies.
- Upgraded Handle Design: The handle features a sturdy, non-telescopic design to completely prevent slipping during use. By simply adding or removing the extension poles, the height can be adjusted to 3 different lengths: 18.9" (48 cm), 32.5" (82.5 cm), and 42.5" (108 cm) from ground to top. This customizable height helps prevent back bending and muscle strain, making your cleaning tasks effortless
- Flexible wheels: Upgrade wheel screws to avoid being too tight to spin or too loose. More comfortable 3-inch rubber wheels roll smoothly on carpet, grass, concrete, and hardwood floors. Just push and pull this rolling magnet-sweeper to pick up metal nails easily.
- Lightweight materials: The magnetic nail sweeper's compact and lightweight design makes the sweeping can be done anywhere you want, Push or pull it under the furniture, passing through the workshop floor, driveway, mud, grass, and gravel.
Why does the construction record of the EPR design matter?
Sizewell C uses a design whose projects have faced lengthy construction periods and cost pressure. The PAC points to the international record and says no comparable plant has demonstrated on-time, on-budget delivery. Delays would matter under a RAB model because consumers can continue supporting the project while output is deferred, and a later completion can increase financing and construction costs.
The committee says the government must focus not only on delivering one station but also on creating a commercially derisked nuclear sector. Professor Stephen Thomas’s submitted evidence similarly argues that RAB incentives are expensive and risky for consumers and should not become a template for later nuclear projects. That is expert evidence to the inquiry, not a separate PAC finding.
What information is the PAC demanding from ministers?
The committee has asked the government to improve scrutiny and make the public exposure easier to track:
- Provide the project’s cost-scenario analysis within three months.
- Publish updates every six months instead of annually, including expected effects on consumer bills and forecast investor returns.
- Publish funded-decommissioning-programme reports every five years.
- Explain how the 70% UK-spend target and UK-jobs objectives will be met.
Sir Geoffrey Clifton-Brown said: “The government must focus on the successful delivery of this project, not just of a new nuclear power station, but of a commercially derisked nuclear sector for a taxpayer that should never be put in this position again.”
Also popular on Amazon
- APPLY TO MOST DRILLS : 6 pieces screw extractors work with any drill and all the screw size or bolt (3-12mm), These extractor tools are used to reverse the damaged screw counterclockwise until it is released
- The DIY Tools for Men-Men won't know they need screw extractor set until they have one! This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and Unique tool gifts for men women. The must have stocking stuffers for men, gifts for dad, husband, father, him, guy teens, adult, Boyfriend, son on Birthdays, Christmas, Fathers Day or anniversary. Perfect Holiday Gifts Guide
- HIGH QUALITY - This damaged screw remover tool kit is made from High-Speed Steel H.S.S 4341# , which have high hardness of 63hrc, it's durable and easily to remove any damaged screws.
- EASY TO USE: Just two simple steps to get the job done - drill a hole with a cutting size using the right size screw extractor and easily remove the screw or bolt using the removal tool Hardness 63-65HRC: Titanium hardened steel material, more durable than most screw extractors on the market, better hardness and durability than others, buy with confidence and complete peace of mind
- Cool Gadgets for Men Dad Christmas Birthday Gifts for Men and Women - Men won't know they need screw extractor sets until they have one! Every screw has the potential to rust and break, which can create a situation where it cannot be removed. Owning it, there will be no anxiety about rusty screws. This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and unique tool gifts for men women. A must have stocking stuffer for men on birthdays, Christmas, Father's Day or anniversaries, a gifts for dads, husbands, fathers, him, adults, boyfriends, sons. The best and most practical and surprising Christmas gifts
Will Sizewell C increase energy bills?
Consumers are exposed to higher costs if the project exceeds its assumptions, because the RAB structure allows consumer support during construction and over the operating contract. The PAC warns that this could mean higher bills, but the available evidence does not set a definitive household surcharge or lifetime tariff.
The government’s counterargument is that reliable nuclear output could reduce total system costs once the plant operates. Whether that happens depends on delivery cost, completion date, plant performance and the value of the wider grid services it provides.
How should the competing claims be judged?
| Question | PAC and critics | Government and industry |
|---|---|---|
| Who bears overruns? | Consumers and taxpayers absorb most downside risk; investor penalties and extra capital are limited. | RAB incentives are intended to promote cheaper, faster construction. |
| What is the system value? | Higher financing and delay risk could outweigh promised benefits. | Firm nuclear output can reduce balancing and network costs. |
| What should happen next? | More frequent reporting, scenario analysis and decommissioning transparency. | Continue delivery while demonstrating progress and value. |
The practical test is whether the project’s final cost and schedule remain close enough to forecasts for its firm-output and whole-system benefits to justify the public exposure. The PAC is asking ministers to publish the evidence needed to make that judgment before further risk is hidden in long-term charges.
Frequently Asked Questions
Does the PAC criticism cancel Sizewell C?
No. The project’s Final Investment Decision was recorded in July 2025 and contracts were finalised in November 2025. The PAC is seeking stronger oversight and disclosure rather than announcing a cancellation.
Why can households contribute before the reactor generates power?
Under a RAB structure, regulated charges and public finance can support construction as well as operation. That lowers some financing costs for the developer but brings consumer exposure forward into the building phase.
Could Sizewell C still lower electricity-system costs?
Yes, if it reaches operation at an acceptable cost and supplies dependable output that reduces balancing, network and backup requirements. The government’s £2bn-a-year estimate is a system-wide claim, not a guaranteed saving on an individual bill.
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →What does the 60-year operating contract mean for consumers?
It means the potential consumer exposure identified by the PAC extends well beyond construction. The committee’s £12bn figure is an additional-risk estimate under the contract, not a confirmed charge already allocated to households.