Driver FixRecommendedSound, Wi-Fi or graphics acting up? Check drivers firstFind missing or outdated drivers fast.Check DriversThanksgiving DealsAmazon USThanksgiving week: Black Friday picks start earlyAmazon US: current deals, useful picks and tech finds.Check DealsWindows FixRecommendedWindows errors stealing your time? Find the fix fastScan stability, cleanup and performance issues.Fix Now×
BETTESWORTHConstruction

Larsen Toubro Tashkent Airport Project and Construction Stages Explained

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Some links on this page are affiliate links: if you buy through them we may earn a commission, at no extra cost to you.

Larsen & Toubro (L&T) has not yet announced full site construction at the New Tashkent International Airport. Its Public Spaces, Airports & Health vertical is working under a Limited Notice to Proceed (LNTP) on initial engineering, detailed design, planning and procurement preparation. Physical construction of L&T’s package is expected to follow a full Notice to Proceed (NTP), which has not been dated publicly. The International Finance Corporation (IFC) disclosure expects construction to begin in early 2027, run for about 3.5 years and reach commercial operation in 2030; those are project expectations rather than a confirmed L&T start or opening date.

Has L&T started construction at Tashkent airport?

No. L&T has started defined pre-construction work under an LNTP, not full physical site construction. The LNTP authorizes early engineering, detailed design, planning and procurement preparation for the company’s contract package.

As an Amazon Associate I earn from qualifying purchases.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The next contractual milestone is the full NTP. The PPP consortium is expected to issue it after agreed conditions precedent are fulfilled, but neither the conditions nor the NTP date has been published. L&T’s announcement indicates that site construction follows the full NTP, so describing the airport as already under full construction would overstate the current position.

What is the New Tashkent International Airport project?

The project is a greenfield international airport about 35 kilometres from Tashkent in a sparsely populated agricultural area. It is being developed as a public-private partnership between Uzbekistan Airports JSC (UzAirports) and a consortium comprising Vision International Investment Company, Sojitz Corporation, Incheon International Airport and the Korea Overseas Infrastructure & Urban Development Corporation. UzAirports is also expected to hold 10% of the consortium.

Popular on Amazon
Sale
DEWALT 20V MAX Cordless Drill and Impact Driver (DCK240C2) | Power Tool Combo Kit, Includes 2 Batteries, Charger and Bag
  • Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
  • Both tools are designed to fit into difficult to reach spaces
  • Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
  • Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
  • One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips

IFC describes an initial whole-airport capacity of 20 million passengers per annum (MPPA), with expansion possible. L&T separately describes its passenger-terminal and associated-landside design brief as approximately 17 million passengers annually. These figures refer to different scopes:

Figure What it describes Status
20 MPPA Initial capacity of the complete airport IFC project disclosure
Approximately 17 MPPA L&T’s terminal and associated landside package L&T project description

What is L&T building at the new airport?

L&T’s EPC contract covers the passenger terminal and associated landside infrastructure. The listed work includes:

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  • site grading;
  • road infrastructure;
  • structural works;
  • architectural finishes;
  • mechanical, electrical and plumbing (MEP) services;
  • utilities; and
  • installation of advanced airport systems.

L&T classifies the order as “Ultra-Mega”, its internal band for orders above ₹15,000 crore. The company has not disclosed the exact EPC contract value, so the classification should not be treated as a published project price.

What are the construction stages of the Tashkent airport project?

The work is sequenced from contractual authorization through design, civil construction, building fit-out and integrated commissioning.

Also popular on Amazon
Sale
Nicpro Mechanical Carpenter Pencils for Construction (Black, Red) With Case | Deep Hole Marker Pencil Set Includes Sharpener and 26 Refills, Comfortable Grip, Heavy Duty Woodworking Tools for Architect
  • Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
  • Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
  • Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
  • Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
  • Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons

1. Limited Notice to Proceed

The current stage permits defined early activities. L&T is progressing initial engineering, detailed design, planning and procurement preparation while the consortium completes the requirements needed for the full authorization.

2. Conditions precedent and full Notice to Proceed

Once the agreed contractual conditions precedent are satisfied, the consortium is expected to issue the full NTP. This is the trigger for moving L&T’s package into the main site-construction phase. A public date for that notice is not available.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

3. Site preparation and civil works

After the full NTP, the package is scheduled to move into site grading, access and internal roads, foundations and other structural construction. These works prepare the terminal and its landside connections for the building trades and systems contractors.

4. Terminal completion and systems installation

The building phase adds architectural finishes, MEP services, utilities and advanced airport systems. Systems installation must be coordinated with the structural and architectural work so that the terminal can be tested as an operating facility rather than handed over as a shell.

Also popular on Amazon
Sale
Push to Unlock, Katerk 6pcs 1/4 inch Hex Shank Screwdriver Bit Holder | Aluminum Alloy Drill Bit Holder Keychain Quick-Change Extension Bar Drill Screw Adapter, Black Carabiner, Tool Gifts for Men
  • 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
  • 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
  • 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
  • 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
  • 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.

5. Airside-landside interface and commissioning

The airport-wide program also includes airside works being handled by the public partner. IFC says a jointly retained construction-management company is intended to coordinate the interfaces between the consortium’s landside works and UzAirports’ airside works. Integrated testing and commissioning must therefore align both packages before commercial operation.

When will the new Tashkent airport be completed?

IFC’s project disclosure provides the current planning outlook, not a guaranteed completion date:

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Milestone Current indication Qualification
Main construction start Early 2027 IFC expectation; dependent on authorization and conditions precedent
Construction duration About 3.5 years IFC project expectation
Commercial operation 2030 Target in the IFC disclosure, not a confirmed opening date

Because L&T has not published the full-NTP date, the early-2027 start and 2030 operation target may change if approvals, financing, design development or interface work takes longer than planned.

Who is responsible for the airport’s airside and landside works?

The PPP separates responsibilities rather than assigning every airport element to one contractor.

Also popular on Amazon
Sale
Toolwiz Magnetic Pick Up Sweeper 17-inch Wide, 8.8 Lbs Magnet Pull Force | 8.8 Lbs, Rolling Magnetic Sweeper, Heavy Duty Magnet Pickup with Smooth Wheels, Yard Tools, Clean Nails for Construction
  • Toolwiz 17-inch magnetic sweeper maintaining a load capacity of up to 8.8 pounds provides a perfect solution to the problem of clearing small ferrous metal objects, such as nails, tacks, bolts, and metal shavings from workshops or garage floors.
  • Convenient and portable:17” is good for home, small workshop, or small yard as it is space-saving and more reachable for narrow areas. Perfect for collecting nails or small parts in the car, under the table, and in other nooks or crannies.
  • Upgraded Handle Design: The handle features a sturdy, non-telescopic design to completely prevent slipping during use. By simply adding or removing the extension poles, the height can be adjusted to 3 different lengths: 18.9" (48 cm), 32.5" (82.5 cm), and 42.5" (108 cm) from ground to top. This customizable height helps prevent back bending and muscle strain, making your cleaning tasks effortless
  • Flexible wheels: Upgrade wheel screws to avoid being too tight to spin or too loose. More comfortable 3-inch rubber wheels roll smoothly on carpet, grass, concrete, and hardwood floors. Just push and pull this rolling magnet-sweeper to pick up metal nails easily.
  • Lightweight materials: The magnetic nail sweeper's compact and lightweight design makes the sweeping can be done anywhere you want, Push or pull it under the furniture, passing through the workshop floor, driveway, mud, grass, and gravel.
Party Primary responsibility
PPP consortium Fund, construct and operate the landside, including the terminal package delivered by L&T
UzAirports Fund, construct and operate the airside
L&T EPC delivery of the passenger terminal and associated landside infrastructure
Joint construction-management company Coordinate airside-landside interfaces for the overall airport program

How is the project being financed?

IFC is part of a prospective lender pool and describes a possible A loan of up to US$200 million, alongside mobilized financing and hedging arrangements. The disclosure is marked “Pending Approval”, so this is proposed financing rather than evidence that the loan has closed or that it represents the project’s entire funding package.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

What environmental, social and workforce controls apply?

IFC categorizes the project as Category A because it may create significant and diverse environmental and social impacts. Its review covers labor and working conditions, pollution prevention, community health and safety, land acquisition and involuntary resettlement, biodiversity, Indigenous Peoples, cultural heritage, contractor management, supply-chain risks and stakeholder engagement.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The project is expected to require approximately 5,000 construction personnel. At operation, IFC expects about 2,000 direct airport and facility-management staff plus 3,000 contracted and ancillary workers.

Associated facilities include the airport access road, power and gas supply lines, and realignment of agricultural drainage works. Minecology issued a positive opinion in April 2026, subject to conditions for final Stage II environmental-impact approval before construction.

Also popular on Amazon
Sale
Damaged Screw Extractor Set,Christmas Stocking Stuffers for Adults Men Him | Gifts for Men,Mens Gifts for Dad,Husband,Stripped Screws Bolt Drill Bit Tools for Easy Removal of Rusty Broken Screw
  • APPLY TO MOST DRILLS : 6 pieces screw extractors work with any drill and all the screw size or bolt (3-12mm), These extractor tools are used to reverse the damaged screw counterclockwise until it is released
  • The DIY Tools for Men-Men won't know they need screw extractor set until they have one! This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and Unique tool gifts for men women. The must have stocking stuffers for men, gifts for dad, husband, father, him, guy teens, adult, Boyfriend, son on Birthdays, Christmas, Fathers Day or anniversary. Perfect Holiday Gifts Guide
  • HIGH QUALITY - This damaged screw remover tool kit is made from High-Speed Steel H.S.S 4341# , which have high hardness of 63hrc, it's durable and easily to remove any damaged screws.
  • EASY TO USE: Just two simple steps to get the job done - drill a hole with a cutting size using the right size screw extractor and easily remove the screw or bolt using the removal tool Hardness 63-65HRC: Titanium hardened steel material, more durable than most screw extractors on the market, better hardness and durability than others, buy with confidence and complete peace of mind
  • Cool Gadgets for Men Dad Christmas Birthday Gifts for Men and Women - Men won't know they need screw extractor sets until they have one! Every screw has the potential to rust and break, which can create a situation where it cannot be removed. Owning it, there will be no anxiety about rusty screws. This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and unique tool gifts for men women. A must have stocking stuffer for men on birthdays, Christmas, Father's Day or anniversaries, a gifts for dads, husbands, fathers, him, adults, boyfriends, sons. The best and most practical and surprising Christmas gifts

What remains unconfirmed?

  • the exact EPC contract value;
  • the date of the full NTP;
  • detailed terminal and landside design drawings;
  • the complete contractor list beyond the named PPP sponsors; and
  • a fixed airport opening date.

L&T Senior Vice President and Head of Buildings Infrastructure Sthaladipti Saha called the award “a significant milestone in L&T’s global infrastructure EPC portfolio.” The practical takeaway is narrower and more precise: L&T is mobilized for design and procurement preparation, while the full construction phase still depends on the NTP and the project’s contractual and environmental conditions.

Frequently Asked Questions

What does a Limited Notice to Proceed allow on a major airport project?

An LNTP lets the contractor perform only the early activities defined in the authorization, such as design development and procurement preparation. It does not by itself confirm that the entire EPC scope, final price or unrestricted site-work authorization is effective.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Why does the airport have both 17-million and 20-million passenger figures?

The numbers use different boundaries: one is the capacity brief for L&T’s terminal-landside package, while the other is the disclosed initial capacity for the complete airport. They should not be read as two competing passenger forecasts for the same facility.

Does the proposed IFC loan mean the airport is fully financed?

No. The disclosed A loan of up to US$200 million is part of a prospective financing pool and remains pending approval. The disclosure does not establish that the loan has closed or that it covers the full project cost.

What approval is especially important before physical construction?

The project’s environmental process includes conditions attached to final Stage II approval, in addition to the contractual conditions precedent for the full NTP. Those requirements sit alongside land, community-safety and interface-management obligations rather than replacing them.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply. Prices as of November 23, 2026 9:45 pm GMT+0000.
Recommended PC Tool
Recommended PC Tool
Windows Errors? Fix Them Before They SpreadFree repair scan
Crashes, No Sound, or Screen Glitches?Free driver scan

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.