Halloween DealsAmazon USHalloween week deals: useful picks before month-endAmazon US: current deals, useful picks and tech finds.Check DealsSlow PC?RecommendedPC slow today? Run a repair scan before it gets worseResolve common Windows issues and optimize system performance.Scan NowHalloween DealsAmazon USOctober picks are moving - compare before checkoutAmazon US: current deals, useful picks and tech finds.See Picks×
BETTESWORTHConstruction
capital planning

How to Estimate the Total Cost of a School Construction Project

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

There is no reliable national “price per square foot” for a school. A defensible budget starts with a defined program and local, comparable cost evidence, then adds site work, professional services, owner costs, escalation and risk allowances. Use this planning equation: total project budget = land and site acquisition + site development + building hard costs + professional and other soft costs + owner costs (including furniture, equipment, technology, moving and temporary space) + escalation + contingencies. Keep every component visible, state what it includes, and present an early estimate as a range rather than a single seemingly precise number.

Why a school cannot be priced with one national square-foot figure

Two buildings with the same gross area can have very different budgets. A primary school, a secondary school with laboratories and technical workshops, and a special-ne education campus do not have the same room mix, structure, mechanical systems or equipment. Land, labor, material availability, code requirements, weather, site access and the local bidding market also change the cost. Renovating an occupied building introduces surveys, hazardous-material abatement, temporary accommodation and phasing that a new build may not need.

As an Amazon Associate I earn from qualifying purchases.

Ohio Administrative Code Rule 3318:1-3-01, effective January 23, 2023, expresses the point directly: “The square foot cost of a new building is based on the grade configuration and number of students to be housed in the building.” That is an Ohio rule, not a national rate. California’s school-facilities guidance and Connecticut planning documents likewise separate building construction from site and other project costs. Their historical figures are useful for understanding categories, but they should not be presented as current national prices.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

For an early decision, report a low and high case, the estimate date, the location, the price basis and the assumptions that could move the result. A decision-maker can then see whether a change reflects more classrooms, a difficult site, a later bid date or a higher performance standard.

#1 Best Overall
Sale
Nicpro Mechanical Carpenter Pencils for Construction (Black, Red) With Case
  • Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
  • Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
  • Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
  • Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
  • Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons

1. Define the basis of estimate before calculating anything

Write a one-page basis-of-estimate statement. It prevents a low number from appearing to be a complete project budget when it is only a contractor’s building allowance.

Project type and program

  • Identify whether the work is a new school, addition, renovation, replacement, phased program or a combination.
  • State grade levels, enrollment by grade, special-education provision, community or shared-use spaces, athletics, food service, administration, laboratories, technical education and performing-arts requirements.
  • Define the target opening date and whether the school must remain occupied during construction.

Area and performance assumptions

  • Record the gross internal area, the net teaching area and the method used to convert between them.
  • List room counts, capacity standards, circulation, storage, plant rooms, covered play and external learning areas.
  • Set energy, carbon, resilience, accessibility, acoustics, security, technology and durability standards. A higher standard can change both first cost and design effort.

Location, procurement and price date

  • Name the site or a defined geographic market, including whether labor and materials must be brought from elsewhere.
  • State the delivery route—traditional design-bid-build, construction management, single-stage design-and-build or a two-stage route—and the assumed contract packaging.
  • Give the estimate date, the expected tender date, the construction start and the planned completion. Distinguish current dollars from year-of-expenditure dollars.
  • Document funding rules, grants, reimbursement limits, taxes, owner-furnished items and any scope that is expressly excluded.

Federal Highway Administration estimating guidance requires scope, phase and assumptions to be documented. Although that guidance is written for major transportation projects, its discipline is transferable: an estimate is only as useful as its stated boundaries.

2. Build the area-and-unit-cost model

At feasibility stage, the core calculation is gross area multiplied by a cost per square foot drawn from recent, comparable local school projects or bids. Treat the rate as evidence, not a universal fact.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Select comparable evidence

  1. Collect recent bids, completed-project final costs and cost plans for schools in the same labor and materials market.
  2. Filter by grade configuration, capacity, complexity, gross area, structural system, mechanical strategy, sustainability target and whether the figures include furniture, technology and site work.
  3. Normalize each source to a common price date and area definition. Record whether the source is a low bid, an awarded contract, a final account or an early estimate.
  4. Use a range when the comparables are not closely matched. Explain why the proposed project sits toward the lower or higher end.

Adjust the rate instead of hiding differences

  • School type: science laboratories, kitchens, workshops, swimming pools, theaters and special-needs facilities generally require more costly services or equipment than ordinary classrooms.
  • Regional conditions: wage rates, material freight, union or labor-market conditions, taxes and local subcontractor capacity affect bids.
  • Site complexity: rock, poor soils, contamination, flood mitigation, retaining walls, restricted access and utility relocation can make a building rate misleading.
  • Renovation versus new construction: surveys, selective demolition, unknown existing conditions, temporary protection and work in occupied areas can raise the cost even when the area is smaller.
  • Quality and performance: enhanced envelopes, all-electric systems, low-carbon materials, backup power, higher acoustical performance and resilience measures alter both construction and design costs.

Keep the original comparable rates and every adjustment in a schedule. If a reviewer cannot trace a rate to a project, date, location and inclusion list, it is not a strong basis for a budget.

3. Add every cost outside the building contract

The contractor’s building bid is one line in the budget. A complete program estimate separates the following components so alternatives can be compared consistently.

Budget component Typical inclusions Questions to resolve
Land and acquisition Purchase or lease premium, due diligence, surveys, title work and transaction costs Is land already owned? Are demolition, relocation or remediation obligations attached to it?
Site development Demolition, clearing, earthwork, foundations beyond the building allowance, roads, parking, buses, playfields, fencing, lighting, landscaping, stormwater, utilities and off-site connections What is provided by public agencies, and what must the project fund?
Building hard costs Structure, envelope, interiors, mechanical, electrical, plumbing, fire protection, security and fixed specialist systems Does the comparable rate include general conditions, temporary works and contractor overhead and profit?
Professional and other soft costs Architecture, engineering, surveys, geotechnical and environmental consultants, cost management, commissioning, testing, inspection, legal, permits, insurance, financing and project management Which services are owner-retained, and which are included in a delivery contract?
Owner costs Furniture, fixtures and equipment, information technology, communications, instructional equipment, moving, storage, swing space, temporary facilities, staff transition and owner operating or phasing expenses Will the owner buy these directly, and are they needed before opening day?
Escalation Price growth from the estimate date through tender and construction expenditure What index, base date, expenditure curve and schedule are being used?
Risk allowances Design development, construction, program and owner reserves for identified and unidentified risks What risk does each allowance cover, who controls it and when can it be released?

California’s Office of Public School Construction budget structure explicitly distinguishes site acquisition and site-related items. Connecticut planning material identifies site and other costs outside building construction. Prince George’s County Public Schools notes that owner operating expenses, furniture and information technology, logistics and swing space can materially affect a school program. Those categories are a useful completeness check, not a promise that a particular jurisdiction will fund them.

4. Estimate land and site work as its own package

Site costs are often the largest source of early uncertainty because they depend on conditions that are not visible in a classroom plan.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Rank #2
Sale
DEWALT 20V MAX Drill and Impact Driver (DCK240C2) | Includes 2 Batteries, Charger and Bag (
  • Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
  • Both tools are designed to fit into difficult to reach spaces
  • Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
  • Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
  • One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips

Investigations and enabling work

  • Commission a boundary and topographic survey, geotechnical borings and environmental studies before fixing the site allowance.
  • Check contamination, asbestos or lead in existing structures, archaeological constraints, protected trees, flood risk, drainage capacity and neighboring-property requirements.
  • Price demolition, clearing, relocation, temporary access and protection of existing utilities separately from the new building.

External infrastructure

  • Include grading, retaining structures, foundations affected by poor soils, roads, bus circulation, parking, pedestrian routes, play areas, athletic fields, fencing, lighting and landscaping.
  • Obtain written utility capacity and connection information for water, sewer, power, gas, data and fire access. Allow for upgrades or off-site extensions when the authorities require them.
  • Model stormwater detention, infiltration, water-quality treatment and flood-mitigation work rather than assuming it is covered by general site work.

If the site is not selected, carry a site-risk allowance or prepare separate low, central and high site scenarios. Do not bury unknown remediation or utility work in a generic building rate.

5. Include professional, financing and owner costs

Design and owner costs begin before construction and continue through opening. They should be based on the actual scope and procurement route, not a percentage copied without checking inclusions.

Professional services

List architecture, civil, structural, mechanical, electrical, plumbing, landscape, acoustics, theater or laboratory specialists, technology and security designers, environmental consultants, surveyors, geotechnical engineers, code consultants, cost managers, commissioning agents and independent inspectors. Add permitting, plan review, testing, special inspections, legal services, insurance, financing charges and audit requirements where applicable.

Furniture, equipment and technology

Prepare an owner-furnished-equipment schedule by room. It may include desks, seating, teaching walls, laboratory equipment, kitchen equipment, workshop machinery, library shelving, athletic equipment, musical instruments, stage systems, network electronics, wireless infrastructure, audiovisual systems, access control, clocks, public-address equipment and security monitoring. Confirm whether each item is purchased by the owner, supplied by the contractor or excluded.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Logistics and continuity

For an occupied campus, price swing space, temporary classrooms, decanting, storage, staff moves, transportation changes, dust and noise control, utility shutdowns, protection of students and phased commissioning. Include training, software subscriptions or support contracts that must be active at opening. These costs can be real project requirements even though they never appear in a construction bid.

A 2019 University of Colorado Denver planning methodology used assumptions of 30% of construction for soft costs and 5% for site infrastructure. Those figures describe that institution’s planning practice; they are not universal school percentages. Use them only as a prompt to test whether your own scope has omitted a category.

6. Escalate the estimate to the year money will be spent

A current-dollar estimate will understate a project that will not bid or build for several years. Convert each cost stream to year-of-expenditure dollars using a stated local construction-cost index or escalation rate and the expected procurement and construction schedule.

Rank #3
Sale
Push to Unlock,Katerk 6pcs 1/4 inch Hex Shank Aluminum Alloy Screwdriver Bit Holder Light-Weight Quick-Change Extension Bar Keychain Drill Screw Adapter Portable,Black Carabiner,Tool Gifts for Men
  • 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
  • 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
  • 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
  • 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
  • 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
  1. Set the base date for every source cost.
  2. Map the design, permitting, tender, award, mobilization and construction periods.
  3. Assign the selected index or rate to the time between the base date and each expected expenditure.
  4. Apply the escalation to the forecast cash-flow curve, not automatically to the entire budget for the full project duration.
  5. Show the base-dollar total, escalation amount and year-of-expenditure total as separate lines.

The University of Colorado Denver methodology illustrated a 5% annual inflation assumption for its own planning use in 2019. That is an example, not a current or universal school rate. Federal Highway Administration guidance likewise requires the inflation basis and year-of-expenditure convention to be explicit. If the tender date slips, update the escalation rather than leaving the original allowance unchanged.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

7. Set contingency from risk and design maturity

Contingency is an allowance for defined uncertainty, not a hidden markup and not a substitute for completing the design. Separate reserves where the governance process benefits from doing so:

  • Design-development contingency: unresolved quantities, coordination and scope decisions that should reduce as drawings advance.
  • Construction contingency: unforeseen conditions and change risk remaining after the contract scope is defined.
  • Escalation contingency: market movement beyond the selected forecast, if the estimating policy treats it separately.
  • Owner or program reserve: strategic changes, operational requirements or risks controlled by the owner.

Federal Highway Administration’s 2007 Major Project Program Cost Estimating Guidance says construction contingencies are normally around 5% to 10% and can approach 15% when scope-change risk is high. Prince George’s County Public Schools used a 20% master-planning contingency in its FY2019–2024 capital-improvement methodology, published in 2017, when scope and site conditions were not yet developed. A 2019 University of Colorado Denver methodology used 5% for new construction and 10% for renovation. Each figure belongs to its stated context; none is a universal school rule.

Use a risk register

  1. List each risk, its cause, affected cost or schedule, probability and potential impact.
  2. Assign an owner and a mitigation action, such as an additional survey, early utility agreement or design decision.
  3. Quantify the exposure where possible and explain which reserve covers it.
  4. Reduce or transfer the allowance only when the underlying uncertainty is priced, contracted or otherwise closed.

A large early reserve can be responsible when the site and program are still fluid. It becomes misleading when it remains unchanged after design, bids and investigations have removed the risks that justified it.

8. Compare new construction, renovation and additions on equal terms

Do not compare a new-building rate with a renovation rate and call the lower one cheaper without normalizing scope. Use the same capacity, opening date, performance standard, site and owner-cost boundaries.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Comparison factor New build Renovation or addition
Existing conditions Known through new design and investigations, but site risk remains Unknown structure, utilities, hazardous materials and code deficiencies can emerge after opening walls
Phasing Often simpler if the site is vacant May require swing space, temporary protection, night work and repeated relocations
Site and utilities New roads, drainage, services and play areas may be required Existing capacity may be reusable, but tie-ins and upgrades can be disruptive and costly
Program efficiency Room layout, circulation and plant can be optimized Existing geometry can create inefficient areas or require extensive demolition
Risk profile More predictable building scope once design is complete Greater discovery and coordination risk; contingency may need to be higher
Opening strategy One commissioning and move-in sequence is typical Multiple handovers, decants and partial occupancy may extend the schedule

Compare the alternatives by total cost of ownership as well as first cost when the decision involves energy, maintenance, adaptability, temporary accommodation or a shorter construction program.

9. Account for procurement and contract strategy

Procurement changes when market input arrives, how much design is complete at tender and where risk is priced. Traditional design-bid-build can provide a clearer competitive price after design completion but may delay early contractor input. Construction management can package early work and obtain trade feedback sooner, while retaining more owner coordination responsibility. Single-stage design-and-build transfers defined design and coordination obligations but requires a clear employer’s requirement. A two-stage design-and-build route can bring a preferred contractor into design development before the final price is agreed.

Rank #4
Sale
2 Pack Carpenter Pencils Mechanical Pencils with 12 Refills, (2 Colors)
  • Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
  • Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
  • Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
  • Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
  • Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed

The UK Department for Education’s procurement framework is England-specific, but it illustrates the general principle: route selection affects when supplier input and pricing enter an education project. Record the selected route, contract packages, allowances, bonds, insurance, taxes, inflation treatment and owner-furnished items in the basis of estimate. Do not compare a guaranteed-price package with an incomplete design estimate without adjusting for the risk each party retains.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

10. Produce an estimate that can be audited and updated

Use a cost plan with a change log rather than a static spreadsheet. At minimum, retain:

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  • Area schedules, room data and enrollment assumptions.
  • Quantity takeoffs or elemental allowances and the source of every unit rate.
  • Comparable project names, locations, dates, contract stages and inclusion lists.
  • Site investigation findings, utility correspondence and environmental assumptions.
  • Professional-fee, owner-cost, furniture, equipment and technology schedules.
  • Escalation index, base date, expenditure curve and year-of-expenditure convention.
  • Risk register, contingency calculation, exclusions and unresolved decisions.
  • Procurement route, contract packaging, schedule, phasing and temporary-facility assumptions.
  • Version number, preparer, reviewer, approval date and a log of changes since the previous estimate.

Review at defined milestones

  1. Feasibility: test capacity, site options, broad area and order-of-magnitude ranges.
  2. Concept or schematic design: verify the room program, site strategy, systems and major risks.
  3. Design development: replace allowances with coordinated quantities, specifications and equipment decisions.
  4. Pre-bid: reconcile documents, update market evidence, confirm exclusions and set the tender estimate.
  5. Bid and contract: compare bids on a normalized scope, identify qualifications and reconcile accepted alternates.
  6. Construction and closeout: maintain forecasts, approved changes, committed costs, remaining risk and final account information.

Federal Highway Administration guidance calls for continual updates, independent validation and multidisciplinary review. For a school, that means the educational planner, facilities staff, architect, engineers, estimator, finance lead, information-technology team and operations representatives should review the same cost plan before major approvals.

11. A practical worksheet for the first estimate

Create one line for each cost category and show three scenarios. The arithmetic can remain simple while the assumptions become more precise:

Line Low case Central case High case
Land and acquisition Known or separately quoted Most likely allowance Higher acquisition or relocation exposure
Site development Favorable ground and utility assumptions Current investigation-based allowance Remediation, drainage or off-site upgrades
Building hard cost Lower bound of comparable local evidence Best-matched normalized rate Higher complexity or performance standard
Professional and other soft costs Confirmed contracted scope Full consultant and approval scope Expanded specialist, legal or financing needs
Owner costs Existing furniture or temporary-space capacity Planned FF&E, IT, moving and commissioning New equipment, swing space or extended logistics
Escalation Earlier procurement Scheduled year-of-expenditure Later award or higher market movement
Contingency and reserve Known scope with limited residual risk Risk-register-based allowance Unresolved site or program risk

Once design quantities and local bids are available, replace scenario placeholders with documented values. Keep the three cases until the decision team accepts the remaining risk; collapsing to one number too early creates false certainty.

12. Common estimating failures and their fixes

Failure: multiplying area by an unexplained rate

Fix: identify grade mix, capacity, location, date, project stage and inclusions for every comparable, then show adjustments and a range.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Failure: treating the construction contract as the project budget

Fix: add land, site work, design, permits, testing, management, furniture, equipment, technology, moving, temporary space, financing, escalation and reserves as visible lines.

Best Value
Milwaukee 48-22-3104 Inkzall Point Marker, Fine, Black, 4-Pack
  • Milwaukee Ink all Fine Point Marker, Black, 4 Per Pack
  • 4 per pack Features Clog Resistant Marker Tip Writes through Dusty, Wet and Oily Surfaces Durable Marker Tip for Writing on Concrete, OSB and Rough Surfaces
  • Clog resistant tip writes on dusty, wet and oily surfaces and is optimized for rough surfaces such as OSB, cinderblock and concrete
  • Hard hat clip- attaches for easy access
  • Quick dry time with reduced smearing and marking

Failure: carrying today’s dollars into a later bid date

Fix: state the index and expenditure schedule, then update the forecast when procurement slips.

Failure: using one contingency percentage for every phase

Fix: tie separate allowances to design maturity and a risk register; reduce them only as risks are resolved.

Failure: ignoring occupied-campus logistics

Fix: price swing space, decanting, temporary services, protection, phased commissioning, moves and staff transition before approving the program.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Failure: comparing alternatives with different boundaries

Fix: normalize capacity, site, performance, opening date, owner costs, escalation and contingency before selecting new construction, renovation or an addition.

What a decision-ready school budget should show

A credible estimate lets a board, superintendent, facilities team or funder answer five questions without interpreting hidden assumptions:

  • What is being built, for how many students and to which performance standard?
  • Which local projects or bids support the building rate, and what does that rate include?
  • What land, site, professional, owner and temporary-facility costs sit outside the building contract?
  • How has the estimate been converted to the planned spending year?
  • Which risks remain, how much reserve covers them and when will the estimate be independently reviewed?

If any answer is unclear, the estimate is not finished—regardless of how many decimal places appear in the total.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Leave a Reply

Your email address will not be published. Required fields are marked *

What’s actually slowing this PC down?

Pick the symptom - the matching free tool is one click away.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Recommended PC Tool
Recommended PC Tool
Outdated Drivers Are Slowing You DownFree scan - exact matches
Windows Errors? Fix Them Before They SpreadFree repair scan

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.