Start with a defined scope, not a headline price. A data-center cost-per-megawatt figure is useful only when you state the market, price date, capacity denominator, cooling and building form, and exactly what the number includes. JLL’s 2026 global benchmark is $11.3 million per MW for 2026, but it covers shell and core for a single-tenant, 50 MW, air-cooled facility and excludes land and active IT equipment. A modern greenfield project in the United States or Canada can benchmark at $17.6 million per MW under Cushman & Wakefield’s different scope, which also excludes chips and GPUs.
The practical way to prepare a preliminary capital budget is to use a matching benchmark as a cross-check, then price the actual site, utility connection, schedule, technical brief, tenant fit-out and uncertainty. The guide below shows how to do that without turning unlike numbers into a misleading “all-in” rate.
As an Amazon Associate I earn from qualifying purchases.
What a data-center cost-per-MW estimate actually tells you
“Cost per MW” is a ratio, not a complete budget. The numerator might mean shell-and-core construction, a greenfield development, or a wider owner-funded program. The denominator might be IT load, utility service capacity, gross facility demand, or another engineering measure. Those choices can produce materially different results for the same site.
Do these 3 things before closing this tab:
1Scan for outdated or missing drivers - takes under a minute2Clear out junk files and repair common Windows errors3Fix the driver behind crashes, sound loss and screen glitchesEvery preliminary estimate should therefore place these items next to the figure:
#1 Best Overall
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
- Geography and market: city, country and any local labor, land or utility conditions.
- Price vintage: the month or year to which prices are current, plus the escalation assumption for later spending.
- Capacity basis: IT capacity, utility capacity, critical facility load or another explicitly defined denominator.
- Facility form: single-story or multistory, air-cooled or liquid-cooled, new build or conversion, and the planned redundancy and resilience level.
- Workload and density: conventional enterprise demand, high-density compute or an AI deployment that needs a substantial tenant technology fit-out.
- Cost boundary: what is included, excluded, supplied by a utility, paid by a tenant or still unpriced.
Without those labels, two apparently precise figures can be incomparable. A benchmark is best used to test whether an early concept is in the right order of magnitude, not as a bid or a funding commitment.
Current benchmarks and their boundaries
The following figures are useful reference points because their publishers state important assumptions. They are not interchangeable totals.
| Publisher and date | Figure | What it covers | Important exclusions or limits |
|---|---|---|---|
| JLL Research, 2026 Global Data Center Outlook | $7.7 million/MW in 2020; $10.7 million/MW in 2025; $11.3 million/MW forecast for 2026 | Average global construction cost for a single-tenant, 50 MW, air-cooled data center; shell and core | Land acquisition and active IT equipment are excluded; tenant technology fit-out is separate |
| Cushman & Wakefield, 2026 guide | $17.6 million/MW average | Greenfield development cost for the most modern facilities in the United States and Canada | Chips and GPUs are excluded; market and workload variation is significant; scope is not the same as JLL’s shell-and-core measure |
| Turner & Townsend, 2025–2026 index | Indicative dollar-per-watt benchmarks across 52 markets | Cross-market construction-cost comparison based on a survey of 250 experts | The landing-page information does not establish enough detail to reconcile every cost boundary with the other benchmarks |
JLL’s series implies a 7% compound annual growth rate from 2020 to 2025. That trend is a time-series observation from JLL’s stated benchmark, not a guaranteed escalation rate for a particular project.
JLL market ranges for 2026
JLL’s listed 2026 market estimates range from $6 million per MW in Mumbai to $18 million per MW in Tokyo. Each is a shell-and-core estimate on the same stated 50 MW, single-tenant, air-cooled basis, with land and active IT excluded.
| Market | JLL 2026 estimate per MW |
|---|---|
| Mumbai | $6 million |
| Dallas | $10–11 million |
| Phoenix | $10–11 million |
| Atlanta | $10–11 million |
| Dublin | $10–11 million |
| Seoul | $9–12 million |
| Northern Virginia | $11–12 million |
| Paris | $11–12 million |
| Amsterdam | $11–12 million |
| Sydney | $11–12 million |
| Frankfurt | $11–13 million |
| Chicago | $12–14 million |
| London | $12–14 million |
| Singapore | $12–15 million |
| Tokyo | $18 million |
These ranges should not be expanded into a full project budget. In particular, a low market benchmark does not mean that land, interconnection, taxes, tenant equipment or schedule risk will be low.
Step 1: Define the project before multiplying anything
Write a one-page basis of estimate before selecting a rate. The document should be specific enough that a cost consultant, utility or contractor can identify what is being priced.
Record the location and delivery strategy
- City, country and candidate parcel or powered-land area.
- New greenfield build, expansion, conversion or leased shell.
- Target energization date, construction start and required operating phases.
- Whether the owner or a tenant funds the building, utility work, fit-out and equipment.
Define the capacity denominator
State whether “MW” means planned IT load, utility service capacity, gross facility demand, critical load or another measure. Do not silently treat these as equivalent. If the project uses a utility-capacity figure but the benchmark uses IT load, obtain the engineering relationship between them and show the conversion assumption. If that relationship is not yet known, keep both figures visible instead of forcing a single rate.
Recommended Free Tools
Rank #2
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Both tools are designed to fit into difficult to reach spaces
- Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
- Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
Describe the technical brief
- Number of phases and the MW delivered in each phase.
- Redundancy and resilience target, including any requirement for concurrently maintainable or fault-tolerant systems.
- Rack density and the share of high-density or liquid-cooled halls.
- Air-cooled, direct liquid-cooled or hybrid cooling concept.
- Single-story, multistory or a combination.
- Intended workload, including whether AI infrastructure is planned.
- Security, office, storage, loading, fuel and other owner requirements that affect the building.
At concept stage, these descriptions can be ranges. The important point is to expose them so that a later estimate can change one assumption at a time.
Step 2: Select a benchmark with matching scope
Use JLL’s shell-and-core figure as a global early construction comparison when the proposed facility resembles its stated 50 MW, single-tenant, air-cooled basis. Use Cushman & Wakefield’s $17.6 million-per-MW figure as a North American greenfield development cross-check for a modern facility, while preserving its different scope and its exclusion of chips and GPUs. Use Turner & Townsend’s index as an additional location check where its detailed market data and definitions are available.
Do not average these sources into a synthetic industry price. A mathematical average would hide the fact that the geography, development boundary and capacity assumptions differ. Instead, create a comparison note with four columns:
- Publisher’s stated figure and price year.
- Capacity basis and facility assumptions.
- Included and excluded work.
- Reason the benchmark is or is not comparable with the project.
If no benchmark matches the project’s scope, retain the nearest reference as a sanity check and mark the unmatched items for local pricing.
PC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Crashes, No Sound, or Screen Glitches?
Random freezes, missing sound and display glitches usually trace back to one bad driver. Find and replace yours safely.Free scan · under a minuteStep 3: Build an explicit cost map
A preliminary capital budget should show the categories that can move independently. At minimum, create the following lines and assign a status to each: included, excluded, utility-supplied, tenant-funded or unpriced.
| Cost category | Questions to answer | How to price it at concept stage |
|---|---|---|
| Land and site work | What is the purchase or lease price? Are grading, demolition, roads, drainage, remediation and security included? | Use a parcel-specific land proposal and a civil/site-work opinion based on surveys and geotechnical information. |
| Utility connection and power infrastructure | Who pays for the interconnection, substation, feeders, transformers, switchgear and studies? What capacity and energization date are committed? | Obtain a written utility scope and an allowance from an electrical designer or contractor for owner-funded works. |
| Shell and core | What building structure, envelope, slabs, fire protection, internal roads and base-building systems are included? | Apply a clearly matched construction benchmark, then validate with a local concept estimate. |
| Mechanical and cooling systems | Are chillers, heat rejection, pumps, controls and distribution part of shell-and-core or a separate package? What percentage of halls is liquid-cooled? | Develop an equipment schedule and request budget quotes; identify any premium for the selected cooling design. |
| Tenant IT equipment and fit-out | Are servers, storage, network gear, racks, busways, in-row systems and commissioning included? Is the tenant purchasing them? | Use a tenant equipment list and vendor budgetary quotations. Keep chips and GPUs separate where the benchmark excludes them. |
| Owner-side and project costs | Have design, permitting, legal, insurance, financing, commissioning, taxes, program management and temporary facilities been included? | Build a project-specific allowance with the owner’s advisers; label each allowance and its basis. |
| Contingency and escalation | What uncertainty remains in scope, quantities, price date, schedule and site conditions? | Show a base estimate, explicit assumptions, escalation date and contingency as separate lines rather than burying them in unit rates. |
JLL explicitly excludes land and active IT from its shell-and-core benchmark. Cushman & Wakefield identifies power infrastructure and contingencies as major parts of a greenfield development. Those facts support a visible cost map, but they do not establish a universal percentage allocation for every project category.
How much can design choices change the estimate?
Liquid cooling
JLL states that liquid-cooled facilities carry a 10% cost premium in the context of its benchmark. Treat this as publisher guidance for that benchmark, not as a universal multiplier. Confirm whether the premium applies to the whole shell-and-core scope or only affected mechanical and distribution packages, and then price the actual proportion of liquid-cooled capacity.
Rank #3
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
Multistory construction
JLL states that multistory construction in the Americas adds 20% to construction costs in its benchmark context. The adjustment should not be applied automatically to every project: height, structural grid, logistics, seismic design, site constraints and the reference scope all matter. Obtain a structural concept and a local contractor check before carrying the adjustment into a funding case.
AI and high-density tenant fit-out
JLL says tenant technology fit-out for AI infrastructure can reach $25 million per MW. This is separate from its shell-and-core number and can exceed the building cost in a high-density deployment. Treat it as a technology package with its own equipment list, delivery schedule, power-distribution requirements, cooling interfaces and commissioning plan. Do not add it silently to a construction benchmark.
How to price the actual site and schedule
Benchmark selection is only the first pass. A site-specific budget needs dated local evidence because the largest risks may sit outside the building rate.
Confirm power availability
- Request the utility’s written indication of available capacity, point of connection, required studies, customer-funded works and target energization date.
- Separate utility-owned infrastructure from owner-funded substations, feeders, transformers, switchgear and on-site generation.
- Record whether capacity is firm, conditional, phased or dependent on network upgrades.
- Price temporary power and schedule exposure if permanent service will not be available for testing or commissioning.
Power scarcity and powered-land premiums can change both land value and schedule. A parcel with a low purchase price is not economical if interconnection work or waiting time defeats the operating plan.
Obtain local construction and labor input
- Ask a local contractor or cost consultant for a concept estimate tied to drawings, equipment assumptions and a stated price date.
- Identify skilled-trade availability, wage assumptions, working-hour restrictions and local productivity.
- Request budget quotes for long-lead electrical and mechanical equipment, with validity periods and escalation language.
- Test material inflation and currency exposure where equipment is imported.
Cushman & Wakefield identifies skilled-trade shortages, long equipment lead times, wage increases and material inflation as active constraints. Carry them as schedule and cost risks rather than hiding them in an arbitrary unit-rate uplift.
Align the estimate with the procurement schedule
Prepare a procurement register showing required-by dates for transformers, switchgear, generators, cooling equipment, controls, structural steel and tenant systems. For each item, record the quote date, lead time, manufacturing location, deposits, testing requirements and the consequence of late delivery. A price that is valid for 30 days is not a firm budget for a two-year program.
Worked examples: use the math without overstating precision
Example: a shell-and-core starting point
Suppose a concept calls for 50 MW on a basis comparable to JLL’s 2026 global air-cooled, single-tenant benchmark. Multiplying 50 MW by $11.3 million per MW produces $565 million as an indicative shell-and-core starting point. It is not an all-in project budget: land, active IT and other unpriced categories remain outside that arithmetic.
Rank #4
- Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
- Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
- Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
- Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
- Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed
Example: a market-range sensitivity
For the same 50 MW denominator, JLL’s published range would produce approximately $300 million at the $6 million-per-MW Mumbai reference and $900 million at the $18 million-per-MW Tokyo reference, before the exclusions stated by JLL. The spread demonstrates why geography and scope must accompany the number; it is not a quotation for either site.
Example: separating AI fit-out
If a project has 50 MW of AI tenant capacity and the tenant fit-out reaches JLL’s stated upper figure of $25 million per MW, the technology package could be as much as $1.25 billion. Added to the illustrative $565 million shell-and-core starting point, the arithmetic reaches $1.815 billion before land, utility work, owner costs, contingency and other exclusions. The calculation is a sensitivity case, not a prediction: actual equipment mix, density, purchasing strategy and the share of AI capacity determine the result.
The Tool Desk
Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Contingency, escalation and uncertainty
Keep uncertainty visible in three separate places:
- Base estimate: the priced scope at a stated date.
- Escalation: the time and market movement between that date and each expected spend.
- Contingency: an allowance for identified design, quantity, site, schedule and procurement uncertainty.
Cushman & Wakefield reports contingencies as the second-largest category in its average greenfield development cost and reports power infrastructure at an average 21% of total greenfield development cost. That 21% is a publisher-reported average for its stated greenfield context; it is not a default allocation for every project. The available benchmarks do not establish one universal contingency percentage, so set contingency through a risk register and update it as design maturity improves.
Use a risk register rather than a hidden buffer
- List each unresolved item, such as geotechnical conditions, utility scope, permitting, equipment lead time or tenant specification.
- Assign an owner, probability, cost effect and schedule effect.
- State whether the item is included in the base estimate, an allowance or contingency.
- Remove or reduce the allowance when a quote, design decision or utility commitment resolves the risk.
This approach lets decision-makers see why the budget changes instead of treating every revision as unexplained cost growth.
How to compare two data-center cost estimates
Before comparing figures, normalize the following axes:
| Comparison axis | Check |
|---|---|
| Geography and market | Are the sites subject to similar land, labor, tax, utility and logistics conditions? |
| Construction versus greenfield scope | Does one figure cover only shell and core while the other includes development, power or owner costs? |
| Cooling design | Are both air-cooled, both liquid-cooled, or is one a hybrid with a different density? |
| Building form | Are both single-story, or does one include a multistory premium? |
| Workload and density | Does either figure include high-density or AI tenant technology? |
| Land, utility work and IT | Which party funds each item, and is it included, excluded or merely unpriced? |
| Contingency and price date | Are allowances and escalation stated on the same date and in the same currency? |
| Capacity denominator | Are both rates based on the same definition of MW? |
If any answer is unknown, label the comparison “not directly comparable” and identify the missing information. A precise-looking conversion is less useful than an explicit limitation.
Free tools Windows power users keep installed
One-click scans. No signup required.
A practical preliminary-budget workflow
- Write the basis of estimate. Capture location, phase, MW definition, facility form, cooling, density, resilience, workload, schedule and ownership boundaries.
- Choose one primary benchmark. Select the source whose geography and scope are closest; retain other publishers as cross-checks, not blended averages.
- Build the cost map. Separate land, site work, power, shell and core, cooling, tenant fit-out, owner costs, escalation and contingency.
- Mark every boundary. For each line, record included, excluded, utility-supplied, tenant-funded or unpriced.
- Apply only documented adjustments. Consider JLL’s stated liquid-cooling and multistory guidance only when the project matches its context, and carry AI technology separately.
- Request local evidence. Obtain utility correspondence, land terms, civil information, contractor input and budgetary equipment quotations.
- Model phases and dates. Allocate capacity and spending by phase, then align escalation and long-lead procurement with the schedule.
- Run sensitivities. Test power-delay, land, cooling, density, multistory and tenant-fit-out cases without changing the denominator silently.
- Publish the estimate with an update date. Show base cost, assumptions, exclusions, escalation, contingency and the next information needed to improve accuracy.
Common estimating mistakes and their fixes
Calling a shell-and-core rate “all-in”
Why it fails: land and active IT may be excluded, while utility and owner costs remain unpriced.
Fix: use a cost map and title the figure by its boundary.
Best Value
- Milwaukee Ink all Fine Point Marker, Black, 4 Per Pack
- 4 per pack Features Clog Resistant Marker Tip Writes through Dusty, Wet and Oily Surfaces Durable Marker Tip for Writing on Concrete, OSB and Rough Surfaces
- Clog resistant tip writes on dusty, wet and oily surfaces and is optimized for rough surfaces such as OSB, cinderblock and concrete
- Hard hat clip- attaches for easy access
- Quick dry time with reduced smearing and marking
Dividing by the wrong MW
Why it fails: utility capacity, facility demand and IT load are not automatically equivalent.
Fix: define the denominator and show any engineering conversion.
Averaging incompatible benchmarks
Why it fails: a global shell-and-core figure and a North American greenfield figure measure different things.
Fix: keep separate scenarios and explain the scope difference.
Applying a universal percentage breakdown
Why it fails: the available sources identify major categories but do not support one line-item allocation for every project.
Fix: obtain project-specific quotes and retain allowances until scope is defined.
Quick wins for a faster PC:
Clear out junk files and repair common Windows errorsFree Scan →Scan for outdated or missing drivers - takes under a minuteDriver Scan →Leaving power until the end
Why it fails: interconnection, network upgrades and energization dates can determine whether the site works at all.
Fix: make the utility scope an early gated deliverable.
Hiding AI equipment in the building rate
Why it fails: tenant technology can be many times the shell-and-core cost and may have a different buyer and schedule.
Fix: create a separate IT fit-out package with its own equipment list and commissioning plan.
Using an old quote as current money
Why it fails: labor, materials, equipment lead times and currency can move during a long program.
Fix: record quote validity, price date and escalation for every major package.
What to hand to a cost consultant or development team
A useful request for proposal should include the technical brief, site information, utility correspondence, phasing plan and the cost boundary you want reported. Ask for:
- A base estimate with quantities or measurable scope behind each major line.
- Separate totals for land, utility and power infrastructure, shell and core, mechanical and cooling, tenant fit-out, owner costs, escalation and contingency.
- A statement of the capacity denominator and any conversion assumptions.
- Assumptions, exclusions, allowances and items supplied by others.
- Low, base and high sensitivities for unresolved site, power, schedule and workload risks.
- A price date, currency, validity period and update mechanism.
- A procurement and commissioning schedule linked to the cash-flow forecast.
John McWilliams, Head of Data Center Insights at Cushman & Wakefield, summarized the location challenge on September 3, 2026: “The data center industry is entering a new phase where access to power, land, and skilled labor are increasingly determining where growth can occur.” A budget that prices only the building misses those constraints.
The decision rule for an early capital budget
Use a cost-per-MW figure to test a concept, not to approve construction. The estimate is decision-ready only when a reader can answer four questions without guessing:
- What exactly does the MW denominator measure?
- Which geography, price date and benchmark scope produced the rate?
- Which costs—especially land, power, IT and contingency—are outside it?
- What site-specific quotes or commitments will replace the allowances next?
When those answers are documented, the preliminary budget becomes a traceable model that can be updated as the utility commits capacity, design fixes the cooling and density, tenants define their equipment and contractors return current prices.