Black Friday PreviewAmazon USBlack Friday preview: compare before the rush hitsAmazon US: current deals, useful picks and tech finds.Check DealsSlow PC?RecommendedPC slow today? Run a repair scan before it gets worseResolve common Windows issues and optimize system performance.Scan NowBlack Friday PreviewAmazon USThe best pick may show up before FridayAmazon US: current deals, useful picks and tech finds.See Picks×
BETTESWORTHConstruction
Bagmati Province

Gautam Buddha International Cricket Stadium construction delayed: progress, costs and completion outlook

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Some links on this page are affiliate links: if you buy through them we may earn a commission, at no extra cost to you.

Gautam Buddha International Cricket Stadium in Bharatpur Metropolitan City-15 is behind schedule. The latest report, dated October 27, 2026, puts physical progress at 65% and says a January completion is unlikely after delayed provincial funding, a work stoppage, slow execution, rising material costs, weather disruptions and technical complications from building on older structures.

The contract deadline is also reported inconsistently: Nepal News and Republica identify January 6, 2027, while Onlinekhabar reports January 11. The contractor is preparing an extension request, and city officials have indicated that roughly three to four additional months could be required if the pace does not improve.

As an Amazon Associate I earn from qualifying purchases.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What is the latest progress on Gautam Buddha International Cricket Stadium?

Onlinekhabar reported on October 27, 2026, that the stadium was 65% physically complete. That figure does not mean the venue is close to operational: major playing-field work, electrical installation and finishing activities remain open, while funding interruptions have already stopped work for a period.

Report date Physical or financial status Work and schedule details
July 2026 48–50% physical completion One spectator tower and one parapet were complete; five pitches and supporting infrastructure remained underway. Nepal News listed January 6, 2027, as the deadline.
August 2026 About 60% physical progress; 45% financial progress Republica reported about five months remaining before January 6, 2027.
October 27, 2026 65% physical progress Onlinekhabar reported a funding-related stoppage and said the January target was unlikely. It gave January 11 as the completion date.

The different physical and financial percentages are not interchangeable. Physical progress describes completed construction, while financial progress reflects the value of work paid or recognized under the contract.

Popular on Amazon
SS Bolt Cricket Kashmir Willow Cricket Bat,Bat Cover Included : Adult Size, Short Handle - Full Size
  • SS made up of kashmir willow
  • Grade 5 willow
  • Weights 1280 grams
  • best peformance with tennis ball
  • lasts 20 overs

Why is Gautam Buddha Stadium construction delayed?

The immediate trigger was late release of Bagmati Province funds, but several problems have compounded one another. The contractor also needs to increase its work rate to recover lost time.

Provincial payments arrived late

Bharatpur Metropolitan City expected Bagmati Province to finance 70% of the project, with the city covering 30%. Engineer Adarsh Pokhrel said delayed provincial budget release affected construction. Republica reported that work stopped for about five months while a promised Rs 90 million provincial allocation was not released.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Contractor engineer Dharmendra Gupta said, “If the amount had been released on time, the work would have progressed according to schedule.” The interruption is significant because specialist field work and finishing trades cannot all be compressed safely into the final weeks.

The contractor has also been slow

Officials and the contractor agree that the remaining work must accelerate. The October report says the company’s pace has been another factor in the delay, separate from the payment stoppage.

Also popular on Amazon
Kookaburra Kahuna Pro 8.1 Cricket Bat Made from Kashmir Willow, Lightweight and Durable Cricket Bat for All Levels, Classic Kahuna Design (Short Handle)
  • Handmade Willow Bat: This Kookaburra Kahuna Pro 8.1 cricket bat is meticulously handcrafted from premium Kashmir Willow for exceptional performance.
  • 【Optimal Weight Distribution】The bat features a carefully balanced weight distribution, ensuring optimal power transfer and control during swings.
  • Textured Handle: The handle is coated with a textured grip, which provides a secure and comfortable hold for improved grip and swing control.
  • 【Massive Sweet Spot】The large sweet spot of the bat maximizes the area for powerful, well-timed hits and delivers maximum energy transfer.
  • Robust Construction: Made with great attention to detail, this bat offers long durability to withstand the rigors of intense play.

Prices, weather and inherited structures complicated execution

Contractor manager Samrat Silwal cited higher material prices, changing weather and the need to build on old structures. He said technical decisions sometimes conflicted as the team adapted the new work to what was already on site.

The cricket field is a critical path

Republica reported that only about 20% of field work was complete in August. The field requires four soil layers and internal pipes, followed by soft topsoil and Baruna grass. Materials were still arriving, and rain slowed the sequence. Because the playing surface depends on several layers being installed in order, late field work can delay practical readiness even when stands appear substantially complete.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What work is still unfinished?

The open items are concentrated in the field, services and finishing rather than a single remaining structure.

Playing surface and drainage-related layers

  • Four soil layers and internal field pipes must be installed.
  • Soft topsoil and Baruna grass remain to be laid for the playing surface.
  • Field materials and weather-sensitive work continue to affect the schedule.

Parapets and spectator structures

By October, two parapets were reported complete. The third was about 90% complete and the fourth about 70% complete. Earlier reporting had recorded one spectator tower as complete, showing progress but not a finished venue.

Also popular on Amazon
Reebok Blaze Plastic Cricket Bat – Full Size 34" × 4.5", Lightweight PVC, Durable Design for Practice & Recreational Play, Suitable for Ages 15+ (Green)
  • Ideal for players aged 15+ years and above
  • Made from high-grade PVC / plastic material for durability and lightweight play
  • Ergonomic design offers good grip and control for casual / recreational use
  • Suitable for use with different types of balls (tennis, soft rubber) for practice or fun matches
  • Lightweight construction helps reduce fatigue and aids stroke development

Services and finishing

  • Electrical connection and installation were still pending in the October report.
  • Earlier progress reports also listed plumbing, painting, tiling and other finishing work as incomplete.

How much does the stadium project cost?

The reported contract value increased after a variation order, while separate public funding figures describe allocations and money already invested.

Amount What it represents Source and qualification
Rs 785.09 million Original contract value, including VAT Reported by Onlinekhabar in 2026
Rs 862.48 million Reported contract value after the first variation order Onlinekhabar, 2026
Rs 230 million Bagmati Province investment reported to date myRepublica, 2026
Rs 70 million Bagmati Province allocation for the current fiscal year myRepublica, 2026
Rs 140 million Bharatpur Metropolitan City allocation for the current fiscal year myRepublica, 2026
About Rs 220 million Additional provincial funding that may be needed Estimate from city engineer Santosh Acharya, reported by myRepublica in 2026

The first variation order was approved shortly before the original construction period ended. The contractor says the added scope and higher costs make the original period unrealistic; the revised contract value should therefore not be read as a final operating or total-life cost for the stadium.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

When will Gautam Buddha International Cricket Stadium be completed?

No single completion date is settled in the available reports. Nepal News and Republica identify January 6, 2027, as the contract deadline, while Onlinekhabar’s October 27 report says January 11. That five-day discrepancy may reflect date conversion or different references to the contract period, so neither date should be treated as uncontested.

The contractor was preparing an extension application, which Onlinekhabar said must be filed 35 days before contract expiry. Dharmendra Gupta estimated that about three extra months may be needed if work does not accelerate. City engineer Santosh Acharya warned that three to four additional months could be necessary at the current pace.

Also popular on Amazon
NERF Foam Cricket Starter Set - 30" Bat + Balls + Wickets | Complete Starter Kit, Includes Balls + Stumps, Comfort Grip Handle, Indoor + Outdoor Play, Kids + Adults
  • FULL SET: Get outside and start the cricket fun in no time with this all-in-one cricket set designed for kids and adults!
  • FOAM CRICKET BAT: This set comes with a 30" NERF foam cricket bat for fun, kid-friendly play
  • CRICKET BALLS: Set comes with (2) NERF foam cricket balls which are perfect for playing on any surface indoors or outdoors
  • WICKETS INCLUDED: Set also includes (3) stumps and (2) bails so you can set up your field and play!
  • FUN FOR ALL: This complete cricket starter set is perfect for kids and adults who want to get moving and play cricket with family and friends!

Acting Mayor Chitrasen Adhikari said, “We have been telling the construction company to complete the stadium quickly. It won’t be very late now.” Engineer Acharya likewise said, “Payment will not be stopped now. If the contractor accelerates the work, it can be completed within the given timeframe.” Those statements describe an expectation, not an approved extension or a guaranteed opening date.

How did the project reach this point?

The Dhurmus–Suntali Foundation began the project in 2019 under a much larger public plan, then halted work in 2021 after it could not raise enough money. The foundation formally asked Bharatpur Metropolitan City to take ownership on December 17, 2021. Republica reported that the foundation cited Rs 184.3 million in debt, while completed work was valued at Rs 571.2 million.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The city later revived the project with federal, provincial and local support. In 2024 it signed a contract with Himalayan–Kalinchowk BBR JV, with Bagmati Province responsible for 70% of financing and Bharatpur Metropolitan City for 30%.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Will the stadium be ready for international matches?

The reported 65% completion level and the unfinished playing surface, electrical work and finishes mean the stadium cannot yet be treated as match-ready. The reports do not establish a confirmed international fixture or an approved operational date. Readiness will depend first on completing the remaining construction and resolving the contract extension and funding schedule.

Also popular on Amazon
SS T20 Legend County Premium English Willow Cricket bat - Limited Edition, Mens Size
  • All new SS T20 Legend County EW cricket bat is launched by Sareen Sports in limited quantities, with hand selected English willow wood
  • Hand Selected premium grade English willow that comes with 5-7 straight grains structure and weigh less than or equal to 2.9 Oz or1160 Grams
  • This Cricket bats Bow is designed to enhance position of the hands by placing them ahead of the ball which is an essential for giving power to your shots playing with leather ball.
  • Bat handle is 9 Piece rounded Handle, made of Sarawak Combination that absorbs shock when the leather balls ping the bat, added with 3 tones aqua grip for maximum protection to offer greater control
  • All bats are authetic & genuine and can be verified with SS hologram that is visible at the back of the bat

What should be watched next?

  • Whether Bagmati Province releases the remaining committed funds on schedule.
  • Whether the contractor increases manpower and output enough to recover the stoppage.
  • Completion of the four-layer field build-up, pipes, topsoil and Baruna grass.
  • Electrical installation and the outstanding plumbing, painting, tiling and other finishes.
  • Approval of an extension and the date ultimately recorded in the contract documents.

Frequently Asked Questions

Why did the Dhurmus–Suntali Foundation leave the stadium project?

The foundation stopped work in 2021 after failing to raise sufficient money and formally sought a handover to Bharatpur Metropolitan City on December 17, 2021. Republica reported that it cited Rs 184.3 million in debt against completed work valued at Rs 571.2 million.

What does the first variation order mean for the stadium contract?

A variation order changes the contracted scope, price or both to account for approved additional work. In this case, the reported value moved from Rs 785.09 million including VAT to Rs 862.48 million, and the order was approved near the end of the original construction period.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Who is responsible for financing the revived project?

The 2024 arrangement assigns 70% of financing to Bagmati Province and 30% to Bharatpur Metropolitan City. The delayed release of the provincial share became a direct cause of the work stoppage reported during construction.

Has an international match been scheduled at the stadium?

The cited progress reports do not announce a confirmed international fixture or an operational opening date. Until construction, services and the playing surface are complete and the schedule is formally settled, a match date remains unconfirmed.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply. Prices as of November 15, 2026 6:34 pm GMT+0000.
Recommended PC Tool
Recommended PC Tool
Outdated Drivers Are Slowing You DownFree scan - exact matches
PC Slower Than It Used to Be?Free scan - under a minute

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.