DriversRecommendedOutdated drivers can make a good PC feel brokenScan driver issues before chasing fixes manually.Scan NowBlack Friday PreviewAmazon USBlack Friday preview: compare before the rush hitsAmazon US: current deals, useful picks and tech finds.Check DealsPC HealthRecommendedCrashes, freezes, slowdowns? Check your PC nowSpot repairable issues before they interrupt work.Check PC×
BETTESWORTHConstruction

Force Majeure in Construction Contracts: How to Decode Triggers, Notice and Relief

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Some links on this page are affiliate links: if you buy through them we may earn a commission, at no extra cost to you.

Force majeure terms in a construction contract decide when an extraordinary event can excuse, suspend or delay a party’s performance. The answer is never determined by the words “force majeure” alone: you must read the defined events, the required causal link to a particular obligation, notice and evidence deadlines, mitigation duties, and the remedy alongside the governing law. For a contractor, employer or supplier, the practical sequence is to identify the precise trigger, show how it affected the affected work, give compliant notice, preserve proof and then apply the clause’s time, money and termination provisions. This guide explains how to do that, using an international framework and clearly labelled illustrations from English and Canadian sources.

What does force majeure mean in a construction contract?

A force majeure clause allocates the consequences of a specified impediment to contractual performance. Depending on its wording, it may excuse a breach, suspend an obligation, extend time, shift particular costs, or permit termination after a prolonged disruption. It does not automatically cancel the contract, waive every deadline or cover every event outside a party’s control.

As an Amazon Associate I earn from qualifying purchases.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Construction agreements commonly address events such as natural disasters, war, government orders, epidemics, strikes, transport interruption and utility failure. Whether an event qualifies depends on the actual definition, any exclusions, the required level of impact and the law governing the contract. A clause that lists “flood” may not cover every period of heavy rain; a clause requiring prevention or impossibility may not respond to a disruption that merely makes work more expensive.

UNIDROIT’s international model states that non-performance is excused where the party proves an impediment beyond its control that could not reasonably have been taken into account when the contract was concluded or avoided or overcome, including its consequences. The model is a useful analytical framework, not a universal rule: UNIDROIT says its provision covers ground addressed by several legal doctrines but is identical to none of them. Read the contract and governing law before relying on it.

Popular on Amazon
Sale
DEWALT 20V MAX Cordless Drill and Impact Driver (DCK240C2) | Power Tool Combo Kit, Includes 2 Batteries, Charger and Bag
  • Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
  • Both tools are designed to fit into difficult to reach spaces
  • Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
  • Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
  • One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips

“Non-performance by a party is excused if that party proves that the non-performance was due to an impediment beyond its control and that it could not reasonably be expected to have taken the impediment into account at the time of the conclusion of the contract or to have avoided or overcome it or its consequences.” — UNIDROIT Principles of International Commercial Contracts, Article 7.1.7(1)

How should you decode the trigger language?

Start with the words that define the event, rather than with the label in the heading. Mark each listed event, the catch-all wording, exclusions and any references to government action, labour events, supply-chain interruption, epidemic or natural disaster. Then ask whether the list is exhaustive, illustrative or linked to a general standard. That is a question of wording and applicable law, not a presumption.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Clause feature Question to ask Construction example
Named events Is the event expressly included, and is it defined? A “government order” may include a legally binding site closure, but not an informal recommendation.
Catch-all phrase Does “any event beyond control” expand the list or merely introduce it? Read the grammar and surrounding examples; a court may treat examples as limiting context.
Exclusions Are shortages, price rises, insolvency, design errors or subcontractor failure carved out? An excluded “lack of funds” will not become force majeure because a supplier’s prices rose.
Threshold Must the event prevent, make impossible, materially hinder or merely delay performance? “Prevents” is generally more demanding than “materially affects,” but the contract and law control.

UNIDROIT guidance advises parties to tailor a clause to their specific needs. In a construction contract, tailoring should distinguish events affecting the site, labour, materials, logistics, permits and access, and should state which party bears each resulting risk.

How do you prove that the event caused the delay or non-performance?

The event itself is not enough. Connect it to a particular contractual duty and show the route from event to consequence. Identify the affected activity, the date the impact began, the contractual completion or delivery obligation, and why the work could not be performed by another reasonable method.

  1. Identify the duty. Is the issue a possession date, excavation, shipment of equipment, testing, commissioning, payment, design submission or completion milestone?
  2. Establish the critical impact. Use the approved programme, logic links and contemporaneous updates to show whether the affected activity controlled completion or only created float-consuming delay.
  3. Separate direct from indirect effects. A government closure of the project site is different from a supplier’s decision to allocate scarce stock elsewhere. Explain each causal step.
  4. Consider alternative performance. Could another route, supplier, crew, sequence, design or delivery method have satisfied the duty? If so, document why it was unavailable, unsafe, unlawful or commercially unreasonable under the clause.
  5. Quantify the period and consequence. State the days of delay, the work affected and any additional cost only where the clause provides that relief.

The UK Supreme Court’s decision in RTI Ltd v MUR Shipping BV [2024] UKSC 18 concerns negotiated wording, causation and reasonable steps in its English-law context. It should not be generalized into a universal rule for construction contracts. The decision illustrates why the exact text and the relationship between the event and the obligation matter.

What do control, foreseeability and mitigation require?

Many clauses ask whether the impediment was beyond the affected party’s control, whether it could reasonably have been anticipated at contracting, and whether it could have been avoided or overcome. Some clauses use different tests or allocate particular risks expressly. Do not substitute the UNIDROIT model for the negotiated wording.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

“Foreseeable” is assessed at the time of contracting, not with hindsight after the disruption. A known seasonal weather pattern, an announced regulatory change or an obvious supply constraint may be treated differently from an unforeseeable event, depending on the contract and law. A party may also lose relief if it assumed the relevant risk elsewhere in the agreement.

Also popular on Amazon
Sale
Nicpro Mechanical Carpenter Pencils for Construction (Black, Red) With Case | Deep Hole Marker Pencil Set Includes Sharpener and 26 Refills, Comfortable Grip, Heavy Duty Woodworking Tools for Architect
  • Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
  • Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
  • Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
  • Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
  • Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons

Mitigation usually means taking reasonable steps to reduce the effect, not guaranteeing that the event will have no consequence. Examples include resequencing unaffected work, sourcing an alternative compliant material, applying for an available permit, protecting stored goods and communicating with the other party. Keep records of quotations, rejected alternatives, safety assessments and approvals so that the decision can be explained later.

What notice must you give under a force majeure clause?

Notice is often a condition of contractual relief or a separate source of liability. Find the deadline, permitted delivery method, recipient, required content, update duty and evidence requirements before sending anything. Under the UNIDROIT model, the notice describes the impediment and its effect on performance; late receipt can create liability for damage caused by the delay in notification.

A practical first notice should include:

  • the contract, package, purchase order or work section affected;
  • the event, date and location, with the clause subparagraph relied upon;
  • the specific obligation and milestone affected;
  • the facts establishing causation and the expected or known duration;
  • steps already taken and planned to avoid or overcome the effect;
  • the relief requested, such as an extension of time or suspension; and
  • a statement that evidence and periodic updates will follow, if the clause requires them.

Send the notice exactly as the contract requires—such as to a named contract administrator, by a specified portal or by formal email—and retain proof of delivery. Calendar every update date. If the event develops gradually, give an initial precautionary notice and update it as facts become reliable rather than waiting for a perfect forecast.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Check the consequence of a missed deadline. Some contracts make timely notice a condition precedent to any extension or payment; others preserve the underlying relief but impose damages caused by late notice. The contract’s wording and governing law decide which treatment applies.

What evidence should a construction team preserve?

Build an evidence file while the event is occurring. Preserve the executed contract and amendments, the force majeure definition, programmes and revisions, site diaries, labour and plant records, delivery tickets, supplier correspondence, notices, photographs, weather or authority records, meeting minutes and mitigation decisions. Keep versions with dates and authors so that the sequence cannot be reconstructed only from memory.

Link each record to an activity and period. For example, pair a road-closure order with delivery logs showing the blocked route, the alternative route assessment, the revised delivery date and the effect on the installation sequence. A general folder of news articles is weaker than contemporaneous project records tied to the contractual obligation.

What relief can the clause provide?

Read the remedy and duration provisions with the termination, payment, liquidated-damages, suspension and dispute clauses. Relief may be limited to the affected duty and a reasonable period; it may not cover every knock-on cost.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Also popular on Amazon
Push to Unlock, Katerk 6pcs 1/4 inch Hex Shank Screwdriver Bit Holder | Aluminum Alloy Drill Bit Holder Keychain Quick-Change Extension Bar Drill Screw Adapter, Black Carabiner, Tool Gifts for Men
  • 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
  • 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
  • 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
  • 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
  • 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
Possible consequence What to check
Excuse from performance Which duty is excused, and does the excuse last only while the impediment continues?
Extension of time Is the extension day-for-day, subject to concurrency rules, or limited by a notice condition?
Suspension Who may suspend, who pays protection and remobilisation costs, and what restart notice is required?
Cost relief Does the clause allow direct cost, overhead, escalation or only time relief? Are payment obligations excluded?
Termination After what period may either party terminate, and what happens to materials, demobilisation, payment and security?
Damages Does the clause suspend liquidated damages, preserve them for unaffected delay, or address only breach liability?

A temporary impediment does not necessarily end the contract. UNIDROIT’s model limits an excuse for a temporary impediment to a reasonable period in light of its effect and preserves specified rights. Your agreement may set a fixed number of days, require a termination election or apply a different standard.

Does force majeure excuse payment obligations?

Never assume it does. Payment clauses are often drafted separately, and some force majeure provisions expressly exclude money owed or amounts already due. Check whether the event actually prevents payment, whether an alternative payment method was available and whether another clause allocates insolvency, banking or currency risk.

Likewise, a material-price increase or loss of profitability is not automatically a force majeure event. It may be addressed by a price-adjustment, change-in-law or hardship mechanism instead. Use the clause that matches the risk rather than treating every commercial difficulty as an impediment.

How does force majeure differ from frustration or other delay rights?

Force majeure is primarily contractual: the parties define events and consequences in advance. Frustration is a legal doctrine that may apply where a supervening event radically changes or makes performance impossible, but its availability and effects depend on the governing law. A written force majeure clause may allocate the risk before a court reaches a frustration analysis.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Also distinguish force majeure from extensions for employer-caused delay, variations, changes in law, exceptionally adverse weather, suspension for non-payment and general claims for additional time. Each mechanism can have different notice, proof and cost rules. A notice should identify every potentially applicable contractual route without claiming inconsistent relief.

For Canadian federal procurement, the Office of the Procurement Ombudsman’s force majeure guidance discusses written clauses, notice and evidence and distinguishes their operation from the common-law doctrine of frustration. That is procurement guidance, not a rule for every Canadian or international construction contract.

Which governing law and forum apply?

Record the governing-law clause, dispute forum, contract type and any incorporated standard terms before reaching a conclusion. The same words can produce different results under English law, Canadian common law, civil-law systems or an international model clause. The forum may also affect how exclusions, causation, mitigation and notice conditions are interpreted.

Also popular on Amazon
Sale
Toolwiz Magnetic Pick Up Sweeper 17-inch Wide, 8.8 Lbs Magnet Pull Force | 8.8 Lbs, Rolling Magnetic Sweeper, Heavy Duty Magnet Pickup with Smooth Wheels, Yard Tools, Clean Nails for Construction
  • Toolwiz 17-inch magnetic sweeper maintaining a load capacity of up to 8.8 pounds provides a perfect solution to the problem of clearing small ferrous metal objects, such as nails, tacks, bolts, and metal shavings from workshops or garage floors.
  • Convenient and portable:17” is good for home, small workshop, or small yard as it is space-saving and more reachable for narrow areas. Perfect for collecting nails or small parts in the car, under the table, and in other nooks or crannies.
  • Upgraded Handle Design: The handle features a sturdy, non-telescopic design to completely prevent slipping during use. By simply adding or removing the extension poles, the height can be adjusted to 3 different lengths: 18.9" (48 cm), 32.5" (82.5 cm), and 42.5" (108 cm) from ground to top. This customizable height helps prevent back bending and muscle strain, making your cleaning tasks effortless
  • Flexible wheels: Upgrade wheel screws to avoid being too tight to spin or too loose. More comfortable 3-inch rubber wheels roll smoothly on carpet, grass, concrete, and hardwood floors. Just push and pull this rolling magnet-sweeper to pick up metal nails easily.
  • Lightweight materials: The magnetic nail sweeper's compact and lightweight design makes the sweeping can be done anywhere you want, Push or pull it under the furniture, passing through the workshop floor, driveway, mud, grass, and gravel.

For an English-law project, read the UK Supreme Court judgment in RTI Ltd v MUR Shipping BV [2024] UKSC 18 only as authority for its contractual context. For an international contract, the UNIDROIT guidance on managing contractual relationships and non-performance provides a disciplined way to analyse event definitions, causation, notice and consequences, while leaving the governing law in control.

What’s actually slowing this PC down?

Pick the symptom - the matching free tool is one click away.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What is a reliable step-by-step review method?

Use this sequence before asserting or rejecting a force majeure claim:

  1. Collect the controlling documents. Assemble the signed agreement, amendments, schedules, specifications, purchase orders, incorporated terms and governing-law and forum clauses.
  2. Map the trigger. Highlight the event list, catch-all language, exclusions, control and foreseeability tests, and any special wording for epidemics, government action, labour or supply interruption.
  3. Map performance. Name the duty, milestone, location and date affected. Test whether the event prevented, delayed or materially hindered that duty and whether another method was reasonably available.
  4. Map procedure. Calendar initial notice, updates, evidence delivery, meetings and claim-submission deadlines. Follow the prescribed recipient and method.
  5. Map mitigation. Record alternative suppliers, resequencing, protection, safety and regulatory steps, including why rejected options were not reasonable.
  6. Map consequences. Determine time relief, cost entitlement, payment treatment, liquidated damages, suspension rights, termination thresholds and reinstatement duties.
  7. Escalate the legal question. If the wording is ambiguous, the financial exposure is material or termination is contemplated, obtain advice in the governing jurisdiction before withholding performance.

What common mistakes undermine a force majeure position?

  • Relying on the label alone: “Force majeure” in a heading does not expand a narrow definition.
  • Proving the event but not causation: A regional disruption does not establish that this project’s critical activity was prevented.
  • Ignoring exclusions and assumed risks: Ordinary subcontractor failure, cash-flow problems or market volatility may be allocated elsewhere.
  • Sending late or incomplete notice: A factual email to the wrong recipient may not satisfy the agreed procedure.
  • Failing to mitigate: Doing nothing while unaffected work could proceed can reduce or defeat relief.
  • Claiming every consequence: Time relief does not automatically create a right to overhead, escalation or payment.
  • Stopping records too early: Continue updates until the impediment ends and the effect on the programme is resolved.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

How should parties draft a clearer construction force majeure clause?

Drafting should identify the events and exclusions, the required impact, control and foreseeability tests, mitigation standard, notice content and timing, evidence, update obligations, temporary-event treatment, cost allocation, payment obligations, termination rights and dispute process. State whether the list is exhaustive and whether examples expand or illustrate the general standard. Allocate supply-chain and subcontractor risk expressly rather than leaving it to implication.

UNIDROIT’s guidance expressly says it is advisable to include a clause tailored to the parties’ specific needs. On a construction project, that means aligning the clause with the programme, procurement lead times, site-access assumptions, permit regime and the contract’s separate extension-of-time and change mechanisms.

What should a contractor or employer do today?

Locate the clause and governing-law provision, then make a one-page event map: trigger, affected duty, first impact date, critical-path effect, notice deadline, mitigation actions, evidence and requested relief. Send a compliant protective notice if the deadline is approaching, continue unaffected work where safe and contractually required, and maintain dated records. Do not suspend payment or terminate solely because an event sounds like force majeure; confirm the precise contractual consequence first.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Frequently asked questions

Can a force majeure clause cover a subcontractor’s failure?

Only if the clause’s wording and risk allocation reach that failure. Many contracts distinguish an external event affecting a subcontractor from the subcontractor’s ordinary default, insolvency or procurement choice. Check both the force majeure definition and clauses making the main contractor responsible for subcontractor performance.

Does a force majeure event automatically extend the completion date?

No. The contract may require notice, proof of critical delay and a formal extension determination. Concurrent delay, float and separate extension-of-time rules can change the number of days even when the event qualifies.

Also popular on Amazon
Damaged Screw Extractor Set,Christmas Stocking Stuffers for Adults Men Him | Gifts for Men,Mens Gifts for Dad,Husband,Stripped Screws Bolt Drill Bit Tools for Easy Removal of Rusty Broken Screw
  • APPLY TO MOST DRILLS : 6 pieces screw extractors work with any drill and all the screw size or bolt (3-12mm), These extractor tools are used to reverse the damaged screw counterclockwise until it is released
  • The DIY Tools for Men-Men won't know they need screw extractor set until they have one! This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and Unique tool gifts for men women. The must have stocking stuffers for men, gifts for dad, husband, father, him, guy teens, adult, Boyfriend, son on Birthdays, Christmas, Fathers Day or anniversary. Perfect Holiday Gifts Guide
  • HIGH QUALITY - This damaged screw remover tool kit is made from High-Speed Steel H.S.S 4341# , which have high hardness of 63hrc, it's durable and easily to remove any damaged screws.
  • EASY TO USE: Just two simple steps to get the job done - drill a hole with a cutting size using the right size screw extractor and easily remove the screw or bolt using the removal tool Hardness 63-65HRC: Titanium hardened steel material, more durable than most screw extractors on the market, better hardness and durability than others, buy with confidence and complete peace of mind
  • Cool Gadgets for Men Dad Christmas Birthday Gifts for Men and Women - Men won't know they need screw extractor sets until they have one! Every screw has the potential to rust and break, which can create a situation where it cannot be removed. Owning it, there will be no anxiety about rusty screws. This screw extractor set is GIFTS WRAP AVAILABLE, can be gifted to your loved ones as it reflects a fresh trend with fun and practical. Amazing and unique tool gifts for men women. A must have stocking stuffer for men on birthdays, Christmas, Father's Day or anniversaries, a gifts for dads, husbands, fathers, him, adults, boyfriends, sons. The best and most practical and surprising Christmas gifts

Can I rely on a government announcement as evidence?

An announcement can support the existence and timing of an event, but it may not prove that your contractual duty was prevented. Pair it with site records, programme analysis, delivery evidence and a documented explanation of why reasonable alternatives could not overcome the effect.

What if the clause has no force majeure heading?

A clause can allocate extraordinary-event risk without using that label, through terms on prevention, exceptional events, suspension, change in law or extensions of time. Read the operative wording and related clauses rather than searching only for the phrase “force majeure.”

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

When should a lawyer review the claim?

Obtain jurisdiction-specific advice before rejecting a claim, withholding payment, imposing liquidated damages, suspending work or issuing termination notice where the exposure is significant. A lawyer can test the clause against the governing law, forum, evidence and procedural deadlines before an irreversible step is taken.

Frequently Asked Questions

Can a force majeure clause cover a subcontractor’s failure?

Only if the clause’s wording and risk allocation reach that failure. Many contracts distinguish an external event affecting a subcontractor from the subcontractor’s ordinary default, insolvency or procurement choice. Check both the force majeure definition and clauses making the main contractor responsible for subcontractor performance.

Does a force majeure event automatically extend the completion date?

No. The contract may require notice, proof of critical delay and a formal extension determination. Concurrent delay, float and separate extension-of-time rules can change the number of days even when the event qualifies.

Can I rely on a government announcement as evidence?

An announcement can support the existence and timing of an event, but it may not prove that your contractual duty was prevented. Pair it with site records, programme analysis, delivery evidence and a documented explanation of why reasonable alternatives could not overcome the effect.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What if the clause has no force majeure heading?

A clause can allocate extraordinary-event risk without using that label, through terms on prevention, exceptional events, suspension, change in law or extensions of time. Read the operative wording and related clauses rather than searching only for the phrase “force majeure.”

When should a lawyer review the claim?

Obtain jurisdiction-specific advice before rejecting a claim, withholding payment, imposing liquidated damages, suspending work or issuing termination notice where the exposure is significant. A lawyer can test the clause against the governing law, forum, evidence and procedural deadlines before an irreversible step is taken.

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply. Prices as of November 14, 2026 12:04 pm GMT+0000.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Recommended PC Tool
Recommended PC Tool
PC Slower Than It Used to Be?Free scan - under a minute
Outdated Drivers Are Slowing You DownFree scan - exact matches

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.