Carr Properties says it plans to begin construction in spring 2028 on a 373-unit apartment community at 300 Montgomery Street in Alexandria’s Old Town North, with completion targeted for spring 2030. The roughly two-acre block is the former Montgomery Center site. Those figures describe the developer’s October 2026 announcement, not a newly published city approval. Alexandria’s approved record still describes a 327-unit rental project with 22 apartments affordable at 60% of area median income, ground-floor retail and an arts component. Until the city or Carr Properties publishes an updated entitlement, the 373-unit design and its retail, arts and affordable-housing details should be treated as proposed.
What is replacing Montgomery Center in Old Town North?
Carr Properties acquired the Montgomery Center block at 300 Montgomery Street from MC Property, LLC and announced plans for a 373-apartment community. The developer says the project will occupy about two acres and include a rooftop pool and an amenity lounge with waterfront views.
As an Amazon Associate I earn from qualifying purchases.
Do these 3 things before closing this tab:
1Scan for outdated or missing drivers - takes under a minute2Repair Windows errors before they cause bigger problems3Fix the driver behind crashes, sound loss and screen glitchesThe announcement was reported by ALXnow on October 27, 2026, and by Bisnow on October 22, 2026. Carr Properties executive vice president and chief development officer Austen Holderness described Old Town as a neighborhood with strong long-term residential demand. Oliver Carr III said the company is continuing to grow in the Old Town Alexandria market.
When will Montgomery Center construction start and finish?
The current schedule is a target rather than a guaranteed construction date:
Popular on Amazon
| Milestone | Current target | Source and status |
|---|---|---|
| Construction start | Spring 2028 | Carr Properties’ October 2026 announcement; target |
| Completion | Spring 2030 | Carr Properties’ October 2026 announcement; target |
Earlier materials carried different expectations. A May 2025 construction newsletter anticipated a June start for the then-current 327-unit plan, while the 2022 applicant narrative described a 331-unit concept. Those schedules predate Carr Properties’ acquisition and the 2026 announcement, so they should not be used as the current timetable.
How many apartments will the project have?
Carr Properties’ current announcement calls for 373 apartments. Alexandria’s published approval, summarized on the city’s 2025 housing page from the 2023 action, describes 327 rental units. The two figures represent different stages or versions of the proposal; available reports do not establish whether the 373-unit plan is an amended entitlement, a redesigned plan awaiting approval or another change in the application.
Also popular on Amazon
| Item | Current Carr Properties announcement | Alexandria approved baseline |
|---|---|---|
| Homes | 373 apartments | 327 rental units |
| Affordable homes | Not yet confirmed for the 373-unit design | 22 units at 60% AMI |
| Retail and arts uses | Current program not stated | Ground-floor retail and an arts component |
| Site area | Roughly two acres | 87,187 square feet, or 2.0015 acres |
| Gross floor area | Not stated | 405,945 square feet, excluding the underground garage |
| Schedule | Spring 2028 start; spring 2030 completion | Older expectations in 2025 materials |
Will the new project still include retail and an arts venue?
That remains unconfirmed. Alexandria’s approved baseline includes ground-floor retail and an arts component, and the May 2025 newsletter described an arts venue, retail storefronts and more than 27,000 square feet of publicly accessible area. Carr Properties’ 2026 announcement highlights residential amenities but does not say whether those earlier public-facing elements remain, have been redesigned or are awaiting a new approval.
The earlier May 2022 applicant narrative also described public plazas and an Arts Paseo, along with two or three underground parking levels. These are historical design details, not commitments that can be assigned to the 373-unit plan without an updated filing.
Also popular on Amazon
How many affordable apartments are planned?
The only published affordable-housing commitment in the available approval record is 22 apartments affordable to households at 60% of area median income (AMI) within the 327-unit plan. Alexandria’s housing page also records a $878,201 contribution to the city’s Housing Trust Fund and City Council approval in April 2023.
Carr Properties has not publicly stated an affordable-unit count or a replacement Housing Trust Fund contribution for the 373-unit announcement. The 22-unit commitment therefore should not be presented as applying automatically to the larger design.
Quick wins for a faster PC:
Fix the driver behind crashes, sound loss and screen glitchesFind Drivers →Repair Windows errors before they cause bigger problemsFix Now →Also popular on Amazon
Where does the site fit in Old Town North’s development pipeline?
The block is near Carr Properties’ separate Margot project at 425 Montgomery Street. Margot contains 237 units and is expected to welcome its first residents in early 2027. Its opening would precede the Montgomery Center construction target, creating a nearby point of comparison but not changing the approvals or schedule for 300 Montgomery Street.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.What must happen before a 2028 start is credible?
A spring 2028 groundbreaking depends on the 373-unit concept securing the city approvals and permits needed for construction. The practical checkpoints are:
Also popular on Amazon
- An updated entitlement or site-plan record identifying the approved unit count and building program.
- City documentation of any affordable-housing units, income limits and Housing Trust Fund obligations carried into the revised plan.
- Confirmation of retail, arts, plaza and publicly accessible-space requirements.
- Construction and related permits, followed by a financing and mobilization plan consistent with the announced start.
Until those documents appear, the 2028–2030 timeline is Carr Properties’ stated objective, while the 327-unit plan remains the city’s published approval baseline.
Frequently Asked Questions
What does 60% of AMI mean for an affordable apartment?
AMI is the area median income measure used to set eligibility for income-restricted housing. A 60% AMI designation generally applies to households whose income is no more than 60% of the applicable local median, with the precise dollar limits updated by housing authorities.
Recommended Free Tools
Can Alexandria approve a different unit count from the one the developer announced?
Yes. A developer can announce a redesigned concept before the city records an amended entitlement. The enforceable unit count and conditions are the ones in the city’s approved plans and subsequent permit documents, not an announcement alone.
What does the approved gross-floor-area figure exclude?
Alexandria’s 405,945-square-foot figure excludes the underground garage. That means it is not a measure of the complete constructed volume, and it should not be compared directly with a future figure unless both use the same measurement rules.
What should nearby residents monitor for schedule changes?
Watch Alexandria planning and permitting postings for an amended site plan, public hearings, permit issuance and any construction notices. Those records will show when the proposed design becomes an actionable project and whether the target dates move.