The first barge carrying the main steelwork for the Narrow Water Bridge reached Warrenpoint Harbour in Northern Ireland on 20 October 2026, moving the cross-border project into its main-span installation phase. The Caroline delivered an 82-metre deck section and the bridge’s 114-metre pylon after a five-day voyage from Belgium. A second barge carrying the remaining fixed-span deck section was due to follow, while installation of the delivered components is expected to take eight to 12 weeks, subject to weather and operating conditions.
What arrived at Warrenpoint Harbour?
The Caroline arrived with two of the bridge’s three major steel components: Deck 2, an approximately 82-metre section, and the 114-metre pylon. Together with Deck 1, which was shipped separately, the components weigh approximately 2,245 tonnes.
As an Amazon Associate I earn from qualifying purchases.
| Component | Length | Approximate weight | Transport status |
|---|---|---|---|
| Deck 2 | 82 metres | 690 tonnes | Delivered by Caroline on 20 October 2026 |
| Pylon | 114 metres | 866 tonnes | Delivered by Caroline on 20 October 2026 |
| Deck 1 | Not stated | 725 tonnes | Shipped on Karel Victor; voyage expected to take about seven days, conditions permitting |
The weights for the individual pieces were reported by Afloat; BAM UK & Ireland gives the combined weight of the three principal steel components as approximately 2,245 tonnes.
How did the bridge sections get from Belgium to Warrenpoint?
Caroline departed Belgium on 15 October. Under tow from Multratug 29, it travelled through Dutch canals, crossed the North Sea to Carlingford Lough and then continued up the Newry River to Warrenpoint Harbour. The route combined inland waterways and exposed sea passage, making tides, weather and marine operating conditions important to the delivery schedule.
Popular on Amazon
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
The second barge, Karel Victor, left Belgium on 18 October carrying Deck 1. Its crossing was expected to take roughly seven days, although that estimate was conditional on weather and marine conditions.
How will BAM install the deck and pylon?
BAM has already installed temporary supports and skid tracks in the Newry River. These will allow the steelwork to be transferred from the barges and moved into its planned position. A 1,500-tonne crane is being assembled on the southern embankment for the lifting operation.
Windows Errors? Fix Them Before They Spread
Repair common Windows errors and clear accumulated junk for a smoother, more stable PC - no reinstall needed.Free scan · no reinstallOutdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware match- Receive and position the barges: The delivered sections are brought into the harbour and aligned with the temporary works.
- Transfer the steelwork: The crane and support system move each component from barge level onto the prepared skid tracks and supports.
- Skid into position: The deck sections and pylon are moved along the tracks to their installation locations.
- Complete the main-span installation: The components are aligned and secured as the bridge structure takes shape.
BAM expects this installation phase to last eight to 12 weeks. The duration is an estimate rather than a fixed completion date because lifting and marine operations can be paused by wind, tide, river conditions or other operating constraints.
Also popular on Amazon
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Both tools are designed to fit into difficult to reach spaces
- Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
- Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
What kind of bridge is Narrow Water Bridge?
Narrow Water Bridge will be a 195-metre, two-span cable-stayed crossing linking Cornamucklagh near Omeath in County Louth with Narrow Water near Warrenpoint in County Down. It is designed for vehicles, cyclists and pedestrians, creating a new crossing around Carlingford Lough.
The shorter northern span will contain a movable bascule section. Opening that section will allow marine traffic to continue using the Newry River rather than permanently closing the navigation route. Belgian steel specialist Aelterman is fabricating the bascule span, with delivery expected in October 2027.
When will Narrow Water Bridge open?
Main construction is currently forecast to finish in the fourth quarter of 2027. After construction, the bridge will require testing and commissioning, with opening forecast for early 2028. Both dates are projections, not completed milestones, and may change as marine works, fabrication and commissioning progress.
Also popular on Amazon
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
| Milestone | Status or forecast |
|---|---|
| Caroline arrival at Warrenpoint | Completed 20 October 2026 |
| Karel Victor delivery of Deck 1 | Expected after a voyage of about seven days from 18 October, conditions permitting |
| Main-span installation | Expected to take eight to 12 weeks |
| Bascule span delivery | Expected October 2027 |
| Main construction completion | Forecast for Q4 2027 |
| Bridge opening | Forecast for early 2028, after testing and commissioning |
Who is funding and delivering the project?
The project is funded through the Irish Government’s Shared Island Fund. Louth County Council is delivering it with the Department of Housing, Local Government and Heritage, while BAM UK & Ireland is the main contractor.
Project partners say the crossing is intended to improve connections between the Mourne Mountains and the Cooley Peninsula, support tourism and active travel, and strengthen economic links around Carlingford Lough. Its practical benefit will depend on completing the fixed and movable spans, commissioning the finished structure and maintaining safe navigation on the Newry River.
John Wilkinson, BAM UK & Ireland’s chief operating officer, described the delivery as requiring “meticulous planning, specialist engineering and international collaboration” to transport and install the structures safely. Taoiseach Micheál Martin called the arrival a major construction milestone and said the bridge would bring communities closer together while supporting recreation, sustainable tourism and regional economic development.
Also popular on Amazon
- Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
- Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
- Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
- Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
- Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed
Frequently Asked Questions
Why was the Narrow Water Bridge steelwork built in Belgium?
The principal steel components were fabricated in Belgium and transported by specialist barges, allowing the large deck sections and pylon to reach the site by water rather than by an overland route through towns and border crossings. The available data identifies Aelterman as the Belgian specialist fabricating the later bascule span.
The Tool Desk
Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Will boats still be able to use the Newry River after the bridge opens?
Yes. The shorter northern span is designed as a movable bascule section, which can be raised to keep marine traffic moving on the Newry River. Its delivery is expected in October 2027.
How much lifting capacity is available for the bridge installation?
BAM is assembling a crane rated for 1,500 tonnes on the southern embankment. That crane will work with temporary river supports and skid tracks to transfer and position the delivered steelwork.
Does the project have a published construction cost?
No project cost figure is identified in the available project statements. The confirmed funding route is the Irish Government’s Shared Island Fund, with delivery led by Louth County Council and its government partners.
Quick Recap
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.
Free tools Windows power users keep installed
One-click scans. No signup required.