The Edison is a planned downtown Milwaukee apartment tower, not a completed building, and it is not the USA’s tallest timber tower. It was designed to surpass Milwaukee’s completed Ascent. Construction paused in September 2025 after the developer, Neutral, cited tariffs, broader inflation, and higher material costs. In October 2025, a city official reported an estimated $25 million gap between the expected budget and projected cost. In 2026, the contractor, C.D. Smith, filed suit seeking more than $11.3 million and foreclosure. The project’s status after that reporting has not been independently confirmed.
How “tallest” applies to The Edison
The word “tallest” describes the Edison’s ambition, not a finished building. The Wisconsin Department of Natural Resources, in its 2025 report using data through December 2024, calls Ascent the tallest timber tower. Ascent is a 25-story, 284-foot building completed in 2022, according to its structural engineer, Thornton Tomasetti. The Edison was planned to exceed it.
Rankings in this category depend on definitions. Ascent is a hybrid: it has a six-level concrete podium and concrete cores over 19 mass-timber levels. If “timber” means any building with a timber structure above a concrete base, the Edison’s mass-timber and concrete hybrid design would qualify in the same way. The title’s claim therefore rests on a planned height and a stated design goal, not on a measured result.
Timeline of the project
| Date | What was reported | Source and qualification |
|---|---|---|
| January 2025 | Neutral announced $133.3 million in construction financing from Bank OZK and Pearlmark. | The Daily Reporter, 2025. This is the reported financing amount, not proof that all capital needed to finish the tower was in place. |
| June 2025 | Construction began. | The Daily Reporter, 2025. |
| September 2025 | Neutral paused the project, citing tariffs, broader inflation, and higher key input hard costs. It said it was working with the contractor on cost reduction and value engineering and set no date to restart vertical work. | Engineering News-Record (ENR), September 2025. |
| October 2025 | Milwaukee Department of City Development Commissioner Lafayette Crump told a city committee the expected budget had moved from about $205 million to about $230 million. | The Daily Reporter, October 9, 2025. These are figures stated at a city meeting, not audited project accounts. |
| November 2025 | The tower crane and other equipment were removed from the site. | ENR, 2026 report. |
| March 6, 2026 | C.D. Smith filed suit seeking more than $11.3 million for work performed and foreclosure or sale of the unfinished property. | ENR, 2026. This is a filed claim, not an adjudicated debt or a completed foreclosure. |
Published descriptions of the planned tower also differ. ENR’s September 2025 account describes 32 stories and 378 units. The Daily Reporter’s October 2025 account describes 31 stories and the same 378 units. Use “roughly 31 to 32 stories” unless you can cite one source for the exact count.
Do these 3 things before closing this tab:
1Repair Windows errors before they cause bigger problems2Scan for outdated or missing drivers - takes under a minute3Clear out junk files and repair common Windows errors#1 Best Overall
- Play the role of architect and engineer as you build over 20 models of structural elements and real-world buildings!
- Start with Basic structures like trusses, arches, and domes, and move on to scaled-down models of real-world buildings!
- New flexible building pieces mimic steel frames; All plastic building parts are compatible with other Thames & Kosmos engineering and physics kits.
- Explore the field of architectural design and learn about modern day building materials.
- For ages 8+, includes a 44-page, full-color manual that guides building exercises and encourages kids to dream up their own designs.
Why the budget moved
What the developer said
Neutral attributed the pause to tariffs, broader inflation, and increased material costs that had materially raised hard costs. CEO Nate Helbach, quoted by ENR in September 2025, said: “Pausing to value-engineer is a difficult but prudent step to safeguard the [project] long-term.” The bracket is in the original quotation and marks a word the reporting left for the reader to fill in.
What the city said
At the October 2025 committee meeting, Crump said the developer would consider project changes and seek an additional cash infusion. According to The Daily Reporter, the project was financed with private equity, loans, and individual investors, and had not sought city financial assistance at that time. Crump’s warning was direct: “If those cost overruns to continue at the same pace, it would be challenging to complete the project.”
Rank #2
- Model Description: This model is a recreation of a well-known skyscraper in Manhattan, NYC Famous Skyscraper is a 290-meter-tall Art Deco high-rise, completed in 1932. At the time, it was the third tallest building in the world.
- Premium Parts: Created and authorized by renowned architectural designer SPBrix, this set consists of 742 pieces. The parts have smooth edges with no rough or jagged surfaces, vibrant colors, and a scratch-free finish.
- Clear Instruction: The instruction manual is provided in digital format via a QR code, with clear step-by-step guidance. Building the model enhances hands-on skills, logical thinking, and creativity.
- Value and Significance: Once assembled, this model serves as a valuable decorative piece for display and collection.
- 100% Quality Guarantee: Our customer support team is always ready to provide you with the best service. If you have any problems with a product, please directly contact us at first. We will reply to you at the first time.
What is not established
- The reporting does not isolate how much of the increase came from timber, concrete, steel, or other inputs. ENR noted in 2025 that a city official did not know which material was driving the increase.
- Timber alone should not be described as the cause of the cost escalation. The developer named tariffs and inflation alongside material costs.
- The $25 million gap is a figure stated at a meeting. It has not been verified against the developer’s accounts or a lender’s records.
The contractor lawsuit
ENR reported in 2026 that C.D. Smith sued over unpaid work and an estimated financing shortfall, seeking more than $11.3 million and foreclosure or sale of the unfinished property. ENR also reported that Alderman Bob Bauman expressed “surprise, disappointment and concern that it will never get finished” in 2025 reporting.
The allegations and amounts above come from the reporting. No court docket, ruling, settlement, or foreclosure sale was verified for this article. Treat the $11.3 million as the amount the contractor seeks, not an award or a confirmed liability, and do not assume the case has concluded.
The Tool Desk
Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Rank #3
- Scale 1/24
- Skill Level 3
- Ages 12+
- Italeri P/N 3868
What Ascent shows and what it does not
What Ascent demonstrates
Ascent was completed in 2022. It combines glulam beams and columns with cross-laminated timber floors above a concrete podium, and uses concrete cores for lateral stability. Thornton Tomasetti says the project used an alternate-materials variance under Wisconsin’s commercial code framework and required extensive fire testing and analysis to demonstrate the specified fire ratings. The engineer’s page reports two-hour ratings for beams and connections, three-hour ratings for columns, and sprinklering with stair and corridor pressurization.
Ascent therefore shows that a tall mass-timber hybrid can be designed and built in Milwaukee under project-specific engineering and approval conditions. That is a meaningful precedent for the Edison’s structural concept.
Rank #4
- Highly Detailed: Meticulously crafted 1:60 scale model of the historic HMS BEAGLE
- Authentic Materials: Constructed from high-quality wood and die-cast metal to create a beautiful display model.
- Intricate Design: Features intricate details like rigging, sails, ladders, cannons and deck elements.
- Adult Assembly Required: Engaging project for hobbyists and model enthusiasts, this is Medium difficulty build, model ship build required
- Impressive Scale; dimensions 28.4" inches long x 18.9 " tall X 9 " wide when fully assembled.
Where the comparison stops
Ascent does not show that the Edison’s design, cost, code path, market, or capital stack would perform the same way. JLL announced in February 2024 a $98 million, three-year floating-rate refinancing for the completed Ascent, arranged for a New Land Enterprises affiliate and provided by Barings Real Estate. A refinancing of a finished, leased-up building is a different financial event from funding an unfinished tower whose budget has moved.
Edison and Ascent side by side
| Factor | Ascent (completed) | The Edison (planned) |
|---|---|---|
| Status | Completed in 2022 | Paused in September 2025; no restart date set in the reporting reviewed |
| Height and stories | 25 stories, 284 feet (Thornton Tomasetti) | Planned to exceed Ascent; 31 or 32 stories depending on the source |
| Units | Not stated on the cited engineer page | 378 units (ENR and The Daily Reporter) |
| Structure | Glulam beams and columns, cross-laminated timber floors, concrete podium and cores | Described as a mass-timber and concrete hybrid; structural detail not stated in the reporting reviewed |
| Code path | Alternate-materials variance under Wisconsin’s commercial code framework, supported by fire testing | Not stated in the reporting reviewed |
| Financing evidence | $98 million three-year floating-rate refinancing, February 2024 (JLL) | $133.3 million construction financing announced January 2025; roughly $25 million budget gap reported October 2025 |
| Quality of evidence | Engineer project page and a financing announcement | News reports, a city meeting account, and an unadjudicated lawsuit report |
Industry growth in context
The DNR’s 2025 report, citing WoodWorks, gives the following national-trend figures:
Best Value
- Highly Detailed: Meticulously crafted 1:70 scale model of the historic ENDURANCE
- Authentic Materials: Constructed from high-quality wood and die-cast metal to create a beautiful display model.
- Intricate Design: Features intricate details like rigging, sails, ladders, cannons and deck elements, with 3,292 parts
- Adult Assembly Required: Engaging project for hobbyists and model enthusiasts, this is Medium difficulty build, model ship build required, Average build time: 480 hrs.
- Impressive Scale; dimensions 29.68" inches long x 17.5 " tall X 8.5 " wide when fully assembled.
- 349 mass-timber projects in design or built in 2018, rising to 2,338 by December 2024.
- In Wisconsin, 34 mass-timber projects built or under construction and 13 in design as of December 2024.
The summary reviewed does not restate whether the 2,338 figure is national or state-level, so treat it as an industry indicator rather than a measure of Milwaukee’s pipeline. Industry growth does not remove project-level risks in cost, financing, procurement, approvals, and construction execution, which is where the Edison’s difficulties sit.
Signals that would change the picture
- A court docket entry, ruling, or settlement in the C.D. Smith case.
- A notice of foreclosure sale or a lender action on the property.
- A public update from the developer or city on a revised budget, a restart date, or a changed design.
- A city financial request or incentive application, which the October 2025 reporting said had not been made at that time.
Until one of these appears in a primary record or a dated report, the Edison should be described as a paused, contested project rather than a finished or confirmed one.