October DealsAmazon USOctober deal check: compare before you payAmazon US: current deals, useful picks and tech finds.Check DealsClean PCRecommendedOne scan can reveal what keeps slowing WindowsLook for cleanup and repair opportunities.Run ScanOctober DealsAmazon USDeal season is back - check today's better picksAmazon US: current deals, useful picks and tech finds.See Picks×
Skip to content
Bettesworth Construction
construction

Fiona Stanley Hospital: Delays, Opening Date and Reported Costs

Fiona Stanley Hospital’s official opening was 3 October 2014, with patients admitted from 4 October. Here is how its schedule and reported costs changed.

By Bettesworth Construction Team 3 min read
Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Fiona Stanley Hospital’s official opening ceremony was held on 3 October 2014, and it began receiving patients the following day. Its schedule had shifted repeatedly from an original intention to open in 2010, while reported project costs rose as the project’s scope and costs were better defined.

When did Fiona Stanley Hospital open?

Premier Colin Barnett officially opened the hospital on 3 October 2014. The Auditor General’s later account records 4 October 2014 as the date it opened to patients; these are separate milestones. The Auditor General also notes that full non-clinical services were in place from the patient opening.

In the opening announcement, Barnett said: “After years of planning by successive governments, this State Government began building the hospital here in Murdoch in September 2009 and I am delighted to now see it open.” The WA Government’s announcement, 3 October 2014, described the facility as a $2 billion hospital.

How did the opening date move?

Milestone Date or timeframe What it means
Original opening intention 2010 The initial target recorded by the Auditor General.
Planned opening in the 2010 audit account May 2014 The then-current planned date reported by the Auditor General.
Revised timeframe announced by the Government October 2014 Confirmed in June 2013, later than the April 2014 opening date then expected.
Official opening ceremony 3 October 2014 Premier Colin Barnett formally opened the hospital.
Opening to patients 4 October 2014 The date recorded in the Auditor General’s later account.

The schedule therefore cannot be reduced to a single “opening date”: the original target, successive plans, ceremony and start of patient services refer to different points in the project’s history.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Why was the project delayed?

The Auditor General’s 2010 report cited poor planning that held up project approval, as well as longer construction timeframes reflecting increased scope. In June 2013, the WA Government said the move from the April 2014 date then expected to an October timeframe reflected the project’s scale and complexity, particularly its advanced information and communications technology system.

Those accounts identify contributing factors but do not quantify how much time each one added. They should not be read as a precise breakdown of the delay.

How much did Fiona Stanley Hospital cost?

Date and source Reported figure Description
2004; Western Australian Office of the Auditor General, 2010 report $420 million Initial capital budget recorded for the project.
By 2010; Western Australian Office of the Auditor General $1.76 billion Estimated capital cost as costs and scope were better defined.
3 October 2014; Government of Western Australia $2 billion The Government’s description of the hospital in its opening announcement.

These figures have different dates and descriptions. The Auditor General compared the original capital budget with a later estimated capital cost; the Government used “$2 billion hospital” in its 2014 opening statement. The available accounts do not establish these as directly comparable final outturn figures, so the $2 billion description should not be treated as an audited final project cost.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

What the project timeline shows

The WA Government announced a new tertiary hospital in 2004. According to the Auditor General, forward works began in July 2008 and construction began in March 2009. The project’s planned opening dates moved over time, with the 2010 audit recording May 2014 as the plan and the Government confirming an October 2014 timeframe in June 2013.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

For a construction-focused reading, the central lesson in the published accounts is the combination of approval delays, increased scope and a technically complex project. The sources identify these factors but do not provide a quantified allocation of the overall cost increase or schedule movement to each one.

Sources

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

More from the Site Office

Recommended PC Tool
Recommended PC Tool
PC Slower Than It Used to Be?Free scan - under a minute
Outdated Drivers Are Slowing You DownFree scan - exact matches

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.