If your planning application appears stuck or the council says information is missing, first establish whether the application is valid and registered. Ask the local planning authority (LPA) in writing to confirm its validation date, list every outstanding item and the rule or local validation requirement behind each request, and state the decision date it is working to. Only then can you tell whether you are waiting for validation or whether a valid application is late. If the relevant statutory or agreed period has expired, you may appeal against non-determination—but an appeal is not automatic planning permission.
The steps and deadlines below apply to the English planning system. Scotland, Wales and Northern Ireland use different procedures and appeal routes.
As an Amazon Associate I earn from qualifying purchases.
First identify which delay you have
There are two different problems that are often described as a “delayed application”. They have different clocks and remedies.
The application has not been validated
An LPA may have received your forms and fee but decided that the submission is incomplete or does not meet its validation requirements. The normal decision period does not simply run from the day an incomplete package was uploaded. It normally starts when the application is valid.
#1 Best Overall
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
Ask whether the application has been registered as valid, whether consultation has started and, if not, what is preventing validation. A request for a document needed to make the application valid is different from a request for extra material to assess an application that is already valid.
The application is valid but no decision has been issued
Once an application is valid, the LPA should work to the statutory period for that type of development, unless you and the authority have agreed a longer period in writing. If that period passes without a decision, the issue is non-determination. You can ask for a firm decision date or consider an appeal.
Write to the planning authority and create a clear record
Use the case officer’s published email address or the council’s planning portal contact route. Keep your message factual and ask for a reply in writing. Request all of the following:
- the date the LPA considers the application valid;
- confirmation that it has been registered and whether consultation has begun;
- every document, drawing, fee or other item the authority says is outstanding;
- the legal, policy or local validation-list basis for each item;
- whether a formal non-validation notice has been issued;
- the decision deadline being used, including the date on which the statutory period began;
- details of any extension of time agreed in writing; and
- the next procedural step and a realistic expected decision date.
UK Government guidance on making an application says authorities should “discuss their concerns with the applicant at the earliest opportunity” and “give clear advice about what steps need to be taken to address their concerns.” A precise written request helps you test whether that has happened and prevents dates being lost in telephone conversations.
Check what “missing information” actually means
Information required for validation
Validation requirements come from the national rules and the LPA’s published local validation list, applied to the circumstances of the proposal. For example, a particular drawing, ownership certificate, fee or technical report may be needed before the authority will treat the submission as valid. The fact that an officer asks for a document does not, by itself, establish that it is required in every case; ask how the requirement applies to your development.
Rank #2
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Both tools are designed to fit into difficult to reach spaces
- Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
- Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
If the request is clear and reasonable, supply the material promptly. Name each file, use the council’s required format and ask the officer to confirm receipt and whether the application is now valid. Save the uploaded files, portal confirmation, emails and the fee receipt.
Additional information for assessing a valid application
An LPA can ask for further information while assessing a valid application. That request may help officers understand design, access, drainage, ecology, heritage or another planning issue without changing the original validation date. Ask the officer to confirm whether the application is already valid and whether providing the material changes the decision timetable.
Free tools Windows power users keep installed
One-click scans. No signup required.
If an item appears unnecessary, do not ignore the request. Reply asking for the specific validation-list entry, legal power or policy reason relied on, and explain why you believe it does not apply. A short, written clarification can resolve an over-broad request while preserving your position.
What to do if the LPA says the application is invalid
Ask for the formal notice and its reasons. Preserve the notice, the submitted documents, the fee evidence and all correspondence. A formal non-validation notice matters because the calculation of the decision period can be disputed.
GOV.UK describes a route to appeal against non-determination following a non-validation notice after the relevant time has passed. In that situation, the period is considered to start when the authority has the fee and all other information necessary to validate, excluding the disputed information specified in the Article 12 notice. The Planning Inspectorate can consider the validation dispute as part of the appeal.
Rank #3
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
Do not assume that simply waiting a fixed number of weeks from the original upload date makes an appeal ready. First establish which information was accepted, which item is disputed and when the fee and other validating information reached the LPA.
Recommended Free Tools
Calculate the correct decision period
The ordinary periods in England are procedural deadlines, not statistics about how quickly every council decides. The period depends on the application category and can be replaced by a written extension.
| Application circumstance | Usual statutory period | How to use it |
|---|---|---|
| Most planning applications | 8 weeks | Count from the valid-application date, not automatically from the first incomplete submission. |
| Major development | 13 weeks | Confirm that the LPA has treated the proposal as major development and check any written agreement. |
| Application subject to Environmental Impact Assessment | 16 weeks | Use the EIA period where that category applies. |
| Other categories, including technical details consent or public service infrastructure | Category-specific period | Check the period stated in the relevant planning guidance and the LPA’s correspondence. |
An extension of time changes the relevant date only when it has been agreed in writing between the applicant and the LPA. Keep the signed letter or email and read exactly which period and decision date it covers. A verbal assurance that an officer is “nearly there” is not the same as a written extension.
Ask whether waiting is sensible
Before appealing, ask the LPA for a realistic written decision date and the reason for the delay. Waiting can be practical where the officer has identified a small, defined amendment, statutory consultees are close to responding or a committee meeting is imminent. Set a date to review the position rather than agreeing to an open-ended delay.
Consider the consequences of waiting: a purchase or finance condition may expire, a contractor may need to be rebooked, or a design may become more expensive to change later. Record those consequences in your email and ask whether the proposed timetable can meet them.
Do these 3 things before closing this tab:
1Fix the driver behind crashes, sound loss and screen glitches2Clear out junk files and repair common Windows errors3Scan for outdated or missing drivers - takes under a minuteRank #4
- Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
- Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
- Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
- Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
- Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed
When and how to appeal against non-determination
Where a valid application has not been determined within the relevant statutory period—or another period agreed in writing—you have a right to appeal to the Secretary of State against non-determination. This is an appeal about the application’s planning merits and procedure, not an automatic approval mechanism. The Inspectorate can dismiss the appeal, allow it subject to conditions, or otherwise determine the proposal under the applicable process.
Check the appeal window for your category
The Planning Inspectorate guide for applications dated on or after 1 April 2026 gives most non-determination appeals a six-month limit after the LPA’s determination period expires. Advertisement-consent non-determination has an eight-week appeal period, and other categories have distinct rules. Check the current Inspectorate guide for the exact application type, including any enforcement-related exception, before relying on a date.
Calculate from the expiry of the statutory or written-agreed period—not from the date you first complained about the delay. If the LPA issued a non-validation notice, apply the special validation-dispute calculation rather than the ordinary calculation.
Prepare the appeal file
Gather the material an Inspectorate case will need:
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →- the original application form, plans, supporting statements and fee receipt;
- the LPA’s validation confirmation or non-validation notice;
- the complete chronology of submission, validation, requests and responses;
- the written extension, if any;
- the LPA’s consultation and officer correspondence; and
- a concise statement explaining why the determination period expired and what outcome you seek.
Check the current appeal form and submission instructions, and ensure the appeal is received before the applicable deadline. An incomplete appeal can create avoidable correspondence and risk the time limit.
Best Value
- Milwaukee Ink all Fine Point Marker, Black, 4 Per Pack
- 4 per pack Features Clog Resistant Marker Tip Writes through Dusty, Wet and Oily Surfaces Durable Marker Tip for Writing on Concrete, OSB and Rough Surfaces
- Clog resistant tip writes on dusty, wet and oily surfaces and is optimized for rough surfaces such as OSB, cinderblock and concrete
- Hard hat clip- attaches for easy access
- Quick dry time with reduced smearing and marking
A practical decision framework
| Your status | What to do now | Likely consequence |
|---|---|---|
| Not yet validated; request is clear | Supply the item, obtain receipt confirmation and ask for the new validation date. | The decision clock should be assessed from the valid-application date. |
| Not yet validated; request appears unsupported | Ask for the precise local-list, legal or policy basis and explain why it may not apply. | You may resolve the issue without conceding that an unnecessary item is required. |
| Formal non-validation notice disputed | Keep the notice and calculate the period using the validation-dispute rules; consider the available non-determination appeal route after the relevant time. | The Inspectorate can examine the dispute alongside the appeal. |
| Valid application within its period | Ask for the next milestone and a realistic decision date; continue constructive discussions. | Appealing before the period expires is generally premature. |
| Valid application past its statutory or written-agreed period | Request a final decision date, then decide whether to appeal within the category’s deadline. | An appeal starts a merits-based process; it does not grant permission automatically. |
Common mistakes that make delays harder to resolve
- Counting from the upload date: an incomplete submission may not start the ordinary decision period.
- Accepting a vague request: ask for each missing item and its specific basis rather than exchanging general promises.
- Confusing validation with assessment: extra evidence requested for a valid application does not necessarily reset validation.
- Relying on a phone call: confirm dates, requests and agreements by email.
- Assuming an extension: a longer period must be agreed in writing.
- Missing the appeal window: deadlines differ by category; the six-month general rule does not cover every case.
- Treating an appeal as automatic permission: the Inspectorate considers the planning case and may refuse it.
When specialist help is worthwhile
You can handle a straightforward request for a missing drawing or confirmation yourself. Consider a planning consultant or solicitor where the LPA has issued a formal non-validation notice, the validation issue could affect a purchase or financing deadline, several technical disciplines disagree, or an appeal statement requires detailed planning evidence. Give any adviser the complete chronology and documents; professional input should support, not replace, the written status check with the LPA.
Keep a one-page case chronology
A simple chronology makes the next conversation more productive. Record the submission date, fee payment, every portal status, the date the LPA said the application was valid or invalid, each information request, your response date, any written extension and the statutory deadline. Attach the relevant email or notice to each entry. This allows you to demonstrate exactly which clock applies and prevents an appeal deadline being calculated from the wrong event.
Frequently Asked Questions
How long does the council have to decide a planning application in England?
The usual period is 8 weeks for most applications, 13 weeks for major development and 16 weeks for applications subject to Environmental Impact Assessment. The clock normally starts when the application is valid, and a longer period can replace it if agreed in writing. Other categories have their own periods.
What if the council says my planning application is missing information?
Ask in writing for every outstanding item, the specific legal, policy or local validation-list basis, and confirmation of whether the application is valid. Supply clear, reasonable items promptly and obtain written confirmation of receipt and the resulting validation date. If a request appears unnecessary, ask the officer to explain how it applies to your proposal.
Can I appeal if the planning authority has not decided my application?
Yes, a valid application that has not been decided within its statutory or written-agreed period can be appealed against non-determination. The appeal is not automatic permission. Most such appeals for applications dated on or after 1 April 2026 must be received within six months after the determination period expires, but categories such as advertisement consent have different limits.