Plans and prices
| Plan | Price | Billed |
|---|---|---|
| Core | $7 a year | per user per month / billed annually |
| Advanced | $10 a year | per user per month / billed annually |
| Business | $17 a year | per user per month / billed annually |
| Enterprise | $25 a year | per user per month / billed annually; limited offer showing $35 crossed out and $25 |
From GanttPRO's own pricing page, checked 5 Oct 2026. Every plan
What the maker publishes
- Client/stakeholder sharing
- Shared private links can expose plans to stakeholders and clients with static or dynamic charts. source
- Collaboration
- Users can comment on tasks, attach files, mention teammates, and receive real-time notifications. source
- Comments and attachments
- Tasks support comments and attachments for collaboration. source
- Company
- GanttPRO says its story began in 2014 and identifies DPM Solutions Sp. z o.o. in Kraków, Poland, as the company. source
- Exports
- Projects can be exported in PDF, PNG, XLSX, and XML formats, including during the trial. source
- Founded
- 2014 source
- Free plan
- No source
- Guest access
- Yes source
- Headquarters
- Kraków, Poland source
- Integrations
- The integrations listed by GanttPRO include Slack, Google Drive, Jira Cloud, OneDrive, Microsoft Teams, and Microsoft Project. source
- Integrations
- Integrations include Jira Cloud, Slack, MS Teams and Google/Outlook calendars. source
- Jira availability
- The two-way Jira Cloud integration is available on Business and Enterprise plans. source
- Mobile app
- The iOS and Android apps cover core tasks such as creating tasks, notifications, replying to comments, and tracking time; advanced management requires the web version. source
- Mobile/web availability
- The software is available online and has a mobile app. source
- Native integrations
- 7 source
- Offline use
- GanttPRO says project data cannot be modified offline, though charts can be saved as PNG or PDF for viewing. source
- Planning
- Its Gantt charts support work breakdown structures, task dependencies, auto scheduling, and critical path views. source
- Project management scope
- GanttPRO provides features for efficient project management, tracking tasks, dependencies and resources. source