Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Mining companies calculate annual production by connecting a mine schedule to a processing schedule: tonnes of material, grade, metallurgical recovery and, when sales are reported, contractual payability. A reserve is not simply the mineral inventory divided by mine life. It is the economically mineable portion of a Measured or Indicated Resource after a technically achievable mine plan and all relevant modifying factors have been applied.
The first control is the reporting reference point. A number may describe run-of-mine material, ore delivered to a plant, plant feed, concentrate, doré, cathode or payable metal. Those are different quantities, so a production figure is meaningful only when its basis, moisture convention, grade, recovery, cut-off assumptions and reporting code are identified.
As an Amazon Associate I earn from qualifying purchases.
Start by defining exactly what is being measured
“Annual production” can refer to several points in the material flow. The same operation may report ore mined, ore hauled to a stockpile, ore fed to a mill, concentrate produced and payable metal credited by a smelter. They should not be treated as interchangeable.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
| Reporting point | What the quantity represents | Why it matters |
|---|---|---|
| Run-of-mine (ROM) material | Material excavated from the mine before plant processing, often including ore and material that will be sorted or stockpiled. | Useful for mining capacity, but it does not equal plant feed or saleable metal. |
| Ore sent to the plant | Ore delivered from the mine or stockpile to the processing facility. | Often the reference point used for an Ore Reserve statement under JORC, which requires the reference point to be stated. |
| Plant feed | Material actually entering a particular processing circuit. | Can differ from mine output when stockpiles, blending, bypasses or plant constraints change the schedule. |
| Concentrate, doré or cathode | A processed product containing the target metal, before commercial deductions. | Product tonnes and contained metal are different measures; a concentrate also contains gangue and other elements. |
| Payable metal | The quantity recognized for sale after contractual payability and specified deductions. | It is the closest of these measures to sales revenue, but it is not the same as recovered metal. |
JORC Code 2012 requires public reports to identify the reserve reference point. A statement that says “1.2 million tonnes produced” without saying whether that is wet ore, dry plant feed, concentrate or payable metal is incomplete.
#1 Best Overall
- Valued Carpenter Pencil Set: You will get 2 pcs solid carpenter pencils with 26 piece 2.8 mm refills, 1 replaceable sharpener, 1 plastic storage box.The complete carpenter pencils combination allows you to finish your work faster and more easily
- Deep Hole Marker Pencil: The deep-hole construction pencils adopts 45mm elongated tip design, which is more convenient to mark in the small hole or in other tight areas that other carpenter markers cannot reach
- Carpenter Pencils with Sharpener: The sharpener is screwed into the top of the work pencil, which won't get lost either. Built-in pencil sharpener that keep the lead with pointed and smooth to Improves line of sight in fine work
- Stronger Solid Lead: This work pencil is matched with a 2.8 mm thick lead , which is much thicker and stronger during the drawing process of construction work, it will not break or damage easily
- Marks on Various Surfaces: 3 colors solid construction pencil can marks on various surfaces,such as metal, plastic, wood, paper etc. Ideals for woodworkers, contractors, craftsmen, builders, merchants and masons
Build the annual mine and plant schedules
The annual schedule is the bridge between a geological model and a production result. CIM guidance calls for a schedule showing, by year, ore tonnes, ore grades, product recovery, waste tonnes and grades, plus stockpile feed tonnes and grades. Mine and plant schedules should be separated when stockpiling or other constraints mean the material mined in a year is not the material processed in that year. The guidance is available in the CIM estimation guidance.
Inputs normally carried by year
- Mining movement: ore, waste, dilution and any planned mining losses.
- Ore quality: tonnes and head grade for each relevant ore type or domain.
- Stockpiles: opening balance, additions, withdrawals, grades and closing balance.
- Processing: plant feed, throughput limits, recovery assumptions and product streams.
- Commercial terms: concentrate or doré payability, treatment and refining charges, transport, penalties and royalties where they affect the economic model.
- Timing: ramp-up, shutdowns, maintenance, expansions and mine-life sequencing.
Keeping mine output and plant feed in separate columns prevents a common error: dividing a mine’s annual mined tonnes by a plant recovery that was calculated on a different feed mix.
Calculate contained metal from tonnes and grade
Contained metal is the theoretical quantity of a commodity in the scheduled ore before processing losses. In a consistent unit system:
Recommended Free Tools
contained metal = ore tonnes × head grade
For a grade stated as a percentage, divide by 100 before multiplying. For a grade in grams per tonne, multiply by tonnes to obtain grams and then convert to kilograms or troy ounces as required. Keep the moisture basis consistent: a wet-tonnage feed and a dry-tonnage grade cannot be multiplied without first applying the moisture correction.
Illustrative copper calculation
Consider a schedule containing 1,000,000 dry tonnes at 1.50% copper:
| Step | Calculation | Result |
|---|---|---|
| Contained copper | 1,000,000 × 0.015 |
15,000 tonnes |
| Recovered copper at 88% recovery | 15,000 × 0.88 |
13,200 tonnes |
| Payable copper at 96% payability | 13,200 × 0.96 |
12,672 tonnes before other deductions |
This is an arithmetic illustration, not a reported mine result. It shows why “contained,” “recovered” and “payable” metal must be labelled separately.
Rank #2
- Ergonomically Designed: Work in tight areas with a compact design that gets into tough spots
- Both tools are designed to fit into difficult to reach spaces
- Complete a wide range of applications with a high-performance motor that delivers up to 300 UWO, and an impact driver delivering up to 1,400 in-lbs of torque
- Both the DEWALT impact driver and drill driver feature integrated LED work lights with a convenient 20-second delay, ensuring enhanced visibility in dimly lit or challenging work areas
- One-Handed Loading - Keep one hand free with a 1/4 in. hex chuck that accepts 1 in. bit tips
Apply metallurgical recovery
Recovery measures the share of contained metal successfully extracted by processing. The U.S. Securities and Exchange Commission’s S-K 1300 glossary defines recovery as “that portion (usually expressed as a percentage) of the metal contained in mineralized material that is successfully extracted by processing” (SEC definition).
The basic calculation is:
recovered metal = contained metal × recovery fraction
A single life-of-mine percentage can hide important operating behaviour. Recovery may change with mineralogy, oxidation state, grade, liberation size, reagent regime, throughput and blending. A schedule may therefore use recovery by geological domain, grade bin, ore type or throughput range. The recovery assumption should be tied to the same feed basis as the tonnes and grade; a laboratory result for a narrow sample is not automatically a plant-wide annual recovery.
Recovery is not mining recovery
Metallurgical recovery describes what the plant extracts from the material it receives. Mining recovery describes how much of the designed ore can actually be excavated, while dilution describes unwanted waste or low-grade material that enters the ore stream. A reserve model can apply both mining assumptions and processing recovery, so an analyst should not use the plant recovery percentage as a proxy for extraction from the pit or stope.
Convert recovered metal to payable metal
Concentrate and doré sales often recognize less metal than the processing calculation recovers. A smelter or refinery contract may apply a payable percentage and deductions for treatment, refining, transport, penalties, moisture or impurities. CIM guidance lists these revenue-model inputs alongside recovered-metal schedules.
Do these 3 things before closing this tab:
1Clear out junk files and repair common Windows errors2Scan for outdated or missing drivers - takes under a minute3Repair Windows errors before they cause bigger problemsA simplified commercial calculation is:
payable metal = recovered metal × payable fraction
Rank #3
- 【Great Compatibility】This Katerk 1/4 inch hex shank bit holder is specifically designed for 1/4 inch hex shank drill bits. It's compatible with most 1/4 fast hex handles, hex sockets, various electric screwdrivers, and handheld screwdrivers. The bit holder makes it a valuable addition for any handyman.
- 【Secure and Safe】Built with a secure backup nut design, each drill bit holder securely locks onto your bits, ensuring they stay firmly in place. Additionally, our bit holder incorporates a high-quality steel ball rolling design that holds up to several kilograms of weight, ensuring your various drill bits don't fall off.
- 【Easy One-Handed Operation】The bit holder for impact driver allows you to change bits single-handedly, simplifying your workflow. Its multi-color design further allows for quick identification of the drill bit you need.
- 【Compact and Convenient】Thanks to its compact size, this 1/4 inch bit holder is easy to carry around. The bit holder allows for easy attachment to various tools, making this a convenient addition to your construction accessories. The Katerk bit holder is cast from high-quality alloy material, promising a long product lifespan. Despite its rugged strength, the bit holder remains lightweight, making it portable.
- 【Cool Christmas Gift For Men Stocking Stuffers】 This screwdriver bit holder, driver bit holder, impact bit holder, can be given as a gift to your loved one, especially for anyone involved in construction or electrical work. It's a must-have for stocking stuffers for men and women, tools gifts for dad, tech gadgets for men, gifts for dad, gifts for him, gifts for husband, gifts for boyfriend, cool gadgets for men, and cool gifts for dad.
The result can then be valued using the price assumption and reduced by treatment and refining charges, freight, royalties and other costs specified in the economic model. Payability is contract-specific; it should not be inferred from a generic industry percentage.
What reported production numbers look like in practice
Published figures demonstrate why the basis must accompany every number. Agnico Eagle’s 2025 Annual Information Form reported production from 2.8 million tonnes of ore of 344,555 ounces of gold, 671,148 ounces of silver, 8,446 tonnes of zinc and 2,431 tonnes of copper (2025 filing). These are product figures associated with a stated ore throughput, not a universal conversion factor for every mine.
The same filing gives recovery assumptions used in one reserve calculation: 94.6% for gold, 77.4% for silver, 83.8% for copper and 66.9% for zinc. They are assumptions for that calculation, not guarantees that every year or ore type will achieve those rates.
Wheaton Precious Metals reported 5,100 tonnes of molybdenum in 2025 versus 8,100 tonnes in 2024 and attributed the change to lower recovery (annual information form). The example illustrates that production can fall even when geological tonnes are available if the processing response changes.
Understand how resources become reserves
A Mineral Resource is a concentration or occurrence with reasonable prospects for eventual economic extraction. A Mineral Reserve is the economically mineable part of a Measured and/or Indicated Resource after a pre-feasibility or feasibility study applies modifying factors. Under SEC S-K 1300 definitions, the modifying factors include mining, processing and metallurgy, infrastructure, economics, marketing, legal, environmental, social and governmental matters (SEC definitions).
| Classification | Meaning in an economic mine plan | Confidence and use |
|---|---|---|
| Inferred Resource | Material supported by limited geological evidence and sampling. | Too uncertain to convert to a reserve under S-K 1300 and cannot establish economic viability in that framework. |
| Indicated Resource | Material with enough geological confidence to support mine planning and economic evaluation. | Can support a Probable Reserve after modifying factors are applied. |
| Measured Resource | Material with the highest level of geological confidence in the resource categories. | Can support a Proven Reserve, or in some cases contribute to a Probable Reserve depending on the modifying factors and study. |
| Probable Reserve | Economically mineable material, generally derived from an Indicated Resource and in some cases a Measured Resource. | Lower confidence than Proven, but sufficient to demonstrate economic viability. |
| Proven Reserve | Economically mineable material derived from a Measured Resource. | Highest confidence in the geological and modifying-factor assumptions. |
The SEC-based definitions are reproduced in a company filing at this source. Categories express confidence; they are not forecasts of annual output.
Rank #4
- Long Nib and Deep Hole Marker: Our mechanical carpenter pencil with 45mm nib is designed for easy marking of deep holes or narrow areas. These construction pencils are the great choice for woodworking tools, construction tools, carpenter tools, contractor tools, wood carpentry tools and architect tools
- Extra Refills in 2 Colors for Versatile Marking: The construction mechanical pencil comes with 12 extra 2.8mm refills, including 6 red and 6 black refills. The black refill is suitable for light surfaces, while the red wax is perfect for dark surfaces. Our carpenter mechanical pencil makes sure that you'll have an ample supply for extended use
- Built-in Sharpener: Our construction pencil comes with a built-in sharpener to ensure the mechanical pencil tip is always sharp and ready for use. Never buy an extra pencil sharpener again. A great tool for any woodworker pencil, contractor pencils. The refill can easily be extended or retracted with a simple click of the pencils mechanical, allowing you to work more efficiently and accurately
- Portable Clip Design: Our deep hole construction pencil features a portable clip design, easy to carry and attach to your pocket or tool box, so that you can keep the carpenter pencils mechanical close at hand, making it a convenient tool to have on the go. Great gifts choice for carpenters
- Stronger Pencil Lead: The black refills are made of lead, sturdy and smooth. The red refills are made of wax, clear and light. These marking pencils are much thicker and stronger than normal pencils during the marking process of construction work, suitable for various surfaces, such as glasses, metal, boards, floors, walls, furniture, etc. The written marks can be easily wiped with a wet paper towel when needed
Why a reserve cannot be calculated by applying a percentage to a resource
JORC rejects the practice of taking a resource tonnage and multiplying it by a recovery or conversion factor without a mine design and mine plan. The proposed operation must be technically achievable and economically viable, with a schedule showing how material will be mined, processed and sold. JORC also says that processing recovery factors are important information and should be included in public reports. The requirements appear in the JORC Code 2012.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.“An ‘Ore Reserve’ is the economically mineable part of a Measured and/or Indicated Mineral Resource.”
Cut-off grade connects geology to economics
Cut-off grade is the threshold used to decide whether a block enters the economic estimate. In polymetallic or concentrate operations, the equivalent concept may be a net-smelter-return (NSR) cut-off value. Material above the threshold is not automatically profitable in isolation; it is material that meets the model’s stated assumptions after the relevant costs and recoveries are considered.
Typical cut-off inputs
- Commodity prices and exchange-rate assumptions.
- Mining, processing and general-and-administrative costs.
- Metallurgical recovery and concentrate or product payability.
- Royalties, treatment and refining charges, freight and penalties.
- Sustaining capital and closure or reclamation obligations where included in the economic test.
- Mining method, dilution, mining recovery and practical plant constraints.
Changing any of these can move tonnes into or out of the reserve. Agnico Eagle’s 2025 filing ties reserve tables to stated price assumptions, recovery assumptions and mine-specific cut-off values; the filing reports the recovery percentages listed above (Agnico Eagle 2025 AIF). A reserve number without its cut-off and price basis cannot be compared fairly with one built on different assumptions.
Why annual production is not reserve tonnage divided by mine life
Reserve tonnage is constrained by what can be mined and processed economically, while annual production is constrained by the sequence and capacity of the selected mine plan. Early years may have pre-stripping, ramp-up or development; later years may draw lower-grade stockpiles. A mill expansion, maintenance shutdown, tailings capacity, water supply or blending requirement can change plant feed even when reserve tonnes remain unchanged.
For that reason, an annual schedule normally reports both mined tonnes and processed tonnes. A stockpile can make plant feed higher than current ore mining in one year and lower in another. Grade can also differ between the mine schedule and the plant schedule because the plant is blending material from several periods.
Best Value
- Milwaukee Ink all Fine Point Marker, Black, 4 Per Pack
- 4 per pack Features Clog Resistant Marker Tip Writes through Dusty, Wet and Oily Surfaces Durable Marker Tip for Writing on Concrete, OSB and Rough Surfaces
- Clog resistant tip writes on dusty, wet and oily surfaces and is optimized for rough surfaces such as OSB, cinderblock and concrete
- Hard hat clip- attaches for easy access
- Quick dry time with reduced smearing and marking
A practical calculation workflow
- State the reference point. Label every figure as ROM, ore delivered, plant feed, concentrate, doré, cathode or payable metal. State whether tonnes are dry or wet.
- Lock the units. Convert percentages, grams per tonne, kilograms, tonnes and ounces before multiplying. Record the moisture basis and rounding convention.
- Prepare the mine schedule. For each year, list ore, waste, grades, dilution, mining recovery and stockpile movements.
- Prepare the plant schedule. Show feed tonnes and grades separately when stockpiles, blending or capacity make it different from mine output.
- Calculate contained metal. Multiply scheduled ore tonnes by head grade in consistent units.
- Apply recovery. Use the recovery assumption appropriate to each ore type, grade range or throughput condition.
- Apply commercial terms. Convert recovered metal to payable metal using contract payability, then account for treatment, refining, transport, penalties and royalties in the economic model.
- Test the reserve. Apply the cut-off, mine design, infrastructure, schedule, costs, prices and other modifying factors in a pre-feasibility or feasibility study.
- Document confidence. Identify whether the result is a Proven or Probable Reserve, the resource category supporting it, the reporting code and the competent or qualified person sign-off required in the jurisdiction.
How to compare two mine reports without mixing unlike numbers
Before comparing production or reserves, place these attributes side by side:
- Reporting reference point and product definition.
- Dry versus wet tonnes and the moisture adjustment.
- Ore mined versus ore processed or plant feed.
- Head grade, contained metal and recovered metal.
- Recovery basis: test work, historical plant performance or a domain/grade/throughput model.
- Payability, treatment and refining charges, transport and penalties.
- Cut-off grade or NSR value and the commodity-price assumptions.
- Reserve category, mine method, dilution and mining-recovery assumptions.
- Study level, jurisdictional reporting code and competent- or qualified-person sign-off.
A higher reported metal figure may simply reflect a different reference point or payability convention. A larger reserve may reflect a lower cut-off, a different price deck, a changed mine design or a reclassification rather than the discovery of new geological material.
Common interpretation errors and their fixes
Calling contained metal “production”
Contained metal is in the feed before processing losses. Fix the label and apply recovery before calling it recovered production.
Free tools Windows power users keep installed
One-click scans. No signup required.
Using concentrate tonnes as metal tonnes
Concentrate includes valuable metal plus other constituents. Use the concentrate grade to calculate contained metal, then apply payability.
Applying one recovery percentage to every year
Recovery can vary with ore type, grade and throughput. Use the schedule’s domain, grade-bin or throughput assumptions where available.
Ignoring stockpiles
Stockpiles decouple mining and processing by year. Show opening stockpile, additions, withdrawals, grades and closing balance.
Comparing reserves without economic assumptions
Cut-off, price, cost, recovery and payability assumptions determine which blocks are economic. Compare those inputs before comparing reserve tonnes.
Treating an inferred resource as a reserve
Inferred material is too uncertain for reserve conversion under S-K 1300. Keep it separate from the economically demonstrated reserve.
The Bottom Line
Annual production is the scheduled flow from mine to plant to sale: tonnes multiplied by grade, reduced by processing recovery and, where applicable, by contractual payability. Reserves are the economically mineable part of Measured and/or Indicated Resources after a mine plan, cut-off assumptions and modifying factors demonstrate technical and economic viability. Always read the reference point, units, recovery basis and economic assumptions before comparing a mining number.