The Golden Gate Bridge’s final seismic retrofit phase, Phase 3B, began in early 2026. The work spans the bridge’s towers, side spans, main suspension span and south tower pier, with construction planned across 2026–2036. The first of two contracts covers the towers and side spans and is expected to take about six years.
What Phase 3B will strengthen
The Golden Gate Bridge, Highway and Transportation District says towers and side spans are being addressed first because they are less flexible than the main span. The program includes work on the main suspension span, both side spans, both towers and the south tower pier.
- Install large steel plates at tower bases and strengthen tower trusses.
- Replace expansion joints at roadway-to-tower and roadway-to-pylon interfaces so the structure can move in three dimensions.
- Reinforce lateral bracing and retrofit 255 roadway floor beams.
- Add 38 energy dissipation devices intended to reduce seismic energy transferred to the bridge.
- Repaint the South Tower above the roadway.
The District describes the purpose as improving the bridge’s ability to remain in service after a major disaster and support regional response and recovery. This is a project objective, not a guarantee that the bridge will be undamaged or remain open after an earthquake. District Phase 3 project details
Schedule: the whole phase and the first contract
The District’s current schedule places Phase 3B broadly in 2026–2036. Its first construction contract, awarded in October 2025, is expected to take about six years; that duration applies to only part of the two-contract program, not the entire phase.
Recommended Free Tools
#1 Best Overall
- BUILD A REAL DA VINCI INSPIRED BRIDGE Construct a working model based on Leonardo da Vinci’s famous self-supporting bridge design. This hands-on wooden STEM kit demonstrates real engineering principles through an engaging and rewarding building experience.
- EDUCATIONAL STEM LEARNING EXPERIENCE Explore concepts in engineering, architecture, physics, and history while building. Great for students, hobbyists, makers, homeschool projects, classroom activities, and anyone interested in mechanical design.
- APPROXIMATELY 1 HOUR BUILD TIME Designed to provide an immersive yet manageable project experience. The completed bridge makes an impressive display piece and conversation starter once assembled.
- HIGH-QUALITY WOODEN MODEL KIT – AGE 14+
- Made from durable precision-cut wood components with detailed illustrated instructions. A thoughtful gift idea for teens, adults, engineers, history enthusiasts, and STEM lovers.
The first contract covers the North and South Towers and the North and South Side Spans. A May 21, 2026 District engineering status report records an award to Halmar International, LLC for $863,949,008. The District says the phase is funded with federal, state and District funds. Phase 3 schedule and scope · May 21, 2026 engineering status report
Overnight lane closures and what drivers should expect
A District notice dated October 2, 2026 says weekday overnight lane closures for retrofit construction began Monday, October 5. Closures are approximately 9 p.m. to 5 a.m., Monday through Friday. The bridge remains open in both directions, with at least one travel lane in each direction kept open. Drivers may encounter slower traffic and delays near construction zones. Work may be canceled because of traffic or weather and does not take place on holidays. Check the District’s seismic retrofit updates for notices before traveling.
Rank #2
- Build 20 different models that each teach about force, load, compression, tension and more
- Over 285 interchangeable building pieces
- Includes 36-page, illustrated experiment manual and Assembly guide
- Skill level: Intermediate
Why the retrofit matters—and what it cannot promise
The District’s seismic overview says earlier retrofit phases reduced the bridge’s collapse risk in a major earthquake, but significant damage to the main suspension bridge remained a concern until the full retrofit is complete. Its design criteria include a moderate earthquake defined as a 10% chance of exceedance in 50 years, or 0.46g, and a maximum credible earthquake defined as a 1,000-year return-period event, or 0.65g. The District compares the latter with the 1906 San Francisco earthquake, which it lists as magnitude 8.3 on the Richter scale.
These are design criteria, not predictions of performance or assurances that the bridge will be undamaged or open after any particular earthquake. The District says the bridge can safely withstand a large earthquake today; the final phase is intended to strengthen post-disaster operability and support regional recovery. District seismic retrofit overview
Do these 3 things before closing this tab:
1Repair Windows errors before they cause bigger problems2Fix the driver behind crashes, sound loss and screen glitches3Clear out junk files and repair common Windows errorsRank #3
- HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up.
- NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs.
- PREMIUM SERIES GOLDEN GATE BRIDGE - 2.5 Sheet Model with a moderate difficulty level. Once assembled, dimensions are 14.45 L x 0.94 W x 2.95 H inches. 1:7535 Scale.
- FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions
- HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all.
How the current schedule differs from earlier estimates
A December 2022 District announcement reported a $400 million Federal Highway Administration Bridge Investment Program grant and a then-current construction budget of $879 million. At that time, construction was expected to start in late 2024 and finish in 2029. Those were 2022 estimates; the District’s later project information reflects the phased work and the current Phase 3B period of 2026–2036. Current Phase 3 information · December 29, 2022 grant announcement and earlier estimates
Quick Recap
Best Value
- HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up
- NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs
- BROOKLYN BRIDGE – 2 Sheet Model with a moderate difficulty level. Once assembled, dimensions are 5.39"L x 0.91"W x 1.97"H (13.7 x 2.3 x 5 cm)
- FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions
- HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all
Rank #4
- THE WOODEN SYDNEY BRIDGE 3D MODEL KIT COMES WITH UNIQUE DESIGN YOU WILL LOVE - Be proud to display your assembled Sydney 3D Bridge Wood Puzzles and share your love for iconic landmarks in Sydney Australia. This wooden 3d puzzle bridge makes a model kit for kids who loves architecture model kits, bridge building kit, and 3D building sets for adults. Ideal for kids to start getting interested in building bridges or young engineers building kit.
- THE SYDNEY 3D BRIDGE WOODEN MODEL KIT PUZZLE IS FOR EVERYONE WHO LOVES ICONIC PUZZLES - The Sydney Bridge 3D wooden puzzles for adults and kids is a craft kit to build for those who love playing mind games. Parents can gift 3D wooden puzzles, or architecture model building like this Sydney Bridge to improve mental speed and problem solving skills of their kids. A good bonding project for family, or as kids architecture kit project for school.
- INCLUDED WITH THE PURCHASE OF THE 3D BRIDGE WOOD PUZZLE KIT - Includes 1 Sydney 3D Bridge Wood Craft Puzzle Decor Model Kit with 55 unfinished natural wood puzzle pieces, manual, and 1 paper for sanding the edges. This DIY puzzle bridge building kit for kids can be painted or colored for a more personalized look. Most parts doesn't require glue as the pieces are interlocking. It measures 16.54Lx4.13Wx5.31H inches. Paint and Glue not included.
- HIGH-QUALITY WOODEN PUZZLES FOR ADULTS AND KIDS - This miniature iconic 3D Puzzle Sydney Bridge Wood Model Kit is made of high-grade 3mm natural wood. All wooden puzzle pieces are laser cut and sanded thoroughly to ensure smooth edges. This bridge building educational 3D puzzle feature realistic details of the Sydney bridge, like its arch and towers. Playfully paint this architecture puzzle toy bridge model kit for kids after assembling.
- IDEAL USE FOR THE SYDNEY 3D BRIDGE ADULTS AND KIDS WOOD BUILDING KITS - Challenge your kids or even yourself to build this DIY 3D wooden puzzle Sydney bridge. A perfect addition to your kids wood project, wooden building kits for adults, or wooden Australia puzzles collection. This architecture model building kit puzzle toy can help kids develop their skills in building wood bridge, raise their IQ, problem solving, and shape recognition.
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.