Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →As of Cardinal News’ October 5, 2026 report, construction of AVAIO Digital’s Project Hercules data center campus in Appomattox County had not started. Garet Bosiger, chair of the Appomattox County Economic Development Authority, said construction was expected to begin by the end of 2026, with a building period of about 10 years. Those are forecasts, not completed milestones.
What is planned for the Appomattox site?
AVAIO Digital identifies the project site as 267 Industrial Park Lane in Appomattox and describes it as a 436-acre property. Cardinal News reported that the county’s Economic Development Authority signed an agreement with AVAIO in 2024 to begin development of a $3 billion campus. The project page and report describe a large, phased development; they do not establish that the full campus is already built or operating.
AVAIO says the campus is planned to include 1,000 megawatts (MW) of total baseload power, split between 300 MW of grid power and 700 MW of behind-the-meter baseload. The developer says initial power is expected in 2027. These are AVAIO’s stated plans, not evidence that this capacity has been delivered or that the full transmission expansion is finalized. AVAIO Digital’s Appomattox campus page
How much electricity is available now, and how much is planned?
In the October 2026 report, Appomattox County Administrator Susan Adams said 50 MW was available at the site without additional energy infrastructure. She said AVAIO was pursuing increased electrical transmission capacity from Central Virginia Electric Cooperative and Dominion Energy. That present availability is distinct from AVAIO’s longer-term 1,000 MW configuration; the sources do not say when the full planned capacity will be available.
Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchWindows Errors? Fix Them Before They Spread
Repair common Windows errors and clear accumulated junk for a smoother, more stable PC - no reinstall needed.Free scan · no reinstall#1 Best Overall
- Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
What water and wastewater service is committed?
Town Manager Michael Campbell said the Town of Appomattox would provide up to 45,000 gallons of water and 45,000 gallons of wastewater service per day. As reported by Cardinal News, the town said it had capacity to meet that commitment, and AVAIO would pay utility charges like other customers.
Any request beyond the town’s existing commitment, or infrastructure needed to provide additional service, would require further review and approval, along with agreements addressing capacity, infrastructure, financing and associated costs. The reported daily amounts therefore describe the current commitment, not an established allowance for later expansion.
Rank #2
- Save valuable floor space: 12U wall mount server cabinet Dimensions: 24.25" H x21.65" W x17.72" D. MAXIMUM MOUNTING DEPTH is 14.2".
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access; Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punchout panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
Which approvals are complete, and what remains in progress?
Adams told Cardinal News that AVAIO had submitted the necessary permit applications and that the Virginia Department of Environmental Quality had approved the project’s stormwater management plan. She also said attorneys were finalizing the performance-agreement language. The report does not describe all permit applications as approved or the performance agreement as complete.
County zoning treats data centers as industrial manufacturing, permitted by right in the county’s two industrial districts. According to Cardinal News, the project therefore did not need a public hearing or special approval from the Board of Supervisors to move in.
Rank #3
- Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
- Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
- Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
- Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
- Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose
What jobs are projected?
Bosiger estimated at least 500 construction jobs during the expected building period. He also said the completed campus is expected to contain six or seven data centers, each employing 25 to 40 people, in addition to sitewide roles such as security and landscaping. These are estimates reported in October 2026, not confirmed hiring totals or guarantees.
What concerns have local residents raised?
Cardinal News reported that a petition started in March had close to 300 signatures. Signers raised concerns about limited resident input, changes to the local landscape and environmental impacts. The report also described local debate over potential tax and employment benefits alongside concerns about land, water, electricity and environmental effects. The petition and coverage do not establish that these views represent a measured majority of county residents.
Quick Recap
Sources
- Cardinal News, October 5, 2026 — construction timing, local utility and approval information, job estimates and community discussion.
- AVAIO Digital’s Appomattox, Virginia Campus page — developer-stated site acreage, power configuration and initial-power target.